PLS-140106-A-G-MST-001

Rev No. 0.2

PESTECH SDN BHD


FUJI ELECTRIC ASIA PACIFIC PTE. LTD
JV

ARCHITECTURAL WORKS
METHOD STATEMENT

NEW BINTULU B
275/(132)KV SUBSTATION ESTABLISHMENT
(PLS-140106)

2nd OCTOBER 2017


PESTECH – FUJI JV
LIST OF ARCHITECTURAL METHOD STATEMENT
Tender : New Bintulu B, 275/(132)kV Substation Establishment Tender Number : PLS-140106
Document Number : PLS-140106-A-G-MST-001 Revision Number : 0.1

NO. METHOD STATEMENT DOCUMENT NUMBER CHECKLIST FORM


ARCHITECTURAL
1. Brick Laying Work PLS-140106-BIN-A-MST-AB-01 TBA
2. Plastering Work PLS-140106-BIN-A-MST-AF-01 TBA
3. General Painting Work PLS-140106-BIN-A-MST-AP-01 TBA
4. Screeding Work PLS-140106-BIN-A-MST-AS-01 TBA
5. Tiling Work PLS-140106-BIN-A-MST-AT-01 TBA
6. Door and Window Installation Work PLS-140106-BIN-A-MST-AD-01 TBA
7. Ceiling Installation Work PLS-140106-BIN-A-MST-AC-01 TBA
8. Roofing Work PLS-140106-BIN-A-MST-AR-01 TBA
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Brick Laying

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 30.12.2016
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 1 of 6

1.0 TITLE

Standard practice for brick laying work.

2.0 REFERENCE DOCUMENT

 Specification for Building


 Approved materials
 Approved architectural layout and details drawings

3.0 SCOPE OF WORK

3.1. General Description

This method of statement describes generally the technique of laying brick


work for control building.

3.2. Plan and Equipment

 Batching mixer
 Wheel barrow
 Plumb bob
 String
 Scaffolding

3.3. Material

 Bricks
 Concrete

3.4. Site Planning and Preparation

 Clean the work area with water to remove soil, dirt, nails, concrete
droppings, timber, etc. before setting up for brick laying work.
 Hose down all clay brick with water to remove any soil or dust
particles and ensure that the bricks are moist before commencement
of work.

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 2 of 6

3.5. Methodology

i. Start building the brick wall on a solid footer or foundation beam.


ii. Damp proof course shall be the type and laid in the position as
specified in the drawings.
iii. The bricks are to be laid along the stretcher face on all walls, stretcher
and header on every alternate course of the brickwork.
iv. Prepare sufficient amount of mortar mix in the ratio of 1:3, cement to
sand to be used for each round of brick laying work to avoid drying out
of mortar.
v. Sufficient amount of mortar mix should be spread over the whole
stretcher face of the brick before laying.
vi. Any bullet hole should be rectified by filling with mortar.
vii. Continually wet the brick wall after installation to prevent the bricks
from absorbing too much moisture from the mortar.
viii. Stiffeners will be erected accordingly to the requirements depending
on span and height of walls.
ix. The RC stiffeners shall be cast prior to the commencement of brick
laying work.
x. Install Exmet wire mesh for every 4th courses of brickwork.
xi. Provide lintels to top of door and window openings.
xii. Mild steel dowel bars to be installed at every 0.4m height interval
embedded in RC column to hold wall to column.
xiii. Plumb bob and string will be used to check vertical alignment. String
will also be used to check the horizontal alignment.

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 3 of 6

3.6. Organization, Responsibility and Supervision

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Brick Laying Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for brick laying work.

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY STANDARD/ PERSONNEL INCHARGE


ACTIVITY INSPECTION FORM
METHOD OF TEST ACCEPTANCE CRITERIA TESTED VERIFIED WITNESSED
Brick laying Visualization Randomly  As per approved COW RE/ QAQC Client’s Rep TBA
work inspection during and after architectural drawings. (Hold) Engineer (Witness) (by Minsar)
brick laying work  As per Specification for (Review)
Building

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 6 of 6

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.
 Safety helmets and safety footwear should always be worn.
 All soft spots or holes shall be identified and barricaded if necessary.
 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 2: Emergency Response Team (ERT)

Method statement for brick laying work


PLS-140106-BIN-A-MST-AB-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Plastering Work

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 30.12.2016

i
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 1 of 6

1.0 TITLE

Method statement for plastering work.

