Professional Documents
Culture Documents
Meeting
BEKAPAI - 3
Surface Facilities Modification and
Dogleg Installation (EPCIC)
Contract No. 4500010835
Date : 23 July
2021
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
1. Introduction & Meeting Objective
2. Project Overview / Scope of Work
3. Project Team & Organization Chart
4. Management Commitment
5. HSE Commitment & Objective
6. QA/QC Commitment & Objective
7. Engineering & Procurement
8. Project Milestones
9. Project Strategy, Schedule & Area of Concern
10. Project Deliverables & RFQ Register
11. Project Risks
12. Q&A
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
4500010835
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
C
ontract No. 4500010835
MWP - BH MWP - BE
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
WORK PACKAGES
WP 4. Mobilization / Demobilization
WP 7. Provisional Sum
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Structure
Structural WORK for BE Structural WORK for BH
CP Guide Frame CP Guide Frame
Boat Landing Support Frame Boat Landing Support Frame
Boat Landing & Conductor Protector Boat Landing & Conductor Protector
V-Shape V-Shape
Riser Protector Riser Protector
Sump Deck Platform Weather Shelter
Close Drain Pump / Drum Platform Sump Deck Platform
Weather Shelter Close Drain Pump / Drum Platform
Wellhead Deck Extension Wellhead Deck Extension
Manifold Deck Extension Manifold Deck Extension
Access Platform Valve Access Platform
Vent Stack / Boom Support FG Scrubber Access Platform
E&I Equipment Shelter Vent Stack / Boom Support
Monorail E&I Equipment Shelter
Jacket Reinforcement Monorail
Deck Reinforcement Jacket Reinforcement
Temporary Laydown Area Deck Reinforcement
Temporary lifting frame Temporary Laydown Area
Temporary lifting frame
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Electrical
Electrical WORK for BE Electrical WORK for BH
Installation THeG (7 pack) Installation THeG (7 pack)
Installation isolating switch panel Installation isolating switch panel
Installation 24VDC main distribution board Installation 24VDC main distribution board
Installation 24VDC main battery Installation 24VDC main battery
Installation 24VDC man battery CB panel Installation 24VDC man battery CB panel
Installation JB & plug external power Installation JB & plug external power
Installation 400VAC main DB & battery charger Installation 400VAC main DB & battery charger
Installation 400/230 VAC lighting transformer Installation 400/230 VAC lighting transformer
Installation 230VAC DB lighting Installation 230VAC DB lighting
Installation navigation aids control panel Installation navigation aids control panel
Installation 12VDC navigation aids battery Installation 12VDC navigation aids battery
Installation 12VDC navigation aids battery CB panel Installation 12VDC navigation aids battery CB panel
Installation 24VDC general alarm panel including siren & Installation 24VDC general alarm panel including siren &
flashing light flashing light
Installation 24VDC general alarm battery Installation 24VDC general alarm battery
Installation 24VDC general alarm battery CB panel Installation 24VDC general alarm battery CB panel
Installation radar beacon, fog detector & photocell Installation radar beacon, fog detector & photocell
Installation lighting & junction box Installation lighting & junction box
Installation welding & power socket outlet Installation welding & power socket outlet
Installation grounding system Installation grounding system
Installation cable & tray Installation cable & tray
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
4. Management Commitment
Objectives
Contractor will adopt the following principles in all dealings with COMPANY and other external
parties:
Provide an Incident and Injury Free, (IIF) workplace
Maintain an open and honest culture
Ensure a high level of customer satisfaction
Be proactive in the identification and management of risks and opportunities
Following principles set out below are the critical elements to ensure the
project
objectives are met:
Engineering study and design against COMPANY Project Specifications.
