(ADCOP)
FOC
LAYING & TESTING PROCEDURE
30-99-90-1652
1 INTRODUCTION .................................................................................................................................4
1.1 Main Components of the ADCOP Pipeline System.............................................................................4
1.2 Scope of Procedure .............................................................................................................................4
1.3 Terms and Definitions..........................................................................................................................4
1.4 Abbreviations .......................................................................................................................................4
2 REFERENCES AND STANDARDS....................................................................................................5
2.1 Order of Preference .............................................................................................................................5
2.2 Reference Documents of the Project...................................................................................................5
2.3 International Standards........................................................................................................................5
3 GENERAL ...........................................................................................................................................6
4 TRANSPORT AND STORAGE...........................................................................................................6
5 DRAWINGS REVIEW AND DRUMS ASSIGNATION ........................................................................7
5.1 Drawings Review .................................................................................................................................7
5.2 Single-Reel Test ..................................................................................................................................7
5.3 FOC Drum Assignation........................................................................................................................7
6 FOC LAYING PROCEDURE ..............................................................................................................7
6.1 Pre-laying Inspection and Preparation ................................................................................................7
6.2 HDPE Conduit Pressure Re-test .........................................................................................................8
6.3 HDPE Conduit Passing-through Re-test .............................................................................................8
6.4 FOC Blowing........................................................................................................................................9
7 OPTICAL FIBER SPLICING AND TERMINATION ..........................................................................10
8 FOC RELAY SECTION TEST...........................................................................................................10
9 DOCUMENTATION...........................................................................................................................11
APPENDIX A: FOC SINGLE-REEL TEST FORM .........................................................................................12
APPENDIX B: FOC DRUM ASSIGNATION FORM.......................................................................................13
APPENDIX C: FOC POST-BLOWING TEST FORM .....................................................................................14
APPENDIX D: FOC SPLICING TEST FORM.................................................................................................14
APPENDIX E: FOC RELAY SECTION BI-DIRECTION TEST FORM...........................................................15
The United Arab Emirates (UAE) authorities assigned International Petroleum Investment Company
(IPIC) to execute the Abu Dhabi Crude Oil Pipeline (ADCOP) project which will facilitate the
transferring crude oil from the Habshan production facilities to the Fujairah main oil terminal (MOT) on
the eastern seaboard of UAE. The proposed pipeline is of approximately 404 km in length. The
pipeline shall be designed for transferring of 0.5~1.5 MMBBLD of crude oil.
1.1 Main Components of the ADCOP Pipeline System
Tie-in and manifold facility at MP 21
48” pipeline from ADCO Habshan production facilities to the Fujairah Main Oil Terminal as
mentioned above.
Main Pump Station (MPS) in Habshan area, with tie-in to the existing ADCO pipeline
network. MPS is equipped with custody metering facility, storage/buffer cum relief tanks,
electrically driven main oil transfer pumps and booster pumps.
Intermediate Pump Station (IPS) in Sweihan which contains electrically driven pumps,
station bypass and surge relief facility.
Main Oil Terminal (MOT) located at Fujairah north of the existing Vopak terminal which
will be equipped with tanks, pumps, pressure control system and utilities etc.
MOT loading facilities with 3 SPM’s, loading capacity 80000 bbl/hr each.
1.2 Scope of Procedure
Scope of this Procedure is to guide construction for Fibre Optic Cable (FOC) laying and testing
which shall be blown into HDPE cable conduit buried in the same trench as the pipeline for
ADCOP facilities. However, any additional procedures may be prepared and issued for
approval during the Project life-cycle if necessary or required.
This Procedure is applicable to the following FOC in the ADCOP project:
24 core, G.655 FO cable running from MP 21 Tie-in station to Habshan MPS.
24 core, G.655 FO cable running from Habshan MPS via BVS stations to Sweihan IPS and
from Sweihan IPS via BVS stations to Fujairah MOT.
1.3 Terms and Definitions
Client International Petroleum Investment Company (IPIC)
PMC ILF Consulting Engineers
FEED Consultant Worley Parsons
EPC Contractor China Petroleum Engineering & Construction Corporation
Abu Dhabi Branch (CPECC)
the Project Abu Dhabi Crude Oil Pipeline Project
may One possible course of action
shall/must/is to be A mandatory requirement
1.4 Abbreviations
ADCO Abu Dhabi Company for On-Shore Oil Operations
ADCOP Abu Dhabi Crude Oil Pipeline
DOCUMENT TITLE : FOC
Project No: E 30153
LAYING & TESTING PROCEDURE
PROJECT: ABU DHABI CRUDE OIL PIPELINE PROJECT Page 4 of 16
DOCUMENT No.: 30-99-90-1652 Rev. 0 DATE :13/08/2008
BVS Block Valve Station
dB Decibel
FAT Factory Access Test
FOC Fibre Optic Cable
HDPE High Density Polyethylene
LDPE Low Density Polyethylene
IPS Intermediate Pump Station
MP Mile Point
MPS Main Pump Station
ODF Optical Distribution Frame
OLTE Optical Line Termination Equipment
OTDR Optical Time Domain Reflectometer
ROW Right Of Way
SPM Single Point Mooring
TP Test Point
3 GENERAL
The following guidelines and instructions shall be complied with strictly during the whole construction
of the FOC cable laying and testing.