2.0 REFERENCE DOCUMENT

 JKR Specification for Building


 Approved layout and details drawings
 Project Technical Specification

3.0 SCOPE OF WORK

3.1. General Description

This method statement for application of plastering work encompasses


application procedures, materials, necessary machinery and equipment,
testing, QAQC aspects, and safety aspects.

3.2. Plan and Equipment

 Trowel
 Hawk
 Masking Tape

3.3. Material

 Cement mortar

3.4. Site Planning and Preparation

Check for wall verticality and set out pegs for plastering. Allow a few days
after the erection of brick wall before proceeding with the plastering work.

The area shall be thoroughly cleaned before commencement of any


plastering work. The surface to receive plastering shall be dry brushed to
remove all loose particles and wet the surface before plastering.

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 2 of 6

3.5. Methodology

Surface Preparation

i. Clean and wet the surfaces prior to plastering work to prevent


premature drying out of the mortar.

Plaster Laying

i. Mix mortar in the ratio 1:3 (cement: sand) on a clean platform.


ii. The plaster shall be applied in two coats generally to a total thickness
of 16mm to brick wall and 12mm to soffits, beams, columns and other
smooth surfaces. The first coat shall consist of rough plastering to a
thickness of 10mm for the 16mm plainface, and 6mm for 12mm
plainface. The second coat of 6mm thick shall be finished with a steel
trowel for internal surfaces and with a straight-edged wood float for
external surfaces.
iii. As far as possible, start work at corners to establish the required
thickness for better alignment and evenness control.
iv. Wet the surfaces constantly to prevent excessively rapid or localized
drying out.
v. Clear all mortar dropping as the work proceeds.

Completion Checks

i. Upon completion of the work, check for evenness and alignment and
to rectify any defect.
ii. Check for hollowness spot and rectify as necessary.

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 3 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Plastering Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for plastering work.

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY OF STANDARD/ ACCEPTANCE PERSONNEL INCHARGE


ACTIVITY RECORD INSPECTION FORM
METHOD TEST CRITERIA TESTED VERIFIED WITNESSED
Plastering work Visualization Randomly Before,  As per approved drawings. COW RE/ QAQC Client’s Rep - TBA by Minsar
inspection during and after  As per Specification for (Hold) Engineer (Witness)
plastering work Building (Review)

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.
 Safety helmets and safety footwear should always be worn.

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 6 of 6

 All soft spots or holes shall be identified and barricaded if necessary.


 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 1: Emergency Response Team (ERT)

Method statement for plastering work


PLS-140106-BIN-A-MST-AF-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for General Painting Work

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017

i
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 1 of 6

1.0 TITLE

Method statement for general painting work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved layout and details drawings
 Paint Specification/ Catalogue

3.0 SCOPE OF WORK

3.1. General Description

The control building of substation will be painted with approved colour by


client as per their requirement.

Switchyard plinth of equipment also shall be painted.

3.2. Plan and Equipment

 Roller
 Brush
 Roller pan
 Scaffolding

3.3. Material

 Approved paint

3.4. Site Planning and Preparation

Prior to the commencement of painting work, the surfaces shall be dry, free
from dirt, oil, grease and other deleterious matter. Wood surfaces shall be
sanded to smooth rough spots. All cracks shall be raked out and filled with
approved filler material. Nail heads shall be puttied.

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 2 of 6

3.5. Methodology

Procedure

i. Observe strictly the manufacturer’s instructions with regards to


surface moisture, mixing, application, time lapse between successive
coats, and drying times.
ii. Emulsion paints may be diluted if required but strictly according to
manufacturer’s instructions.

