ARCHITECTURAL WORKS
METHOD STATEMENT
NEW BINTULU B
275/(132)KV SUBSTATION ESTABLISHMENT
(PLS-140106)
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 30.12.2016
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 1 of 6
1.0 TITLE
Batching mixer
Wheel barrow
Plumb bob
String
Scaffolding
3.3. Material
Bricks
Concrete
Clean the work area with water to remove soil, dirt, nails, concrete
droppings, timber, etc. before setting up for brick laying work.
Hose down all clay brick with water to remove any soil or dust
particles and ensure that the bricks are moist before commencement
of work.
3.5. Methodology
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 30.12.2016
i
PESTECH – FUJI JV
PLASTERING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for plastering work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AF-01 Page : 1 of 6
1.0 TITLE
Trowel
Hawk
Masking Tape
3.3. Material
Cement mortar
Check for wall verticality and set out pegs for plastering. Allow a few days
after the erection of brick wall before proceeding with the plastering work.
3.5. Methodology
Surface Preparation
Plaster Laying
Completion Checks
i. Upon completion of the work, check for evenness and alignment and
to rectify any defect.
ii. Check for hollowness spot and rectify as necessary.
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
i
PESTECH – FUJI JV
GENERAL PAINTING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for general painting work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AP-01 Page : 1 of 6
1.0 TITLE
Roller
Brush
Roller pan
Scaffolding
3.3. Material
Approved paint
Prior to the commencement of painting work, the surfaces shall be dry, free
from dirt, oil, grease and other deleterious matter. Wood surfaces shall be
sanded to smooth rough spots. All cracks shall be raked out and filled with
approved filler material. Nail heads shall be puttied.
3.5. Methodology
Procedure
Tools
i. Use good quality brush of suitable size that allow smooth paint flow
on the surface with long, full strokes without loses of bristles.
ii. Large surfaces can be painted with a roller. The roller shall be evenly
saturated with paint by working the roller back and forth in a roller pan.
Painting using roller shall be finished by rolling in one direction.
Process
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
ii
PESTECH – FUJI JV
SCREEDING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for screeding work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AS-01 Page : 1 of 6
1.0 TITLE
Levelling instrument
Tape
Trowel
Floats
Straightedges
3.3. Material
Cement.
Sieved sand (free from debris, organic and impurities)
3.5. Methodology
i. Surface preparation
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
0.2 Issued For Approval 02.10.2017
PESTECH – FUJI JV
TILING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for tiling work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AT-01 Page : 1 of 7
1.0 TITLE
This Method Statement is to describe the materials and procedures for the
installation of tiling works.
Tile cutter
Chalk line
Tape
Spirit level
3.3. Material
Tiles
Acrylic Adhesive
Sieved sand (free from debris, organic and impurities)
Cement
Adhesive cement
Screed shall be laid after concrete slab has been thoroughly roughened,
cleaned, wetted and spread with a layer of neat cement mixture. The setting
bed for floor tile shall be of neat cement grout of the right consistency.
Tiles with chips, cracks or otherwise defective shall not be used for the work.
Tile cutter shall be utilised to cut any tile to ensure a neat edge.
3.5. Methodology
Ensure that the existing plaster wall is vertically straight and does
not exceed the wall finishing level.
Identify and mark the wall tile finishes level and setting out point.
All tiles shall be soaked in water prior to installation.
Mock up shall be arranged for wall tiles at location designated by
the S.O. for the final approval.
Prepare the cement mortar mix for tiling work in the ratio of 1:3,
cement and sand.
Apply the mortar to the back of tile and tap in into place at the
required level position to the wall.
Affix the remaining tiles, ensuring a uniform joint spacing between
tiles and wipe away the excessive slurry mortar that seeps out
from the joint.
Fill the wall tile joints with approved colour grout and wipe clean
the surface before the grout hardens.
Site inspection of completed wall area and any defect rectified.
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
EMERGENGY COMMANDER
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
PESTECH – FUJI JV
BRICK LAYING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for brick laying work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AB-01 Page : 1 of 6
1.0 TITLE
Fixing tools
Masking tape
Ladder
Hand tools
3.3. Material
Door
Window
All doors and windows delivered to site shall be checked to ensure that they
conform in types, sizes and quantities according to the door and window
schedules in the architectural drawings. They should be stored in a dry
place above ground to avoid damages. The dimensions of the door and
window openings together with allowance made for construction tolerance
shall also be checked before installation.
When setting out the lintel beam position, provide temporary propping and
support for a RC lintel.
3.5. Methodology
i. Door installation
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
Chart 1: Site organization chart for door and window installation work.
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
EMERGENGY COMMANDER
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
PESTECH – FUJI JV
CEILING INSTALLATION
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for ceiling installation work Revision No. : 0.1
Doc No. : PLS-140106-BIN-A-MST-AC-01 Page : 1 of 6
1.0 TITLE
This Work Method Statement covers the ceiling work activities and the
preparation, application and workmanship shall comply with the standard
and specification.
Concrete nailer
Concrete driller
Plumbs
Basic hand tools
Cutters
Ladder
Ruler
Scaffold
3.3. Material
v. Storage
3.5. Methodology
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet
REVISION HISTORY
Revision
Description Revision Date
No.
0.1 Issued For Approval 10.04.2017
0.2 Issued For Approval 02.10.2017
i
PESTECH – FUJI JV
ROOFING WORK
Project : New Bintulu B 275/(132)kV Substation Establishment Contract No. : PLS-140106
Doc Title : Method statement for roofing work Revision No. : 0.2
Doc No. : PLS-140106-BIN-A-MST-AR-01 Page : 1 of 6
1.0 TITLE
Mobile crane
Pneumatic drill
Product manufacturer’s tools
3.3. Material
Roof sheet
Roof fittings
3.5. Methodology
i. Preliminary check
ii. Lifting
iii. Laying
iv. Cleaning up
After each installation work, remove all metallic swarf and debris
from the roof areas and gutters to avoid surface staining and rust.
Management
Project Director
Ir. Lee Kong Tee
Project Manager
Nihad Klapic
Supervision
Site Manager
Sylvester Lim
Site Construction
Civil Manager
Thian Fang Soon
5.1 Introduction
Hand Gloves
Long sleeves
Safety boots
Safety Helmet