Professional Documents
Culture Documents
Doc. Rev.
ES-(XTJB)5,6-09-00-0025 2
Engineering Sheet No.
Date :JUL.17.2019
Customer
Sumitomo Corporation
CONFIDENTIAL
THIS DOCUMENT IS THE PROPERTY OF SUMITOMO CORPORATION BOILER DIVISION (SCBD) AND CONFIDENTIAL. IT MUST
NEITHER BE COPIED NOR USED FOR ANY PURPOSE OR MANNER OTHER THAN EXPRESSLY PERMITTED BY MHPS OR WITH
A PRIOR WRITTEN CONSENT OF SCBD NEITHER IS IT TO BE HANDED OVER NOR COMMUNICATED TO A THIRD PARTY IN ANY
WAY. BREACH OR INFRINGEMENT OF ANY KIND WILL LEAD TO LEGAL ACTION.
0 First issue -- -
- -
- -
CONFIDENTIAL
THIS DOCUMENT IS THE PROPERTY OF SUMITOMO CORPORATION BOILER DIVISION (SCBD) AND CONFIDENTIAL. IT MUST
NEITHER BE COPIED NOR USED FOR ANY PURPOSE OR MANNER OTHER THAN EXPRESSLY PERMITTED BY SCBD OR WITH A
PRIOR WRITTEN CONSENT OF SCBD NEITHER IS IT TO BE HANDED OVER NOR COMMUNICATED TO A THIRD PARTY IN ANY
WAY. BREACH OR INFRINGEMENT OF ANY KIND WILL LEAD TO LEGAL ACTION.
1. Purpose
The purpose of this work plan procedure is to define the installation for the
Bottom Ash Handling System in Tanjung Jati B Expansion (Jawa-4) Coal Fired
Steam power Plant 2 x 1000MW. The work plan stated herewith is to ensure that
there is a guideline to be followed for the safe installation.
The necessity for safety precautions during the related must be emphasis.
Attention is therefore drawn to the established site safety procedure (refer to
TJB56-L2-ON-C-00-H-PLA HSE MANAGEMENT PLAN FOR CONSTRUCTION),
which should be adhering to under all practical and possible situation.
2. Scope
The scope covers the handling precautions, foundation layout, setting, alignment
and assembly of other components including inspections related to this
installation.
<Reference Document>
Please refer to documents in Attachment-1 to 3.
3. Materials / Equipments
Below is a general list of the equipment and tools that is required for unloading
and erection work.
a) Required lifting tools and tackles (slings, eyebolts, shackles, chain block,
lever block)
b) Timber or wooden block
c) Hiab truck 10T
d) Mobile Crane 80T
e) Trailer
f) 6t Forklift
g) Roller skid (Turtle Tank)
h) Electrical Winch 3T, 5T
4.Loading / Unloading
a) Place the required crane in good and rigid groud in out rigger in extended
position for hydraulic crane and truck mounted crane. For crawler crane the
parking area should be flat and good bearing strength.
b) For more precaution, place a suitable steel plate or timber mat on bottom of
the outer rigger.
c) Crane jack up (extend outrigger) at maximum position.
d) Check and confirm the level o the crane, before proceeding the unloading
work. (for all type of crane)
e) Swing the crane 360 degrees to confirm the four outrigger in good and stable
position (for telescopic types of crane)
f) Bring and position the trailer in such a way that, the chart working radius is to
be maintained. (for all type of crane)
g) Connect all the recommended lifting gears to the crane hook and lift it up.
h) Once all the lifting gears connected and swing the crane gently to check any
obstruction.
i) If any obstruction, remove it or clear the swing path.
j) If access not reachable to connect the lifting gears to material loaded
container, wooded cradle places an aluminum ladder in appropriate position
for the access of rigger to go top and connect the sling to the above said
packages.
k) Connect the lifting slings to the material loaded container, wooded cradle and
material package case lifting points mension in the case with the help of
shackles.
l) If the all above said method or procedure is accepted by the supervisor, give
the load to the crane and check it.
m) Be sure that, during swinging and lowering all the four outrigger in good
stable ondition.
n) Swing the crane as required and if the crane working radius is in correct,
lower the materials or packing.
( 5 / 16 )
o) Place the materials or packing on top of the timber block if available, and
sure that the materials or packing and timber block in fully contact.
p) After, the lifting supervisor inspected the rigidity, loose the sling and open it
from materials or packing lifting hook.
q) The crane shall be hooked up to the material as per the handing instruction.
r) The material shall be picked up by crane, keeping the material level, till it is
clear off the trailer.
s) The material shall be moved in position over the timber or wooden block and
lowered.
t) The material shall be lowered till it is positioned directly on the timber or
wooden block, and all final adjustments made while it is still hooked up to the
mobile crane.
u) When it is confirmed that material is properly positioned and the proper level.
v) Proceed to unload another materials or packing, container and wooden
cradle by the same safe working manner.
w) Materials which are unloading and load by fork lift (3T and 4.5T) take
precaution during the entire operation.