Tools

i. Use good quality brush of suitable size that allow smooth paint flow
on the surface with long, full strokes without loses of bristles.
ii. Large surfaces can be painted with a roller. The roller shall be evenly
saturated with paint by working the roller back and forth in a roller pan.
Painting using roller shall be finished by rolling in one direction.

Process

i. Painting shall proceed from top to bottom covering a width of about


1m. The next strip shall overlap the first strip slightly before the paint
in that area dries out so that the overlapping line will not be visible.
ii. The number of coatings required for primer and finishing coats for
different surfaces shall be in accordance with specifications.
iii. Avoid excessive or uneven thickness of paint film.
iv. Finished surfaces shall be uniform in finish and colour and be free
from brush marks or other defects.

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 3 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Painting Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for general painting work.

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY STANDARD/ ACCEPTANCE PERSONNEL INCHARGE


ACTIVITY RECORD INSPECTION FORM
METHOD OF TEST CRITERIA TESTED VERIFIED WITNESSED
General Painting Visualization Randomly  As per approved COW RE/ QAQC Client’s Rep - TBA by Minsar
work inspection before and drawings/Catalogue (Hold) Engineer (Witness)
after painting  As per Project Technical (Review)
work Specification.

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 6 of 6

 Safety helmets and safety footwear should always be worn.


 All soft spots or holes shall be identified and barricaded if necessary.
 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 1: Emergency Response Team (ERT)

Method statement for general painting work


PLS-140106-BIN-A-MST-AP-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Screeding Work

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017

ii
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 1 of 6

1.0 TITLE

Method statement for screeding work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved architectural layout and details drawings

3.0 SCOPE OF WORK

3.1. General Description

This method of statement describes generally the sequence technique to


screed floor of control building for substation.

3.2. Plan and Equipment

 Levelling instrument
 Tape
 Trowel
 Floats
 Straightedges

3.3. Material

 Cement.
 Sieved sand (free from debris, organic and impurities)

3.4. Site Planning and Preparation

Floor screeding work shall proceed after casting of concrete slab to


structural finish level/floor concrete level. Screeding is used to create
smooth, flat surface on floors to receive finishes like tiles and marble.

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 2 of 6

3.5. Methodology

i. Surface preparation

 Rectify all defects to substrate prior to screeding work.


 Clean to remove laitance and wet the concrete surface thoroughly.
 Set out the relevant datum points at each floor level with levelling
instrument. Level of finished screeds shall be accurately peg
before commencing screeding works.

ii. Screed laying

 Damp surface before applying the cement screed.


 Where finished screed is to be laid monolithically on the concrete
base as required, it will be laid in one continuous layer where
practicable, all in accordance with requirement.
 Prepare cement mortar mix for screeding work in the ratio 1:3,
cement and sand.
 Where finished screed is to be bonded to hardened concrete base,
screeds up to ±50 mm in thickness shall be spread and
compacted in a single layer.
 Immediately after compaction, the screed shall be brought to an
accurate and reasonably smooth finish by light use of screeding
tool.
 Allow the concrete compound to completely set before stepping
on the screeded floor.

iii. Completion check

 Upon hardening, check for hollow spot and rectify as necessary.

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 3 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Screeding Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for screeding work.

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY STANDARD/ ACCEPTANCE PERSONNEL INCHARGE


ACTIVITY RECORD INSPECTION FORM
METHOD OF TEST CRITERIA TESTED VERIFIED WITNESSED
Screeding work Visualization Random  As per approved architectural COW RE/ QAQC Client’s Rep - TBA by Minsar
inspection checking drawings. (Hold) Engineer (Witness)
 As per Project Technical (Review)
Specification

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 6 of 6

 Safety helmets and safety footwear should always be worn.


 All soft spots or holes shall be identified and barricaded if necessary.
 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 2: Emergency Response Team (ERT)

Method statement for screeding work


PLS-140106-BIN-A-MST-AS-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Tiling Work

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
0.2 Issued For Approval 02.10.2017
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 1 of 7

1.0 TITLE

Method statement for tiling work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved materials
 Approved architectural layout and details drawings
 BS 1197 Specification for Concrete Flooring Tiles

3.0 SCOPE OF WORK

3.1. General Description

This Method Statement is to describe the materials and procedures for the
installation of tiling works.