Implementation of HSE Policy and Quality Policy
Effective communication
Assignment of qualified and experienced personnel familiar with Project requirements
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
LAGGING INDICATOR
2 FATALITY (FAT) 0
8 ENVIRONMENTAL DAMAGE 0
9 MATERIAL DAMAGE 0
10 LTIF 0
11 TRIR 0
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
HSE Program
HSE MEETING
EMERGENCY DRILL
SAFETY
1 Medivac Evacuation / covid -19 2
2 Gas leak 1
3 Fire / Explosion 2
4 Oil Spill 2
5 Electrical Shock 2
6 Radiography Case 1
7 Falling from at Height
1
8 Man Oveboard 1
9 Demonstrans Case 1
10 Handling Criminal Case 1
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
HSE REWARD
1 ASTA Award Monthly Quiz with 3 winners every Month
Best Performance = 1 Winner every Month
2 BEKAPAI Award Monthly
Best or Best CerMat = 1 Winner every Month
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
MCU Program
PERFORM ISSUED
VALIDATED
1 2 BY DOD
3 MEDICAL
MCU PASS
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
PPE Mandatory
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
C P Y Personnel, C T R L O C A L W O R K E R
VISITOR Wo r ke r & S ub Cont.
from out K L AT I M Area
R e g i s t r a ti o n C O V I D - 1 9 C T R f o r m
S WA P R e a c t iv e Do
T E S T S e nd To Hospital
A N T I G E N
Not PCR( S WA B TEST
Enter
at Yard
N o n r e a c ti v e
Wo r k i n g at Ya r d
N e g a ti v e P o s i ti v e
Protokol C O V I D -19
• Bo dy Check Temperature Stay at h o m e
• Use Mask minimum 14 Days
• Regular H an d Washing before return to work Covid -19
• Physical Distance
Medical
T re a t m e nt
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
To conduct disinfectant every Saturday (offices, working and public area and accommodation for
CPY personnel and receiving of the materials
Regular checking personnel body temperature with thermo gun
Wearing mask , physical distancing, and regular hand washing
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Flow Chart Offshore Activity
C T R s u b m i t m a n p o w e r list i n c l u d e c r e w B a r g e ,
Tu b Boat, Cr e w boat
(Mapping Manpower Arrangement )
)
O n l i n e r e g i s t r a ti o n D a i l y Q u a r a n ti n e F o r m ,
D - 1 4 ( h tt p s : / / s i a g a c o v i d 1 9 . p h m - p e r t a m i n a . c o m )
O n l i n e r e g i s t r a ti o n C O V I D - 1 9 S c r e e n i n g
F o r m , D - 3 ( h tt p s : / / s i a g a c o v i d 1 9 . p h m - p e r t a m i n a . c o m )
P o siti ve
Swab
te st S e n d to Hospital PCR( S WA B TEST
Antigen
N e g a ti v e P o s i ti v e
Stay at h o m e
N e g a ti v e m i n i m u m 14 Days
before return to w o r k
C O V I D -19
MEDICAL
TREATM E NT
P R E PA R AT I O N
O F FS H OR E ACTIVITY
D -1 All workers should b e o n
P r e p a r a ti o n the board AW B P o siti ve
A ft e r 1 5 D a y Swab
Tes t
a n ti g e n
W o r k i n g at Si te
N e g a ti v e
O n Line
h tt p s : / / d o c s . g o o g l e . c o m / f o r m s / d / e / 1 F A I p Q L S e D L N I 8 0 8 d p 9 H y j X n 6
puI0Tm T Fw AK JznopY 8Wj YCW4Jfa Mx4w /v ie wfor m
For daily control 18.00 s/d 24.00
O n line F o r m P el a p o ra n Ko nt a kE ra tH a r ia n S P S
, ( h tt p s ; / / f o r m s . g l e / w q Z o L N R 6 w D a S y n o 3 9 )
UntukKontrolHarian 18.00 s/d 24.00
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Quality Objective
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Scope of Work
The particular Project scope of works for Engineering:
Provision of management services and supervision
Interface management
Pre-engineering survey
Perform material take off verification
Endorsement of engineering document which have been supplied by COMPANY
Detail engineering for Electrical and ICSS integration
Construction, installation and hook-up engineering
Pre-commissioning engineering
Commissioning engineering
As-built drawings and Final Documentation
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Engineering Strategy
Strong teamwork with maintain the good behavior 1. Immediate deploying engineering
to deliver and complete the project team & set up the infrastructure
2. Performing the site survey with
Dedicated project team, in term of quality and qualified personnel
experience to manage all elements of the scope of 3. Strengthen the endorsement
work period
4. Early identification for any
Intensify engineering team from the early phase to
discrepancy data
review COMPANY document during endorsement 5. Promoting joint review, especially
period, and during the detail / construction for Electrical, Instrumentation and
engineering with reference to COMPANY or Project ICSS
Particular Specification 6. Selected the capable manpower
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Procurement Support
Engineering team has responsibility to ensure the selected purchased item / materials are met with COMPANY
Standard / Specification.
