Professional Documents
Culture Documents
IMPLEMENTING AUTHORITY
National Highways & Infrastructure Development
Corporation Ltd.
CONSULTANCY SERVICES
FOR PREPARATION OF
FEASIBILITY STUDY AND
DETAILED PROJECT REPORT
FOR TWO / FOUR LANE
BRIDGE INCLUDING
APROACHES OVER RIVER
BRAHMAPUTRA BETWEEN
DHUBRI ON NORTH BANK
AND PHULBARI ON SOUTH
BANK IN THE STATE OF
ASSAM / MEGHALAYA ON NH-
127B (LENGTH: 20km)
Client: Ministry of Road Transport & Highways Contract No. (if any): NIL
Government of India
SharePoint Ref.:
No.: CCU/TRA/DELD15021/NB:jp/2510
AM SB/RG NB/AK
R1 Inclusion of Dolphin Report
30/06/2018 30/06/2018 30/06/2018
JDM AG/SB/RG NB/AK
R0 For Approval
31/01/2018 31/01/2018 31/01/2018
Prepared by / Reviewed by / Approved by /
Revision Description
date date date
CONTENTS
Description
Page No
Chapter
VOLUME – IVA: EIA & EMP REPORT
(i)
Description
Page No
Chapter
8.0 Analysis of Alternatives 148-155
8.1 Impact Analysis 148
8.2 Project Benefits 158
LIST OF ANNEXURE
(ii)
LIST OF TABLES
Table 3.2: Value of Ambient Air Quality Results at Village Chagal Chora 41
Table 3.6: Value of the Noise along the proposed project locations 45
Table 3.7: Showing Test Results of Ground / Surface Water Samples 46-47
Table 3.9: Details of Available Sources, Location and Distance for Borrow soils 49
(iii)
LIST OF TABLES
Table 6-1: Scoping Matrix for the Proposed Bridge Option 100-105
Table 9.5: Environmental Management Plan for Pre construction stage 166-169
(iv)
LIST OF FIGURES
(v)
Description Page No.
Figure 3-19: Total Worker Population in Dhubri District 54
Figure 5-2: Alignment of Two / Four lane bridge between Dhubri and 91
Phulbari
Figure 9-2: Framework for Presentation of EMP during Construction and 163
O&M
(vi)
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
1.0. INTRODUCTION
In India, roads are one of most important modes of ground transportation as they constitute
85% of passenger transportation and 60% of freight transportation in India. However, the
development of the road network in mountainous regions of the Northeastern Region of
India has been much worse than the rest of the country. This is due to financial and
technical reasons. Thus, the Northeastern Region has suffered greater economic disparity
compared to other regions.
While 63.4% of the roads in India have been paved, only 28.5% of the roads in
Northeastern Regions are paved, out of which only 53% of the national highways are more
than 2lanes. This is because the Northeastern Region is located far from the major areas of
India. Furthermore, the roads leading to neighboring countries have been underdeveloped
due to security concerns.
The severe natural conditions of the Northeastern Region featured by steep mountains and
a prolonged monsoon season have also been obstacles for appropriately developing the
road network. Economic growth in this part of the country has therefore been much
delayed. The regional connectivity of the road network should promote cross-border trade
and commerce and help safeguard India’s international borders. This would lead to the
formation of a more integrated and economically consolidated South and Southeast Asia.
In addition, there would be overall economic benefits for the local population and would
promote the integration of the peripheral areas.
The approximate aggregate length of 10,000km of road in the Northeastern Region has
been identified for development. The development of the road network envisages creating
customized and specialized skills addressing issues like the complexities of geographical
terrains and the extensive coordination with the central and state governments.
The Government of India (GOI) thus launched in recent years the “Special Accelerated
Road Development Program for Northeastern Region” for which improvement of the road
network is of great importance. The GOI stated in their “Twelfth Five Year Plan (from
April, 2012 to March, 2017)” that the improvement of national highways in the
Northeastern Region should interconnect major cities within the region. It is within this
context that the GOI requested that the Government of Japan provides assistance in the
carrying out of the design work of two/four lane bridge including approaches over river
Brahmaputra between Dhubri on the north bank and Phulbari on the south bank in the State
of Assam / Meghalaya on NH-127B (length of 20km).