3.2. Plan and Equipment

 Tile cutter
 Chalk line
 Tape
 Spirit level

3.3. Material

 Tiles
 Acrylic Adhesive
 Sieved sand (free from debris, organic and impurities)
 Cement
 Adhesive cement

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 2 of 7

3.4. Site Planning and Preparation

Screed shall be laid after concrete slab has been thoroughly roughened,
cleaned, wetted and spread with a layer of neat cement mixture. The setting
bed for floor tile shall be of neat cement grout of the right consistency.

Tiles with chips, cracks or otherwise defective shall not be used for the work.
Tile cutter shall be utilised to cut any tile to ensure a neat edge.

3.5. Methodology

i. Floor tile installation

 Make sure the screeded surface is clean and even.


 All tiles shall be soaked in water prior to installation.
 Plan the starting tile carefully and use a chalk line as a guide for
laying subsequent tiles.
 Tiling setting out to be confirmed on site by Architect.
 End tiles which require cut pieces shall terminate in an
inconspicuous place.
 Mock up shall be arranged for floor tiles at location designated by
the S.O. for the final approval.
 All joints in floor tiles shall be truly aligned and even. Grout shall
be worked well into joints so that they are completely filled.
 Tap the tiles firmly with a rubber mallet to neatly level with fresh
cement screed.
 Upon completion, clean the surface of the floor with a damp rag
to remove any mortar or grout residue.
 Do not wet the newly laid tiles until the bedding and jointing have
completely set.
 No traffic on flooring within 48 hours upon completion.

ii. Vinyl tile installation

 Any cracks and bumps shall be repaired prior to installation.


 Clean the floor thoroughly to remove dust.
 Plan the tile layout carefully by snapping a chalk line across the
length and width of the room to obtain the intersection of the two
lines. Dry fit a row along the length and width of the room to
determine how they will actually fit when they reach the wall. If the

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 3 of 7

tiles do not end up with proper spacing, adjust the centre


reference lines accordingly before proceeding to install the rest of
the tiles.
 After installing a few rows, use a tile roller to bond them firmly in
place.
 Upon completion of installation, clean the surface by sweeping
away any dirt or debris.

iii. Wall tile installation

 Ensure that the existing plaster wall is vertically straight and does
not exceed the wall finishing level.
 Identify and mark the wall tile finishes level and setting out point.
 All tiles shall be soaked in water prior to installation.
 Mock up shall be arranged for wall tiles at location designated by
the S.O. for the final approval.
 Prepare the cement mortar mix for tiling work in the ratio of 1:3,
cement and sand.
 Apply the mortar to the back of tile and tap in into place at the
required level position to the wall.
 Affix the remaining tiles, ensuring a uniform joint spacing between
tiles and wipe away the excessive slurry mortar that seeps out
from the joint.
 Fill the wall tile joints with approved colour grout and wipe clean
the surface before the grout hardens.
 Site inspection of completed wall area and any defect rectified.

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 4 of 7

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Tiling Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for tiling work.

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 5 of 7

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY STANDARD/ ACCEPTANCE PERSONNEL INCHARGE


ACTIVITY RECORD INSPECTION FORM
METHOD OF TEST CRITERIA TESTED VERIFIED WITNESSED
Tiling work Visualization Randomly  As per approved architectural COW RE/ QAQC Client’s Rep - TBA by Minsar
inspection before and drawings. (Hold) Engineer (Witness)
after tiling  As per Project Technical (Review)
work Specification

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 6 of 7

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of
the benefits of conducting a Job Safety Analysis (JSA) – carefully studying
and recording each step of a job, identifying existing or potential sewerage
work hazards (both safety and health), and determining the best way to
reduce or eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator
and others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots
and helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 7 of 7

 Safety helmets and safety footwear should always be worn.


 All soft spots or holes shall be identified and barricaded if necessary.
 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve &
etc. in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition
if permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.

EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 2: Emergency Response Team (ERT)

Method statement for tiling work


PLS-140106-BIN-A-MST-AT-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Door & Window Installation

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 1 of 6

1.0 TITLE

Method statement for door and window installation work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved layout and details drawings

3.0 SCOPE OF WORK

3.1. General Description

This method of statement generally describes door and window installation


work which covers the construction procedure, setting out and material.

3.2. Plan and Equipment

 Fixing tools
 Masking tape
 Ladder
 Hand tools

3.3. Material

 Door
 Window

3.4. Site Planning and Preparation

All doors and windows delivered to site shall be checked to ensure that they
conform in types, sizes and quantities according to the door and window
schedules in the architectural drawings. They should be stored in a dry
place above ground to avoid damages. The dimensions of the door and
window openings together with allowance made for construction tolerance
shall also be checked before installation.

When setting out the lintel beam position, provide temporary propping and
support for a RC lintel.

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 2 of 6

3.5. Methodology

i. Door installation

 All doors shall be positioned accordingly as specified in the


architectural drawings.
 Door frames shall be erected from the floor concrete
level/structural finish level and firmly embedded in screed up to
the floor finish level. Before carrying out the screeding work, the
frame shall be checked for vertical and horizontal alignments
and braced securely to prevent movement and distortion.
 Unless specified, all doors openings shall be provided with lintel
beam to support the loads above the openings.
 When fitting the door, allow a clearance of :
a. 10mm between the edge of the door and the frame for
expansion and for receiving paint thickness
b. 50mm between the bottom of door and floor finish level
to accommodate floor unevenness.
 No squeaky sound during opening and closing of the door.
 Lockset and door closer should be functional.

ii. Window installation

 All windows shall be positioned accordingly as specified in the


architectural drawing.
 Window frames shall be checked for vertical and horizontal
alignment and braced securely to prevent movement and
distortion when sealing with mortar to the surrounding wall.
 Unless specified, all window openings shall be provided with
lintel beam to support the loads above the openings.
 For aluminium window, rake out joints around the external edge
of window and point with an approved sealant to form a smooth,
flat joint to prevent water ingress.
 Glazing shall be clean and evenly sealed with putty or gasket for
aluminium windows.

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 3 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Door & Window Installation


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for door and window installation work.

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
PESTECH – FUJI JV
DOOR AND WINDOW INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for door and window installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AD-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY OF STANDARD/ PERSONNEL INCHARGE


INSPECTION
ACTIVITY METHOD TEST ACCEPTANCE TESTED VERIFIED WITNESSED RECORD
FORM
CRITERIA
Door and window Visualization Checking is carrying  As per approved COW RE/ QAQC Client’s Rep - TBA by Minsar
installation work inspection out during and after drawings. (Hold) Engineer (Witness)
work completed  As per Project (Review)
Specification.

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
PESTECH – FUJI JV
DOOR AND WINDOW INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for door and window installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AD-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.
 Safety helmets and safety footwear should always be worn.

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
PESTECH – FUJI JV
DOOR AND WINDOW INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for door and window installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AD-01 Page : 6 of 6

 All soft spots or holes shall be identified and barricaded if necessary.


 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.

EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 1: Emergency Response Team (ERT)

Method statement for door and window installation


PLS-140106-BIN-A-MST-AD-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Ceiling Installation

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 1 of 6

1.0 TITLE

Method statement for ceiling installation work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved layout and details drawings

3.0 SCOPE OF WORK

3.1. General Description

This Work Method Statement covers the ceiling work activities and the
preparation, application and workmanship shall comply with the standard
and specification.

3.2. Plan and Equipment

 Concrete nailer
 Concrete driller
 Plumbs
 Basic hand tools
 Cutters
 Ladder
 Ruler
 Scaffold

3.3. Material

 Approved ceiling board


 Aluminium ceiling frame

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 2 of 6

3.4. Site Planning and Preparation

i. Material preparation/delivery schedule

Material shall be prepared in accordance with the construction program.