( 6 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
SUMITOMO CORPORATION BOILER DIVISION
5. Flow chart
Conveyor-1 Conveyor-2
01 Erection of BA Transition Hopper
Steelwork and Body
( 7 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
6.1.1 Foundation
a) Determine and mark the reference elevation for plant erection at any
position desired on the foundation, using for example, an alignment
scope.
b) Determine the centerlines for conveyor erection (X and Y direction) from the
reference line for plant erection and mark them on the foundation.
c) Check the location of foundation bolts with the foundation plan and the base
plate plan.
6.2 Installation
6.2.1 Transition Hopper Steelwork and body
a) Assemble the hopper supporting structure near the setting location
or outside the boiler mat whichever depending on the work area
conditions (assembly of 2 columns) 5.5m by 4.5m for erection. About
3.5Ton
b) The casing of the transition hopper is divided into upper, middle and
lower parts. Assemble the casing in suitable sized panels on the
ground and hang temporarily on the boiler buckstays and hopper
supporting structure.
Transition Hopper
Casing
Sole Plate
Anchor bolt
Horizontal section
SUMITOMO CORPORATION BOILER DIVISION
Supporting Structure Crusher Platform
Fig-4 Conveyor-1 Outline
( 9 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
( 9 / 18 )
Hydraulic Unit
Diverter
Crusher
Inclined Block-2
L10xW1.2xH1.3m
Lot3
Lot3 Inclined Block-1
L12xW1.2xH1.3m
Horizontal Block
( 12 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
6.2.17 Fablic Compensator
a) Install the fablic compensator according to the drawing.
Refer to Fig-9 and reference drawing shown on Chapter-7 9.0 in
Attachment-2
Furnace Inlet
Header
Inner &Outer Sheild
(Seal Plate)
Fablic Compensator
Transition Hopper
Casing
Doc.No: TJB56-L2-ON-C-00-H-PLA-0001
HSE MANAGEMENT PLAN FOR CONSTRUCTION
1) All workman from contractor that are involved in this operation, including
supervisors, foreman and operator etc. would be provided with the
required PPE such as safety helmets, harness, safety shoes, safety
glasses (goggles). As per the site laydown envilonment all crew would be
provided by dust mask and ear protection.
2) Prior to the operation or work, safety personnel shall ensure that all the
relevent safety permit are approved.
3) The lifting slings, chain blocks and shackles used shall have valid
statutory certificates.
4) Lifting supervisor and signalman from contractor will coordinate with
operator to ensure safety and smooth operation.
5) No un authorized personnel shall stand under any suspended load.
6) The chemical substances, paint materials, lubricant oil are kept in
separate area under hazards material sign board, no smoking sign
board.
7) The hazards material are kept in proper ventilated places.
8) Plan tools and equipment safety
a. The following four basic principles shall be applied to and govern the
safe use of hand power tools, and wich principles are,
To choose the right tools for the job
To use only tools in a good condition
To use the tools correctly, and only for the purpose they were
intended
To maintains and store tools properly
( 14 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
h. Scaffolding work
Select only good & rigid scaffold component materials.
Store scaffold material with proper racks / container and
barricade around the storage area with proper signage.
Use only trained, competent and authorized scaffold erectors to
carry out work.
Safety harness with 2 lanyards attached to a shock absorber
must be anchored to rigid member of existing scaffold at all time.
Tie down all hand tools to part of body or to safety harness.
a. Lifting Crew
Certified liftingsupervisor will oversee the lifting operations.
Ceriffied rigger to do rigging of the loads.
Certified signalman to do signaling during the lifting opeartions.
Certified and licensed crane operator to operate the crane
Certified lorry loader operator to operate lorry crane.
b. Machine Maintenance
Daily pre-start checks to be done prior to commencing the work
Pre-start checks also to be done when taking over from another
operator.
All warnign devices to be checked and operating.
Fallts of damaged to be reported
Defects effecting safety to be reported immediately to the
supervisor.
Plant with safety defects to be stood down until hazards is
rectified.
Regular maintenance and servicing to be carried out in
accordance with manufacture’s specifications.
Operators to read appropriate sections of the operation and
maintenance manual.
( 15 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025
e. Lifting Limits
If the weight of the load is unknown, do not guess, but seek
further advice.
Refer also to the load chart for load-reach relationship.
No laods in excess of the safe working load shown on the load
( 16 / 16 )
Doc.
No. ES-(XTJB)5,6-09-00-0025