1.1.1 General
1.1.3 Brief Description Of Nature, Size, Location Of The Project And Its Importance To The
Country
The proposed project is the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km) on EPC Mode under JICA.
The climate along the proposed project is subtropical humid climate. The average annual
rainfall of the Dhubri District is 2,363 mm and 3300 mm in West Gharo District. The
variation in the rainfall from year to year is not large. The climate of the district is largely
controlled by South west monsoon activates from May and continues up to September-
October with about 65% rainfall occurring during the monsoon. The monthly evapo-
transpiration is about 40% of the rainfall, the highest in August, and lowest in January.
July/August is the hottest month when the maximum temperature is about 30°C.
December/January is the coldest month, as the mean daily minimum temperature is
recorded at 10 °C.
All major utilities will follow the Two/Four Lane Bridge construction as the proposed
project connects two major Town / District such as Dhubri District in the State of Assam
and West Garo District in the State of Meghalaya.
§ Proposed section of the bridge traverses between Dhubri on North Bank and
Phulbari on South Bank in the state of Assam/Meghalaya on NH-127B (Length:
20km)
§ Project aims at making Two / Four bridge over river Brahmaputra.
§ Proposed bridge length is 18.36 Km
§ Proposed ROW is 60 meter.
§ Proposed C.D works is 1 Nos Box Culvert(3mx3m)
§ No Sanctuary or National Park is located within 10 km radius of the proposed
project.
§ There are no major temples, schools or a Primary health centre is going to be
affected due to the proposed bridge.
§ The proposed bridge passes through a number of villages, few of them are
Chagalchora, Bhasani Char Part-1, Adabari part-2, Aironjongla, Aminer Char,
KotiaraglaGaon, Boushkata Char, Chaitar Char Part -2, Dhanabkuti Village, and
Phulwari. List of the affected villages are given in Table 1.2.
§ There will be a temporary impact during construction on water species that are
present in the Brahmaputra River along the project alignment.
§ There is no major wildlife migrant route within the study area, which could be
affected.
§ There is no historical monument which is protected by Archaeological Survey of
India (ASI) is affected due to proposed project.
The Environmental Impact Assessment study is carried out considering likely potential
impacts on physical, biological, socio-economic and cultural resources within
approximately 100 m each side of the project road. The important ecological sensitive area
up to 10 Km from the project road have also been covered in screening .This is in
accordance with the commonly accepted international standards. The 100 m study area is
considered adequate for the assessment of most physical and social effects arising from
project development. However, it is also recognized that a number of potential (positive
and negative) impacts could also have effects beyond this boundary, such as effects on road
linkages, employment effects, and some community activities. The important ecological
sensitive area up to 10 Km from the project road has also been covered in Environmental
Impact Assessment report.
located in the state of Assam & Meghalaya as shown in the Fig 1.1.
There are many village level small markets along the road. Venders sell vegetables and
other commodities along the roadsides. Thus blocking the road width available to the
traffic and also making the area prone to accidents. Noise level is some time higher in peak
hours of urban stretches for the road due to traffic movement. Bad condition road surface
leads to air pollution in some stretches. Table 1.2 provides details of list of villages falling
along the project road.
Design speed is the basic parameter, which governs the geometric characteristics of the
road. The proposed design speed for different terrain categories as per IRC: 73-1980 are as
follows: Environmental clearance: As per Ministry of Environment Forest and Climate
Change notification no. S.O. 2559 (E) dated 22nd August, 2013, MOEF&CC clearance is
only required for “Expansion of National Highways greater than 100 km involving
additional right of way or land acquisition greater than 40m on existing alignments and 60
m on re-alignments or by-passes.”. As per preliminary assessment, the project section will
not involve land acquisition of 60 m width for a length of approx. 20 km. Hence, it is
envisaged at this stage MOEF&CC clearance is not required for this proposed project.
However, the same will confirmed after finalisation of project parameters.
Forest clearance: During environmental screening survey, it is ascertained that there are no
forest land required for this proposed project. Hence, Forest clearance is not applicable.
However, this will be further verified during preparation of land acquisition plan.
Wild Life Clearance: During environmental screening survey, it is ascertained that there is
no sanctuary/national park exist within the 10 km radius from the project site and
accordingly it is confirmed that wild life clearance will not be applicable.
