TAILING MINE FILTRATION PROJECT

Site Installation Civil, Structural, Mechanical & Piping (CSMP)


PT. Agincourt Resources

Date : May 16th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

GENERAL ACTIVITIES

General Pre-start meeting Internal EMK TBM


CIVIL

JSEA briefing before concreting Continue install rebar axis 7-6-5

Mixer truck first loading !st pouring footing GL 15-13 Axis A-B-C

First slump test First pouring footing GL 15 -13


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 16th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

First pouring footing GL 15 -13 Ongoing pouring footing GL 15 -13

Unloading PERI material Ongoing pouring footing GL 15 -13

2 more unit TM arrive at TMF Mobilize structure material to TMF


Piping

Mobilize pipe HDPE to TMF Mobilize pipe HDPE to TMF


TAILING MINE FILTRATION PROJECT
Site Installation Civil, Structural, Mechanical & Piping (CSMP)
PT. Agincourt Resources

Date : May 16th, 2023

DAILY PHOTOGRAPH
PHOTOGRAPH

Site Establishment

Continue install roof shelter for TMF area Concreting workshop floor
Prepared by : Approved by :

Project Control