Material Take Off
Verify the material supplied by COMPANY, therefore Contractor to perform the review and re-calculate the
required materials
Interfaces Plan and Register
Facilitate agreements between project team or with other stakeholders regarding roles & responsibilities, timing
for providing interface information and identification of critical interfaces early in the project through a
structured process
Risk Register
This register will include all information about each identified risk, such as the nature of that risk, level of risk,
who owns it and what are the mitigation measures in place to respond
Constructability, Maintainability and Operability Review
Contractor Engineering Team with COMPANY’s Project Team shall consider as constraint for the
constructability,
maintainability and operability of the facilities
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Management of Change
All potential design changes shall be reviewed and approved by authorized personnel before the
implementation since design change may affect to other issue
Technical (Engineering) Query
All technical questions, requests for information, clarifications regarding the Contract, specifications, drawings,
scopes of works and other COMPANY issued documents will be raised and actioned in accordance with the
procedure of Technical Queries (TQ).
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Procurement
Vendor Management and Procurement Plan
Procurement shall control and monitor all aspects of the procurement process and
provide resources to
procure, expedite, inspect and transport all materials and equipment.
Item of Concern
Purchasing
Purchasing personnel shall ensure that all goods, supplies, and inventory needed for the project are ordered
and kept in stock, as well as control inventory levels and costs associated with purchasing the items
Refer to COMPANY Approved Vendor List
Unprice Material to be provided for Bekapai 3 (Attachments\Unprice Material.pdf)
Subcontracting
Subcontracting personnel has task to select subcontractor to perform a specific task as part of the overall
project and is normally paid for services provided to the project by the originating general contractor.
Subcontracting activity for this project such as, but not limited to the following:
• ICSS Integration
• Marine Warranty Surveyor ; Tugs and Barge
• Underwater (diving) work
• NDT etc.
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
8. Project Milestones
Effective date Effective date
15 June 2021 15 July 2021
No Contract Milestone (based on ITB) (Actual) Remarks
Date / Status Date / Status
Project Schedule
Project Schedule : Project Schedule.pdf
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Manpower Loading
Monthly Manhour
70,000
60,000 57,300 57,300 57,300 57,300 57,300 57,300 57,300 57,000
54,600
49,500
50,000
41,400
40,000
29,400 30,300
30,000 27,000
20,100
20,000
9,900 10,800
9,000
10,000
-
Month - 1
Month - 2
Month - 3
Month - 4
Month - 5
Month - 6
Month - 7
Month - 8
Month - 9
Month - 10
Month - 11
Month - 12
Month - 13
Month - 14
Month - 15
Month - 16
Month - 17
Month - 18
Note : Exclude marine spread personnel
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Manpower Loading
600,000 578,700
521,400
500,000 464,100
406,800
400,000
349,500
292,200
300,000
234,900
200,000 180,300
130,800
89,400
100,000 59,100
18,900 29,700
9,000
-
Month - 1
Month - 2
Month - 3
Month - 4
Month - 5
Month - 6
Month - 7
Month - 8
Month - 9
Month - 10
Month - 11
Month - 12
Month - 13
Month - 14
Month - 15
Month - 17
Month - 18
Month - 16
Note : Exclude marine spread personnel
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Phase 5:
1. Remote activity for Step #3 MWP BE well connection.
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Underwater Work
Particularly for the underwater work i.e. dogleg installation; following tools
shall be
available:
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
1.All field instrument shall 1.All field instrument, PLC, 1.All field instrument shall 1.All field instrument, PLC, 1.All software modification
be ready WHCP & Electrical be ready WHCP & Electrical shall be ready before
2.Piping TP-2 ~ 9 shall be equipment including the 2.Piping TP-1 ~ 10 shall be equipment including the upload
ready including the cabling etc shall be ready ready including the cabling etc shall be ready
isolation 2. Piping TP-1, TP-11 ~ 25 isolation 2.Piping TP-1 ~ 4, TP-21 ~
3.Piping TP-22 ~ 26 shall shall be ready including 31 shall be ready
be ready including the the isolation including the isolation
isolation
1. Modification existing 1.Tie-in tubing well control 1.Tie-in cable for new field 1.SAT & loop checking 1.Upload software to
WHCP to existing well BH-3 instrument to existing JB new WHCP & FGS Panel existing PCS, SSS and
2.Modification existing 2.SAT & loop checking 2.Replacement electronic via existing radio HMI
wireless gateway new WHCP & FGS Panel level switch system 2.Communication
3.Tie-in Instrument Gas via existing radio 3.Tie-in fusible plug 2.Perform tie –in piping (interface) test between
and Vent System to new system 4.Perform tie –in piping TP-1 ~ 4, TP-21 ~ 31 BG, BH, BE and BA
field instrument 3.Perform tie –in piping TP-1 ~ 10
4. Tie-in fusible plug TP-1, TP-11 ~ 25
5. Perform tie –in piping General Notes :
TP-2 ~ 9 1. Window period shall be decided under coordination between COMPANY
6.Perform tie –in piping and EPCIC Contractor
TP-22 ~ 26 2. Shutdown requirement and scenario to be confirmed during Construction
phase
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Bayu Constructor
Accommodation Work Barge (AWB) 1
Bayu Laut
Logindo Synergy
Anchor Handling Tug (AHT/S) 1
Logindo Braveheart
Spearhead
Crew Boat 1
Spirit
Megawati X
Tug Boat 1
Megawati XI
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Contract Status
Completed
Contract Sign off (SC19B, SC23)
Performance Bonds
Pending
Contract Package (initial) Awaiting document from PHM
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Area
No of Concern / Highlight Issues Description Remarks
No Description Remarks
AOC shall be identified into 2 phases; Before Rig-In and After Rig-In as considering for
11 the Step #3 of Well Connection
Project Milestone shall be revised based on actual contract effective date; including
12 for KD 7A and KD 7B
Target for well shutdown at active well on BH shall be determine to minimize the well
13 shutdown duration
14 The existing positive isolation shall be informed to Contractor; subject for site survey
15 POB Management (crew change management) for offshore campaign
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
MDR : MDR.pdf
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
PIPING MATERIAL
No Description Target PO Delivery Time ROS
1 Pipes 08-Aug-21 12 wks 26-Nov-21
2 Flanges & Blind Flanges 10-Aug-21 16 wks 25-Dec-21
3 Manual Valves (out of LLI by CPY) 21-Aug-21 34 wks 20-Apr-22
4 Studbolts 26-Aug-21 10 wks 07-Nov-21
5 Fittings 26-Aug-21 12 wks 23-Nov-21
6 Gaskets 30-Aug-21 10 wks 11-Nov-21
7 Spacer Ring 26-Aug-21 12 wks 21-Nov-21
8 Spade & Spacer 26-Aug-21 12 wks 21-Nov-21
9 Spectacle Blind 24-Aug-21 12 wks 21-Nov-21
10 U-Bolts and Support Clamp 10-Sep-21 16 wks 04-Jan-22
11 Miscellaneous Items 16-Sep-21 10 wks 28-Nov-21
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
PIPELINE MATERIAL AND PASSIVE FIRE PROTECTION MATERIAL