The following major activities are involved for the design and construction of proposed
project bridge:
§ Field surveys;
§ Consultation exercises with official and non-official sources; identifying existing
relevant baseline data;
§ Identifying the scope of baseline surveys required;
§ Identifying key issues to be addressed within the EIA,
§ Providing a technical brief for the EIA
In order to meet future traffic requirement, the proposed Construction of Two / Four
lane bridges including approaches to upgrade to achieve high speed of travel with
comfort and safety. Construction scheme is followed to minimise land acquisition
issues.
Pavement markings are proposed as per IRC: 35-1997, “Code of Practice for Road
Marking” with centre-line, edge line, continuity line, stop line, give way lines,
diagonal/chevron markings and zebra crossings. The pavement marking shall be of hot
applied thermoplastic paint with glass beads as per the MORT&H specification for
Road and Bridge Works, 2001(4th Revision, latest reprint). Appropriate bridge safety
measures are provided with stop signs, give-way signs, traffic merging and diverging
signs, lane closure signs, compulsory keep left/right signs or any other signs as per
IRC-67.
While developing the intersections design codes and standard drawings of Type design
will be followed.
Following are the expected benefits due to the improvement in the project bridge:
§ Better level of service in terms of improved riding quality and smooth traffic flow.
§ Faster transportation will ultimately lead to massive savings in the form of reduced
wear and tear of vehicles, reduced vehicle operating costs (VOCs) and total
reduction in transportation costs etc.
§ With the improvement of road surface, the traffic congestion due to obstructed
movement of vehicles will be minimized and thus wastage of fuel emissions from
the vehicles will be reduced.
§ Increased safety as people shift from boats to surface transport.
§ Enhanced connectivity between rural & urban population which will benefit the all
sections of the society like general population, small-medium-large scale industries,
farmers, businessmen etc.
§ Improved access to higher education facilities & modern health facilities.
§ Strengthening of both rural & urban economies which in turn will improve
economic scenario of the state and country.
§ Improved bridge connectivity helps in better implementation and management of
government schemes.
1.1.11 Various studies/reports being prepared for the project and how the environment screening
study relates to feeds into the overall project preparation
The various activities / components involved in the project include design process and
construction activities. Some of the major activities likely to take place to implement the
proposed up-gradation / improvement project are: Site clearing & grubbing, earthwork,
pavement removal, granular sub-base, water bound macadam sub-base / base, bituminous
pavement layers, pavement widening, drainage, safety measures, waste material
management, equipment staging & materials, aggregate and sand quarries etc. These major
activities have been taken into account while finalizing the methodology for the impact
assessment of the project. Table 1.1 provides details of Environmental Features.
Alignment
Illegal and / or improper § Only approved and licensed Quarries and Borrow pits shall be
mining permitted.
§ Non Productive, barren lands, raised lands, riverbeds are to be
recommended for borrow material
Location of Camps
Site selection/ Location § Labour Camp/ Construction camps should be located at least
of Labour Camp/ 500 m away from existing habitations and one kilometre away
Construction Camps from reserved forest.
§ All sites used for camps should be adequately drained and they
should not be subjected to periodic flooding.
§ Camps should be located such that drainage from and through
the camps will not endanger any domestic or public water
supply.
§ Living accommodation and ancillary facilities should be
erected and maintained to standards and scales approved by
the Engineer
§ Toilets and urinals should be provided in accessible places
away from the asphalt plant and mixing yard
§ Construction Camp should not be placed in ecologically
sensitive areas
Project Component for Details of Env. Features
Design
Utilities
Relocation of utility § Affected utilities like electric poles, water pipe lines, hand
lines / community pumps, etc. shall be relocated with prior approval of the
utilities. concerned agencies.
§ All the cultural properties that have been identified as affected
shall be relocated.
Road Safety
Clearance/ permission § NOC from State Pollution Control Board / statutory authorities
for establishment of Hot
mix plants/ Batching § NOC for quarry sites , Hot Mix Plant , Crushers
plants etc.
Noise Level § Improved traffic speeds and riding conditions shall reduce
noise levels
For Hot mix plant and § Noise screening by trees plantation scheme proposed as noise
construction machinery barriers
& At sensitive receptors. § Provide noise attenuation at critical locations like Hospital,
school etc.
