URBAN EXTENSION ROAD (UER)-II

Package 2: From Karala-Kanjhawala Road to NajafgarhNangloi Road


(Km 15+000 to Km 28+450) NH 344M

INTRODUCTION OF PROJECT ROAD

Client

NATIONAL HIGHWAYS AUTHORITY OF INDIA

EPC Contractor

KRISHNA CONSTRUCTIONS PVT. LTD.

Design Consultant

NITYA NAYRA CIVIL SOLUTIONS PVT. LTD.


INDEX MAP

Start of Package-II
Km-15+000

End of Package-II
Km-28+450
PROJECT INFORMATION

Development of 6-lane Urban Extension Road-II (UER-II) – NH 344 M, Package


2 (From KaralaKanjhawala Road, Km 15+000 to Nangloi Najafgarh Road, Km
28+450) in the state of Delhi on EPC mode
Employer National Highway Authority of India

Design Consultant Nitya Nayra Civil Solution Pvt. Ltd.

Project Value Rs. 1132.69 Cr.

Start Date Yet to declare

Completion Date 24 months from the start date

Project Duration 24 Months

DLP/O&M Period 10 Years


SCOPE OF WORK
S.No. Description Scope
1 Project Length 13.45 Km
2 Service/Slip Road 24.091 Km
3 RCC Drain 44.227 Km
4 ROB 3 Nos.

5 Elevated Structure 3 Nos.

6 Elevated Turns 3 Nos.


7 VUP/Underpass 7 Nos.
8 Subway 3 Nos.
9 MJB/MNB 0 Nos.
PROJECT OVERVIEW

5%1% Road works including culverts, widening and repair of


20% culverts
ROB
19%
VUP/Subway

Elevated Structure

18% Other Engineering Works

Electrical utilities & public health utilities ( Water pipe


lines & sewage lines)
31% 6% Translocation of trees
CAMP LOCATION

RE Pannel
Casting Yard
Location Ch.
18+000Km

Main Camp &


Casting Yard
Location Ch.
22+800Km
LOGISTIC PLAN
MOBILIZATION STATUS

Manpower Mobilisation Schedule


Mobilisation Schedule
Sl. No. Description UOM Remarks
Aug-21 Sep-21 Dec-21
1 Manpower Nos 31 69 16

Machinery Mobilisation Schedule


Mobilisation Schedule
Sl. No. Description UOM Remarks
Aug-21 Sep-21
1 RMC plant with DG Nos 1 1
2 Motor Grader Nos 1 -
3 Soil Compactor Nos 2 -
4 Excavator Nos 2 -
5 Wheel Loader Nos - 1
6 Tipper Nos 6 -
7 Transit Mixer Nos - 2
8 Backhoe Loader Nos 2 -
9 Diesel Tanker Nos 1 -
PROGRESS-I

Machinery Mobilisation Schedule

Mobilisation Schedule
Sl. No. Description UOM Remarks
Aug-21 Sep-21

1 RMC plant with DG Nos 1 1

2 Motor Grader Nos 1 -

3 Soil Compactor Nos 2 -

4 Excavator Nos 2 -

5 Wheel Loader Nos - 1

6 Tipper Nos 6 -

7 Transit Mixer Nos - 2

8 Backhoe Loader Nos 2 -

9 Diesel Tanker Nos 1 -


PROGRESS-II

• Camp Construction -We have identified the land for establishment of our camp construction. The main
camp shall be situated at Ch. 10+900 RHS (opposite to Rohini heliport) and camp-1 at Ch. 3+350 LHS.
• The C&G work has been completed for camp-1 and started for camp-2. simultaneously, Prefab material
shifting for camp construction is in progress.

• EHV Line shifting- Three agencies had visited the site and preparation of estimate is in progress for
shifting/raising of EHV line.

• Forest Permission for Tree Cutting- Site visit recently performed by forest department Delhi regarding
permission of tree cutting. One land of nearly 55 hectares has been identified near Ch. 5+100 for plantation
of tree.
KEY PLAN-I
KEY PLAN-II
KEY PLAN-III
TYPICAL CROSS-SECTION-I
TYPICAL CROSS-SECTION-II
TYPICAL CROSS-SECTION-III
SITE PHOTOGRAPH