Comply with FOC and FOC blowing machine manufacturers’ recommendation.
Don’t stand on FO cable and no vehicle shall be permitted to drive over it.
FO cable drums shall not be allowed to roll for moving.
FO cable drums shall not be laid flat.
FO cable drums shall be fixed against rolling off during transportation or storage.
A spreader bar must be used above the drum to avoid inward pressure on the top of the drum
flanges while lifting the drum by crane or other lifting device.
The ends of FO cable shall be kept sealed with heat shrinkable caps at all time unless
necessary to open for inspection, test or connection.
FO cable shall not be twisted, kinked or folded.
Bending radius of FO cable shall be not less than 20 times of its diameter or subject to vendor.
FO cable drums shall not be dropped on the ground directly while unloading.
The enough length of FO cable shall be remained for upcoming use such as test or splicing at
manholes and stations.
OTDR, splicing machine and other test instruments shall be certified and calibrated, and be
confirmed the calibration test certificate not older than one year.
Generally 0.5~1m of the FO cable end will be cut off for test or splicing.
All works shall be performed by full-skilled, experienced and qualified personnel.
The following items shall be checked, inspected or test before FOC and its accessories to be installed
are transferred to the Site.
Check the identification number of FO cable drum.
Inspect documents provided by manufacturer such as FAT report, guidelines, specifications,
and pack lists etc.
Two adjacent section FO cables can be joined after they have been blown, or FO cable can be
terminated after it has been blown to station and when the shelter for telecommunication is
ready.
Splicing shall be done by well-trained and authorized persons only.
Splicing shall be done in controlled environment to assure splicing machine, FO cable, testing
equipments and accessories are placed in dust-free, temperature-controlled environment.
Sufficient length of cable shall be installed at all cable ends to reach the controlled environment.
Splicing shall be made by the use of a fusion splicing machine which shall be the core
alignment type and fully compliant with the optical fibre specification.
A Semi Automatic cleaver should be used for cutting the fibre to guarantee a plain cut at 90
degree.
Splicing along the cable route shall be done only at manhole location consistent with the design
drawings.
Optical fibre splicing shall be monitored with OTDR and optical talk sets shall be used to keep
contact between splicing operator and OTDR monitor.
The parameters of the splicing machine shall be set correctly according to the manufacturer’s
manual and the performance of the FO cable to be spliced.
The insertion loss resulted from splicing shall be less than 0.1dB.
Fibre optic splices shall be enclosed in the splice protection sleeves which shall be inserted in
the cassette of the splice enclosure.
The excess or loose bare fibre shall be organized and secured well in the splice tray.
Each splice enclosure shall be uniquely tagged for identification.
After splice enclosure has been successfully closed and mounted the chamber shall be
carefully cleaned up and closed.
FOC relay section test can be performed after FO cables between two adjacent stations have
been blown, joined and terminated successfully.
FOC relay section test shall be done bi-directionally from ODF to ODF installed in stations.
Testing shall be done by well-trained and authorized persons only.
The parameters of OTDR shall be set correctly according to the manufacturer’s manual and the
performance of the FO cable to be test.
DOCUMENT TITLE : FOC
Project No: E 30153
LAYING & TESTING PROCEDURE
PROJECT: ABU DHABI CRUDE OIL PIPELINE PROJECT Page 10 of 16
DOCUMENT No.: 30-99-90-1652 Rev. 0 DATE :13/08/2008
Each core of the optical fibres shall be test, the loss of any event shall be less than 0.1dB and
average attenuation shall be not more than 0.25dB/km.
All connectors shall be capped immediately after testing finished.
9 DOCUMENTATION
All data such as splicing locations or distance, and test results shall be collected and recorded in time,
and filled into corresponding form or reports, and well-kept by full-time person.
Inner End Mark/Meter Read A/1234 Outer End Mark/Meter Read B/5678
AVAILABLE SECTION
NO. DRUM ID FOC TYPE SECTION TO INSTALL STATUS
LENGTH(m) DISTANCE(m)
2 Installed
3 Fully damaged
4 Partly damaged
10
11
12
13
14
15
16
No Colour of Buffer Tube Colour of Optic Fibre dB Loss Estimated by Splicer dB Loss From OTDR
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
Splicing Operator OTDR Monitor
Date Date
Date Date