Generation of Debris § All works will be carried out such that the damage or
from Dismantling disruption to flora other than those identified for cutting is
Structures and Road minimized.
Surface § Only ground cover/shrubs that impinge directly on the
permanent works or necessary temporary works will be
removed with prior approval from the Environmental Expert,
of Supervision consultant (SC). The concessionaire, under any
circumstances will not damage trees.
Fig.: 1.1: Location map of construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km)
It is therefore the JICA Study Team’s obligation to carry out EIA/SIA/RAP studies, which
supplement the environmental studies carried out by DPR consultants. Thereby additional
requirements short of JICA’s guidelines are fulfilled.
1.2.1 General
appointed as Consultants to carry out the preparation of EIA, SIA & RAP for proposed
Two/Four lane bridges including approaches over river Brahmaputra between Dhubri on
North bank and Phulbari on South bank in the state of Assam/Meghalaya on NH- 127 B
(length – 20 Km). The proposed bridge and approaches traverses in District Dhubri & South
Salmara - Mankachar in Assam & West Garo Hills in Meghalaya State.
The proposed project is the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km) on EPC Mode under JICA.
All major utilities will follow the Two/Four Lane Bridge construction as the proposed
project connects two major Town / District such as Dhubri District in the State of Assam
and West Garo District in the State of Meghalaya.
The following factors are considered in finalizing the proposed bridge/road alignment.
As per traffic forecast, the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km) are to be proposed.
The climate along the proposed project is subtropical humid climate. The average annual
rainfall of the Dhubri District is 2,363 mm and 3300 mm in West Gharo District. The
variation in the rainfall from year to year is not large. The climate of the district is largely
controlled by South west monsoon activates from May and continues up to September-
October with about 65% rainfall occurring during the monsoon. The monthly evapo-
transpiration is about 40% of the rainfall, the highest in August, and lowest in January.
July/August is the hottest month when the maximum temperature is about 30°C.
December/January is the coldest month, as the mean daily minimum temperature is recorded
at 10 °C.
All major utilities will follow the Two/Four Lane Bridge construction as the proposed
EIA and EMP Report 10 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
project connects two major Town / District such as Dhubri District in the State of Assam
and West Garo District in the State of Meghalaya.
There are many village level small markets along the road. Venders sell vegetables and
other commodities along the roadsides. Thus blocking the road intersection width available
to the traffic and also making the area prone to accidents. Noise level is some time higher in
peak hours of urban stretches for the road due to traffic movement. Bad condition road
surface leads to air pollution in some stretches. Table 1.2: provide details of list of villages
falling along the project alignment.
Table 1.2: List of the affected villages falling along the proposed project Alignment
Pavement markings are proposed as per IRC: 35-1997, “Code of Practice for Road
Marking” with centre-line, edge line, continuity line, stop line, give way lines,
diagonal/chevron markings and zebra crossings. The pavement marking shall be of hot
applied thermoplastic paint with glass beads as per the MORT&H specification for Road
and Bridge Works, 2001.
Appropriate road safety measures are provided with stop signs, give-way signs, traffic
merging and diverging signs, lane closure signs, compulsory keep left/right signs or any
other signs as per IRC-67. Advance cautionary signs are proposed for sharp curves along
with chevron signs at the outer edge of the curves.
The summary of the recommended design standard is shown in Table 1.3 below:
Level of Service : B
14m for 2-lanes with paved shoulders/ Granular
Roadway Widths (m) : Shoulder
20m for 4 lane divided carriageway with footpath
(inbuilt up areas)
26m for 4 lane divided highway (approaches to
grade separator)
Roadway Elements
: Carriageway
2-lane- 2X3.5m
4-lane(built up) 2X7.5m
4-lane at approaches to grade separator -2X7.5m
Median
4-lane( built-up)- 1.5m
4-lane at approaches to grade sperator-4.0m
Paved Shoulder
2-lane with PSS- 2x1.5m
4-lane at approaches to grade sperator-2X1.50m
Unpaved Shoulder
2 lane - 2X2m
4 lane - 2X2m
Camber Carriageway/Paved Shoulder- 2.00%
Unpaved Shoulder- 3.0%
Right of Way 60m for bypasses
45m for open areas for 4 lane road
24m for 2 lane road.
