PT PLN (Persero) CFSPP Kalselteng 2 Asam-Asam

UIP KALBAGTENG (2 x 100 MW)


Proyek PLTU Asam-Asam Unit 5 dan 6

PT PLN (Persero) SITE COMMUNICATION


PUSAT MANAJEMEN PROYEK CONSORTIUM
Project Site Team PLTU Asam-Asam Unit 5 dan 6 PT TRUBA JAYA ENGINEERING - HYUNDAI ENGINEERING CO.,LTD. - ITOCHU CORPORATION
No : /SC/PST-Asam asam/2020

To : Consortium THI Date : October 20th, 2020


Category : Mechanical Attachment : 1 set
Subject : Improper Installed Temporary Platform for Coal Silo Installation Closed date :

NO PLN COMMENT CONTRACTOR COMMENT

Refer to :
1. Contract Book I Clause 2.17 Care of Works
2. Contract Book I Clause 3.15 Safety
3. Contract Book III Clause 4.9 Erection and Commissioning, Sub Clause 4.9. 1.3.4 about Acceptable and Unacceptable Work
'Contract Book III Clause 4.9 Erection and Commissioning, Sub Clause 4.9. 1.3.4 about Acceptable and Unacceptable Work
4. Contract Book III Clause 4.9 Erection and Commissioning, Sub Clause 4.9. 1.4.2 about Construction Equipment And Safety
5. Contract Book III Clause 4.9 Erection and Commissioning, Sub Clause 4.9. 6.4.2 about Temporary work Welding
6. Procedure Document No. IKCP0-UHA-BLRC-05-036 about "Coal Bunker Erection Drawing"
Actual Condition at site:
Based on our site observation on September 19th, 2020, PLN found that temporary platform for assembly coal silo has been welded
on coal silo steel plate directly. it was improper installaed for assembly Coal silo installation and will be make potential of decreasing
quality material. In orther side, consortium should consider regarding Labour safety during on temporary platform. Furtheremore,
Contractor is requested to conduct corrective action immediatelly as follows:
1 Remove temporary platform that welded directly on the silo steel plate
2 Check, corrective and conduct surface finishing of coal silo steel plate after removal temporary platform
3 Provide new temporary platform that using scaffold material or other platform without welding process directly on silo steel
4 Conduct safety tag on new temporary platform prior to used
Thank you for your kind attention and cooperation.

PT PLN (Persero)
PT PLN (Persero)
Pusat Manajemen Proyek UPP Kitring Kalbagteng 4 Consortium THI
CFSPP Kalselteng 2 Asam-Asam (2 x 100 MW)

Harrie A.S. Pamunkkaz Fachri Isnaeni Ali Eric Teguh Santoso


Project Team Leader Project Manager Site Manager

Page 1 of 2
Installed Temporary Platform on Coal Silo Steel Plate

Directly welded on Surface Coal Silo Steel Plate