You are on page 1of 1

Advice and guidance Confirm that the circuit or circuits to be tested are de-

energised and isolated. Then, using a high resistance


The connection to Earth is typically achieved by the
protective conductor being connected to the main
ohmmeter set to 500 V d.c. and to the highest earthing terminal (MET) of the installation, to which
Taking you step by step through procedures resistance range on the instrument, carry out the
following test procedure and record the results
the earthing and main protective bonding conductors
are also connected, with the MET connected to the
and requirements for electrical installations obtained. earthing arrangement (the distributor’s earthing
facility (TN system) or the installation earth electrode
• Test between line and neutral on the load side
(TT system), as applicable).
of the main switch (in the OFF/isolation position,
but with all the circuit protective devices in the Having the protective conductors connected to Earth

Insulation resistance testing ON position), as shown in Fig 1.


• Then test between live conductors and circuit
protective conductor connected to the means of
during the test has the advantage that the test might
detect any contact between a live conductor and any
‘unearthed’ metalwork (such as a concealed part of
the building fabric or an isolated section of pipework).
earthing (with the main switch and all the circuit
If the unearthed metalwork has some relatively low
Carrying out an insulation resistance test protective devices in the ON position), as shown
resistance contact with Earth (even hundreds of
in Fig 2.
gives an indication of the condition of thousands of ohms), the defect can be identified by
the person using the insulation test instrument. Such
the insulation of conductors and any a dangerous defect might be caused by the
penetration of a nail, screw or similar making contact
equipment to which they are connected. with a live conductor and the unearthed metalwork. If
Effective insulation is necessary to not corrected, the defect would create a risk of
electric shock.
provide basic protection and to prevent
In many cases there will be a significant time interval
short-circuits and earth faults. between the initial placement of conductors
(sometimes referred to as ‘first fixing’) and the final
An insulator should have high insulation resistance, handover of the installation. It is possible for damage
typically many megohms (M⍀). to have occurred during this time when, for example,
cables were plastered over and flooring and ceilings
The insulation resistance of a conductor is inversely were installed.
proportional to its length – that is, its insulation resistance
decreases as the conductor’s length increases and vice It is essential therefore that all the relevant inspection
versa. It follows that the insulation resistance of a and tests are performed as part of the initial
complete electrical installation, or a section of it, will be verification of the electrical installation. In many
less than that of a single circuit of that installation. cases, this will require inspections and tests carried
out earlier to be repeated. It may not be safe to rely
By reference to Table 61 of BS 7671, Regulation 612.3.2 on inspection and test results obtained at an early
indicates that the minimum acceptable value of insulation stage of the installation process.
FIG 1 Insulation resistance between live
resistance for a distribution circuit with a distribution
conductors Initial verification must be carried out by skilled
board or consumer unit and all its final circuits connected
is 1 M⍀. Although values of this order particularly in a new FIG 2 Insulation resistance between person(s) competent in such work (Regulation 610.5).
installation, would warrant further investigation. live conductors and Earth Where the inspection and testing has been carried
• The test voltage applied may be reduced to 250 V d.c. out by an NICEIC Approved Contractor or an NICEIC
Prior to carrying out an insulation resistance test, any or ELECSA Registered Domestic Installer, the results
equipment likely to influence the test results obtained, or but the minimum acceptable value of insulation However, where the consumer unit has been
resistance remains 1 M⍀ (see Regulation 612.3.2). connected to the meter, the test must be carried out of the inspection and testing should be carefully
be damaged by the test voltage, such as surge protective reviewed by the registered Qualified Supervisor.
devices, dimmers, electronic switches and high on the load side of the main switch (in the
RCDs may also affect insulation resistance test results. It
frequency luminaires, should be disconnected. OFF/isolation position, but with all the circuit
may therefore be necessary to disconnect RCDs while the
protective devices in the ON position).
Where it is not reasonably practicable to disconnect such tests are performed and/or to test the wiring on the load Further advice can be found in the
equipment, or where doubt exists as to whether all such side of RCDs separately, to ensure the wiring is included in It is essential that, when performing an insulation
NICEIC and ELECSA book - Inspection ,
equipment has been disconnected, the following options the testing. resistance test between live and protective
conductors, the protective conductors are connected Testing and Certification
are available: The procedure for performing insulation resistance testing
to the earthing arrangement – that is, to the general newly updated to the 3rd amendment
• Insulation resistance may be measured between as part of the initial verification of a single-phase low voltage
mass of the Earth (Regulation 612.3.1 refers). of BS 7671 Wiring Regulations.
live conductors and protective conductor(s) with all (230 V) is as follows:
live (line and neutral) conductors connected together Temporarily disconnect or isolate equipment likely to be
(Regulations 612.3.1 and 612.3.3 refer). Where this damaged by the test voltage or influence the test results. ● For other guidance and publications please see the NICEIC website.
method is used, there is no potential difference Place all switches in the ON position. Two-way and, where ● Information about the NICEIC Approved Contractor or Domestic
between the line and neutral terminals of connected fitted, intermediate, switches will need to be operated
equipment that could adversely affect the internal Installers schemes,visit www.niceic.com or call 0870 013 0382
during the test procedure to ensure that all live conductors
components. are subjected to the testing. or circle readerlink

www.niceic.com

You might also like