Embankment/ Cutting Slope In filling- 1V: 2 H
In cutting- 1V:1H
The proposed project is the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km) starting chainage Km00+000 in the
State of Assam and ending chainage Km19+282 in the state of Meghalaya.
India.
Forest clearance: During environmental screening survey, it is ascertained that there are no
forest land required for this proposed project. Hence, Forest clearance is not applicable.
However, this will be further verified during preparation of land acquisition plan.
Wild Life Clearance: During environmental screening survey, it is ascertained that there is
no sanctuary/national park exist within the 10 km radius from the project site and
accordingly it is confirmed that wild life clearance will not be applicable.
The following major activities are involved for the design and construction of proposed
project bridge. The proposed project is the construction of Two / Four lane bridges including
approaches over River Brahmaputra between Dhubri on North Bank and Phulbari on South
Bank in the state of Assam/Meghalaya on NH-127B (Length: 20km) on EPC Mode under
JICA.
The climate along the proposed project is subtropical humid climate. The average annual
rainfall of the Dhubri District is 2,363 mm and 3300 mm in West Gharo District. The
variation in the rainfall from year to year is not large. The climate of the district is largely
controlled by South west monsoon activates from May and continues up to September-
October with about 65% rainfall occurring during the monsoon. The monthly evapo-
transpiration is about 40% of the rainfall, the highest in August, and lowest in January.
July/August is the hottest month when the maximum temperature is about 30°C.
December/January is the coldest month, as the mean daily minimum temperature is recorded
at 10 °C.
The proposed project is the construction of Two / Four lane bridges carriageway of varies
from 7m &10.5 m for 2 and 3 lane carriageways respectively. Project Corridor
characteristics are given in Table 1.4.
The Environmental & Social Screening report was prepared after thorough interaction with
the engineering section of the consultants so that the negative impacts on the environment
and human population could be avoided as far as possible. Some of the important findings
of the study are as follows: -
§ There are no major temples, schools or a Primary health centre is going to be
affected due to the proposed bridge.
§ The proposed bridge passes through a number of villages, few of them are
Chagalchora, Bhasani Char Part-1, Aironjongla, Aminer Char, Katieralga Gaon,
Boushkata Char, Chaitar Char Part -2, Dhanabkuti Village, and Phulwari. Details of
the affected villages are given in Table1.2.
§ Proposed section of the bridge traverses between Dhubri on North Bank and Phulbari
on South Bank in the state of Assam/Meghalaya on NH-127B (Length: 20km)
§ Project aims at making Two / Four bridge over river Brahmaputra.
§ No Sanctuary or National Park is located within 10 km radius of the proposed
project.
§ There will be a temporary impact during construction on water species that are
present in the Brahmaputra River along the project alignment.
§ There is no major wildlife migrant route within the study area, which could be
affected.
§ There is no historical monument which is protected by Archaeological Survey of
India (ASI) is affected due to proposed project.
§ There will be likely impact on 24 households (roughly 144 people). Majority of
likely affected people belongs to Muslim religion. Out of 29 likely affected
households, there are 21 men and 3 women. Majority of them are literate. Almost all
the likely affected households are married.
§ All the likely affected HH are totally dependent on agriculture and fishing and that is
the only livelihood source. Very few are running small business like grocery etc.
§ A survey teams was mobilized to conduct the impact assessment and identify likely
affected people and assets. The initial survey covered 24 households. The survey was
conducted in the month of March 2016 under the supervision of consultants engaged
under the project.
§ The survey included basic socio demographic profile, livelihood and income, and
information on affected assets. Public Consultation was arranged in four different
locations like 1) Chagol Chora Part II, 2) Chaitar Char Part I, 3) Rawadari Part II and
4) Adabari
1.2.14 Objectives
The objectives of the EIA include: The policy of the Government of India with regard to
environmental assessment on different kinds of projects are laid down in ‘The
Environmental Impact Assessment Notification’, 2006, issued by the Ministry of
Environment, Forest and Climate Change, New Delhi. As per Ministry of Environment,
Forest and Climate Change Notification no. S.O. 2559 (E) dated 22nd August, 2013,
MoEF&CC clearance is only required for “ Expansion of National Highways greater than
100 km involving additional right of way of land acquisition greater than 40m on existing
alignments and 60m on re-alignments or by-passes.” It is envisaged at this stage MoEF&CC
clearance is not required for this project as per the above referred Notification. The State
Pollution Control Boards (SPCB) has been assigned the responsibility for implementing (i)
The Air (Prevention and Control of Pollution) Act, 1981 and (ii) The Water (Prevention and
Control of Pollution) Act, 1977. With regard to cutting of trees, etc., the Forest
(conservation) Act 1980 shall be referred.