SPECIALTY ITEMS
No Description Target PO Delivery Time ROS
1 Corrosion Coupon 09-Nov-21 12 wks 20-Feb-22
2 Quick Connection 09-Nov-21 12 wks 20-Feb-22
3 Y - Strainer 09-Nov-21 12 wks 20-Feb-22
4 Liquid Trap Drain 09-Nov-21 12 wks 20-Feb-22
5 Injection Quill 09-Nov-21 12 wks 20-Feb-22
6 Flame Arrestor 25-Sep-21 20 wks 03-Mar-22
7 CS Flange with CRA Overlay 25-Sep-21 22 wks 17-Mar-22
8 Sand Probe 09-Nov-21 12 wks 20-Feb-22
9 Bird Screen 02-Nov-21 6 wks 02-Jan-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
ELECTRICAL MATERIAL
No Description Target PO Delivery Time ROS
1 12 VDC Nav. Aids Battery 17-Aug-21 32 wks 17-Apr-22
2 12 VDC Nav. Aids Battery Circuit Breaker Panel 17-Aug-21 32 wks 17-Apr-22
3 230 VAC Lighting Distribution Board 09-Sep-21 18 wks 01-Feb-22
4 24 VDC General Alarm Battery 26-Aug-21 32 wks 12-Apr-22
5 24 VDC General Alarm Distribution Board and Battery Charger 09-Sep-21 18 wks 01-Feb-22
6 24 VDC General Alarm Battery CIrcuit Breaker Panel 17-Aug-21 32 wks 17-Apr-22
7 24 VDC Main Battery Circuit Breaker Panel 09-Sep-21 18 wks 01-Feb-22
8 24 VDC Main Battery 17-Aug-21 32 wks 17-Apr-22
9 400 VAC Main Distribution Board and Battery Charger 09-Sep-21 18 wks 01-Feb-22
10 24 VDC Main Distribution Board 09-Sep-21 18 wks 01-Feb-22
11 400/230 VAC Lighting Transformer 24-Aug-21 20 wks 30-Jan-22
12 400 VAC Power Cable Reel 24-Aug-21 20 wks 30-Jan-22
13 Photocell 09-Sep-21 18 wks 01-Feb-22
14 Isolating switch panel 09-Sep-21 16 wks 20-Jan-22
15 Fog detector 17-Aug-21 32 wks 17-Apr-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
ELECTRICAL MATERIAL
No Description Target PO Delivery Time ROS
16 JB for external power 09-Sep-21 18 wks 01-Feb-22
17 Lighting fixtures and lighting junction boxes 09-Sep-21 18 wks 01-Feb-22
18 Lighting junction boxes 09-Sep-21 18 wks 01-Feb-22
19 Navigation aids control panel and battery charger 17-Aug-21 32 wks 17-Apr-22
20 Power plug and socket outlet 09-Sep-21 18 wks 01-Feb-22
21 Power socket outlet 09-Sep-21 18 wks 01-Feb-22
22 Radar beacon 17-Aug-21 32 wks 17-Apr-22
23 Cable ladders & trays 09-Sep-21 18 wks 01-Feb-22
24 Cable glands 24-Sep-21 14 wks 19-Jan-22
25 Earthing material 24-Sep-21 10 wks 22-Dec-21
26 Electrical bulk material 24-Sep-21 14 wks 19-Jan-22
27 Electrical cables 09-Sep-21 19 wks 08-Feb-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
ICSS MATERIAL
No Description Target PO Delivery Time ROS
1 Acoustic Sand Detector 09-Sep-21 24 wks 15-Mar-22
2 Pressure Transmitter (Hardwire) 09-Sep-21 18 wks 01-Feb-22
3 Pressure Transmitter (Wireless) 09-Sep-21 16 wks 18-Jan-22
4 Flow Transmitter (Wireless) 09-Sep-21 16 wks 18-Jan-22
5 Level Transmitter (Wireless) 09-Sep-21 16 wks 18-Jan-22
6 Temperature Transmitter (Wireless) 09-Sep-21 16 wks 18-Jan-22
7 Resistance Measurement (Wireless) 09-Sep-21 16 wks 18-Jan-22
8 Current Measurement (Wireless) 09-Sep-21 16 wks 18-Jan-22
9 Wireless Discrete Transmitter 09-Sep-21 16 wks 18-Jan-22
10 Wireless Gateway 09-Sep-21 16 wks 18-Jan-22
11 Level Gauge 09-Sep-21 20 wks 15-Feb-22
12 Gas Detector 09-Sep-21 16 wks 18-Jan-22
13 Fusible Plug 09-Sep-21 16 wks 18-Jan-22
14 Manual Alarm Call Point 09-Sep-21 16 wks 18-Jan-22
15 ESD Push Button 09-Sep-21 16 wks 18-Jan-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
ICSS MATERIAL
No Description Target PO Delivery Time ROS
16 Orifice and Restriction Orifice 09-Sep-21 22 wks 01-Mar-22
17 Restriction Orifice 09-Sep-21 22 wks 01-Mar-22
18 Pig Signaller 09-Sep-21 24 wks 15-Mar-22
19 Pneumatic Level Switch 09-Sep-21 24 wks 15-Mar-22
20 Electric Level Switch 09-Sep-21 24 wks 15-Mar-22
21 Pneumatic Pressure Switch 09-Sep-21 16 wks 18-Jan-22
22 Pressure Gauge 24-Sep-21 12 wks 05-Jan-22
23 Pressure Regulator Valve 09-Sep-21 24 wks 15-Mar-22