The material controller shall ensure materials are delivered in the correct
sequence of work. Should there be any delays in delivery due to
unforeseen circumstances (e.g. breakdown etc.) the material controller
shall inform the site personnel accordingly.

ii. Quality control

The type of ceiling material will be examined by the QA representative


as according to Architectural drawing.

iii. Buffer stock

To cope with the site installation demands, it would be necessary to keep


buffer stock of a few days’ installation works either at site or in the factory.
This would allow for continuity of work should there be any break in
delivery.

iv. Material delivery

Upon arrival of materials, they shall be unloaded immediately and


stacked properly at lay down areas.

v. Storage

Storage should provide protection against the weather.

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 3 of 6

3.5. Methodology

i. All setting up and leveling should be based on approved architectural


drawings.
ii. Once completed, the QAQC shall inform the subcontractor to request
for an inspection by the S.O/clerk of work approval prior to
commencing of any physical works.
iii. Then proceed with installation of ceiling joists above the roof beams,
and proceed to install the adjustable suspension brackets prior to
installing the main top cross rail and connector and lastly the furring
channels.
iv. Fix ceiling board.
v. Apply jointing tape to join the ceiling panel.
vi. Once all ceiling are completed, the subcontractor shall request that
the trades commence all marking and setting out works so as to
enable all opening or penetration be made prior to plastering works.

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 4 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Ceiling Installation


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for ceiling installation work.

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 5 of 7

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY OF STANDARD/ PERSONNEL INCHARGE


ACTIVITY INSPECTION FORM
METHOD TEST ACCEPTANCE CRITERIA TESTED VERIFIED WITNESSED
Ceiling Visualization Checking is carrying  As per approved drawings. COW RE/ QAQC Client’s Rep TBA by Minsar
installation work inspection out during and after  As per Project Technical (Hold) Engineer (Witness)
work completed Specification. (Review)

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 6 of 7

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 7 of 7

 Safety helmets and safety footwear should always be worn.


 All soft spots or holes shall be identified and barricaded if necessary.
 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 2: Emergency Response Team (ERT)

Method statement for ceiling installation


PLS-140106-BIN-A-MST-AC-01
New Bintulu B 275/(132)kV Substation Establishment
Contract No.: PLS-140106
Method Statement for Roofing Work

REVISION HISTORY

Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
0.2 Issued For Approval 02.10.2017

i
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 1 of 6

1.0 TITLE

Method statement for roofing work.

2.0 REFERENCE DOCUMENT

 Project Technical Specification


 Approved materials
 Approved roof plan and details drawings

3.0 SCOPE OF WORK

3.1. General Description

This method of statement describes generally the technique of architectural


roofing work for control building.

3.2. Plan and Equipment

 Mobile crane
 Pneumatic drill
 Product manufacturer’s tools

3.3. Material

 Roof sheet
 Roof fittings

3.4. Site Planning and Preparation

 The material is delivered to site in the correct sequence of work in


accordance with the construction schedule to avoid any delay due to
material shortage as well as to avoid lack of storage place.

3.5. Methodology

The general roofing installation procedures provided by the product


manufacturer should be adopted to ensure that the completed roof is safely
laid, properly fastened and the total water tight system to the roof is secured.

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 2 of 6

i. Preliminary check

 Prior to commencement of fixing, the installer should ensure that


purlins, girts or battens are truly in place and that the slope
requirements are met.
 All roofing material are to be stored properly prior to installation
and installation work are to be done in a clean environment.

ii. Lifting

 Roofing sheets shall be lifted carefully to the roofing frame to


avoid damage from bending or buckling of panel.
 Sheet bundles shall be placed over or near purlin supports.

iii. Laying

 The first sheet should be positioned accurately before fastening


to ensure that it is correctly located in relation to other building
elements.
 Make sure that the roofing sheets interlock completely and
securely fastened.
 The last sheet should be cut accurately to the required width to
ensure that it is secured properly to the fascia or parapet.
 The flashing and capping shall be carefully secured to ensure
complete water tightness to the roofing system.
 During laying, the sheets should be periodically checked for
alignment.
 The specified types of wire mesh and insulation wool shall be laid
and fixed firmly to the supports.
 Only the recommended tools and accessories from the product
manufacturer should be used.

iv. Cleaning up

 After each installation work, remove all metallic swarf and debris
from the roof areas and gutters to avoid surface staining and rust.