Transport facilities including bridge/roads bring development. They not only facilitate
transportation and movement, but, as a whole, bring significant economic growth and social
benefits. It is a well-known fact that the economy and human welfare activities of an area
depend on its proximity to the bridge/road. Be it health, hygiene or education, be it
agriculture or business-almost all shades of human life are changed once a bridge/road is
developed in an area. The road allows cultures to mix and interact.
In regions where bridge/roads do not exist, they need to be developed at regular intervals in
view of the growing traffic pressure, road safety, travel time and the vehicle operating costs.
It also increases the access to markets, jobs, education and health services. Obviously, with
this intent the Government of India through National Highways and Infrastructure
Development Corporation (NHIDCL) undertook the required construction of Two / Four
lane bridges including approaches over River Brahmaputra between Dhubri on North Bank
and Phulbari on South Bank in the state of Assam/Meghalaya on NH-127B.
However, all is not rosy in bridge/road development. Whether a new bridge/road is laid, it
disturbs and destroys many more things. The new construction of the bridge/road may result
in loss of productive agricultural land, damage to sensitive ecosystems, removal of trees,
dislodgment of large number of people, disruption of local economic activities and
accelerated urbanization. The properties and people in many cases may fall in the direct path
of bridge/road construction. The livelihood of people is often disrupted. Such a
developmental project may cause soil erosion, interfere with animal and plant species, and
change the level of underground water. People may lose accustomed travel paths and
community linkages and can be culturally affected. The exhaust emissions will also grow
significantly leading to increase in respiratory and other health problems. Some of the
negative impacts may even have far-reaching consequences. One has to be very careful and
cautious in assessing these impacts and to then mitigate them.
In fact, it is easy to quantify the magnitude of physical impacts such as land clearance, trees
removed, and homes affected; but difficult to quantify effects on the biological and aesthetic
environment such as physiological alteration on flora & fauna, reproductive and behavioural
changes in organisms etc. The study therefore has been carried out with utmost care to
analyse, predict and mitigate the environmental and social aspects of the region in
consequence to the proposed bridge/road development.
The key potential environmental issue that may result due to proposed project intervention
is given in the following Table 1.7:
The geographical extent of this study is the area within a 10km radius of the proposed
bridge alignment as shown in the Figure below.
Fig.: 2.1: Satellite Image showing proposedconstruction of Two / Four lane bridges
including approaches over River Brahmaputra between Dhubri on North Bank and
Phulbari on South Bank in the state of Assam/Meghalaya on NH-127B (Length: 20km)
This bridge construction project entails to some extent anegative impact on the natural
environment as well as a social impact including a relatively large scale resettlement. The
survey covers not only direct and immediate impact but also secondary and cumulative
impacts in accordance with JICA guidelines. The survey items include air, water, soil,
waste, ecology, involuntary resettlement, the poor, livelihood, occupational safety, etc.
The legal framework and principles adopted for environment and social consideration of
the project have been guided by the existing legislation and policies of the Government of
India (GOI), the State Government of Assam and Meghalaya. Since the project is
considering getting assistance from JICA, the regulatory/legal framework should be
consistent with the national, state, local, as well as JICA Guidelines for Environmental and
Social Considerations.
This project extends to two states, the Assam and Meghalaya states, across the
Brahmaputra River. The Char lands (sand bars) in the Brahmaputra River which belong to
the Assam state will also be within the scope of land acquisition and resettlement. The
Char lands are unique in that the shapes change according to the changes in water level.
The area of the Char lands becomes smaller due to a rise in water level during the rainy
season (May to October) and expands in dry season (November to April). In this survey, a
census survey was carried out based on the list of villages and land plots prepared by the
district governments from the land acquisition map produced by DPR consultant (prepared
in June 2016). A Resettlement Action Plan (RAP) will be prepared in accordance with
relevant Indian laws and regulations, World Bank’s safeguard policy and JICA guidelines.