24 Temperature Gauge 09-Sep-21 24 wks 15-Mar-22
25 Wellhead Control Panel 17-Aug-21 32 wks 17-Apr-22
26 Fire and Gas System 11-Aug-21 34 wks 18-Apr-22
27 General Alarm 17-Aug-21 32 wks 17-Apr-22
28 Instrument Cable 09-Sep-21 16 wks 18-Jan-22
29 Instrument Valves 09-Sep-21 16 wks 18-Jan-22
30 Instrument JBs 09-Sep-21 16 wks 18-Jan-22
31 Cable Ladder / Tray & Accessories 09-Sep-21 16 wks 18-Jan-22
32 Tubing Tray & Accessories 09-Sep-21 16 wks 18-Jan-22
33 Bulk Material 09-Sep-21 16 wks 18-Jan-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
OTHER MATERIAL
No Description Target PO Delivery Time ROS
1 Safety Equipment 09-Nov-21 6 wks 09-Jan-22
2 Davit Crane (SWL 2 T) 25-Sep-21 20 wks 03-Mar-22
3 Monorail 25-Sep-21 18 wks 17-Feb-22
4 Manual Material Handling Equipment 09-Nov-21 10 wks 06-Feb-22
5 Cathodic Protection - Type RetroPod 25-Sep-21 18 wks 17-Feb-22
6 Cathodic Protection - Type RetroSled and RetroPod 25-Sep-21 18 wks 08-Mar-22
7 Commissioning and Spare Parts Material 25-Sep-21 18 wks 17-Feb-22
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
Inconsistency data between actual (field) Lack of design for constrution, lack of List of the required data along with respective reference as part of Site
10 Survey check list; check list shall be discussed within team to minimize
and design document quantity of supplied material, obstruction
lack of data
11 Un-fit equipment dimension with actual Obstruction, equipment couldn't installed Checking the equipment and proper site survey to be conducted
including the method for measurement
12 Un-fit deck extension with actual Obstruction, deck couldn't installed Checking the equipment and proper site survey to be conducted
including the method for measurement
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
PROCUREMENT
Delay of material delivery of COMPANY
13 Delay of project delivery / completion Expediting and monitoring
Supplied Item
Delay of material delivery of Contractor Expediting and monitoring the delivery; release PO or
14 Delay of project delivery / completion
Supplied Item procurement stage in due time
Empower the engineering development and review, including the
Wrong specification / material, shortage,
15 Cost impact, impact to project schedule allocated spare; raise PO to Vendor based on COMPANY AML
damage
FABRICATION
The pre-fabricated spool / material are
16 Cost impact, rework Strengthen the supervision
not comply with the shop drawing
17 Bad Weather Fabrication Schedule Monitoring the weather / forecast and assess for the schedule
Shortage of consumable (i.e. electrode
18 etc) Fabrication Schedule, Manpower standby Monitoring and supervision the material warehouse
Proper manpower selection, and monitor the manpower
19 Lack of Manpower (number, skills etc) Quality, HSE
projection
LOAD OUT & TRANSPORTATION
Monitoring the weather / forecast and assess for the schedule;
14 Bad Weather Installation Schedule
postphone the execution
15 Delay of provision of Marine Spread Installation Schedule Monitoring the weather / forecast and assess for the schedule
Perform the survey of marine spread properly including any
16 Poor of marine spread Quality, HSE punchlist clearence
Project Kick-Off
Meeting Bekapai 3 - Surface Facilities Modification and Dogleg
Installation (EPCIC)
Contract No. 4500010835
INSTALLATION
Failed of lifting due to inadequate of lifting Reviewing the lifting calculation and methodology; for selection
21 Installation Schedule, HSE, Quality
gear the lifting gear specification including the spare
Hit other equipment at Platform during Monitor the weather and wave motion, install scaffoding for
22 HSE, Quality, Damage
installation protection
12. Q & A