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 3 of 6

3.6. Organization Chart

Management

Project Director
Ir. Lee Kong Tee

Project Manager
Nihad Klapic

Supervision
Site Manager
Sylvester Lim

Site Coordinator Safety & Health Officer


Unie Robert Kenny Anak Naul

Site Construction
Civil Manager
Thian Fang Soon

QAQC Roofing Work


Civil QC Engineer Contractor
Meldrian Yung Kong Cons. S/B

Chart 1: Site organization chart for roofing work.

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 4 of 6

4.0 QUALITY ASSURANCE

4.1 Inspection and Test Plan (ITP)

TEST FREQUENCY STANDARD/ PERSONNEL INCHARGE


ACTIVITY INSPECTION FORM
METHOD OF TEST ACCEPTANCE CRITERIA TESTED VERIFIED WITNESSED
Roofing Visualization Random  As per approved related COW RE/ QAQC Client’s Rep TBA by Minsar
work inspection checking for drawings. (Hold) Engineer (Witness)
overall roofing  As per Project Technical (Review)
Specification.

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 5 of 6

5.0 ENVIRONMENT, SAFETY AND HEALTH

5.1 Introduction

One way to prevent workplace injuries during sewerage work is to


establish proper job procedures and train all employees in safer and more
efficient work methods. Establishing proper sewerage procedures is one of the
benefits of conducting a Job Safety Analysis (JSA) – carefully studying and
recording each step of a job, identifying existing or potential sewerage work
hazards (both safety and health), and determining the best way to reduce or
eliminate these hazards.
Precautions are to be taken for protection of persons and properties from
injury or damage during sewerage system installation work. All site personnel
must adhere to safety requirements:
 Only experienced or skill personnel of sewerage system are allowed at
working area.
 Authorized personnel only to handle with the piling machine, excavator and
others plant and equipment.
 All workers must have proper training to do sewerage work.
 Site personnel must be briefed and be well versed with all site safety
measures.
 Site personnel must be in proper safety working attire e.g. safety boots and
helmets must be worn at all times.
 Site safety member should be available at all times and must be able to
respond correctly to emergency.
 Avoid carrying too heavy loads.

5.2 Personal Protective Equipment

 Hand Gloves
 Long sleeves
 Safety boots
 Safety Helmet

5.3 Safety plan

 There must be sufficient working space and clearance as directed by


superintending officer. Sewerage work shall not be allowed to continue if
fail to provide adequate working space.
 Safety helmets and safety footwear should always be worn.

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 6 of 6

 All soft spots or holes shall be identified and barricaded if necessary.


 Clear up all the grass and bushes before tree identified to avoid stepped
onto sharp or dangerous object.
 Ensure good manual handling process.
 The site shall be kept clear of unnecessary obstruction such as
reinforcement rods, timber with protruding nails, etc.
 First aid boxes in the charge of a responsible person have to be kept at
sites.
 Install water cooler at site.
 All workers shall drink enough water
 Increase rest time for workers to drink enough water.

5.4 Emergency Response Plan

In case if tripping, electrocuted or accident happened during works:


 Stop the work and inform supervising personnel immediately of the
incident/accident.
 Record all information such as work type, workers, equipment involve & etc.
in the incident/accident.
 Immediately study / investigate what could have caused the incident.
 Give detail information to authorized person on all the activity and incident
that occurs.
 Repair or normalize the equipment/structures involve to normal condition if
permitted and send the injured personnel to clinic or hospital nearby.
 For detail action, kindly refer to project safety manual.
EMERGENGY COMMANDER

EVACUATION INCIDENT SAFETY COUNTER SECURITY


CONTROLLER CONTROLLER/ & FIRST AIDER CONTROLLER
HISTORIAN

Chart 2: Emergency Response Team (ERT)

Method statement for roofing work


PLS-140106-BIN-A-MST-AR-01