3.1.1 General
The environmental baseline data comprise the features present within a strip of 10 km or
affected area whichever is more on either side of the proposed alignment. This area is
referred to as study area/ project area in the report. It includes environmental features such
as forest areas, conservation areas, water bodies (rivers, lakes ponds and reservoirs),
industries, wildlife and, places of historical importance, tourism etc.
In order to understand the baseline environmental status and impacts due to the proposed
road widening, observations were made by repeated field visits. The relevant secondary data
were also collected. The methodologies adopted may be classified in the following way:
Questionnaires were prepared after thoroughly studying the environmental guidelines and
conditions of the Ministry of Environmental, Forests and Climate Change (MoEF&CC),
World Bank and Asian Development Bank. Questionnaires for Environmental appraisal for
Road / Highway projects by MoEF&CC were also taken into account while preparing
Questionnaire. Total four sets of questionnaires were prepared for field survey/data
collection. The details of these are as follows.
§ Environmental screening information like national parks, wild life sanctuary, forests,
archaeological, cultural, religious structures etc. within 10 Kms on both sides of the
road.
§ Environmental screening survey, effects on environment: views of the community.
§ The survey of features within Right of Way (ROW) on both the sides of the
proposed bridge/Road.
§ Wild life survey questionnaires for villagers, road users and forest guards
The entire stretch of present section was surveyed and screened. The collection of water
samples, soil samples and other data pertaining to air quality and noise were done within
ROW. The samples were analyzed in Noida Testing Laboratory, accredited by NABL.
Ambient air quality was monitored along the road at selected sites. The locations selected
were those of the city / town area, the market place and the rural areas. The details of
locations and monitoring results are discussed in Chapter – 4. The air quality parameters
considered for the study include Particulate Matter10 (PM10), Particulate Matter 2.5 (PM2.5),
Nitrogen Oxides (NOx) Sulphur Di-oxide (SO2), and Carbon monoxide (CO).
PM10 and PM2.5 were monitored using a Respirable Dust Sampler (RDS) and PM2.5 Sampler.
A pre-conditioned and weighted glass fiber filter paper is used for PM10 and PTFE filter
paper is used for RDS/PM2.5 samplers. A known quantity of the air was sucked through the
filter paper in a prescribed sampling time. The flow was noted from the manometer. The
multiplication of time with rate gave the total quantity of air passed through the filter paper.
After sampling, the filter paper was removed, conditioned, and weighed finally for getting
the concentrations in ambient air.
A known quantity of air was passed through impingers containing sodium hydroxide-
sodium arsenite solution. The estimation of NOx was done colorimetrically using hydrogen
peroxide, sulfanilamide, NEDA, etc. The intensity of the colour was measured at 540 nm
using a spectrophotometer.
Nondispersive Infrared detector (NDIR) based samplers are used to monitor the carbon
monoxide levels.
b) Water Quality
Samples of ground water were collected from hand pumps, wells and Tube-wells. To assess
the water Quality of the area samples were tested for physico-chemical parameters.
c) Soil Quality
The samples were collected from 60 m corridor of the road, at 5-15 cm depth. Besides
studying their texture (sand/silt/clay ratio) they were monitored for physico-chemical
parameters to assess the soil quality of the area.
d) Noise Level
The noise level (Leq) was measured using noise meter at various sites along the entire
stretch of road during day (6.00 am to 10 pm) and night (10 pm to 6.00 am).
The noise levels is expressed as an equivalent noise level (Leq) which is the measurement
duration of sound pressure level as the averaging time. It is calculated as follows:
Leq = 10 Log10 [ ån 1 ]
n/10
n10
19. Flora and Fauna Divisional Forest Office, Dhubri & West
Gharo District
Strip maps of 1 km each have been used in the process of conducting the screening survey.
All types of structures have been mapped on the ‘road –inventory.
Photographs of the important places such as villages, market places, old trees, consultation
with people, plantation areas, etc. were taken to confirm the baseline data of these areas.
The data collected by survey teams were compiled. Along with the field monitoring studies
and secondary data, these were used to identify the environmental problem spots or ‘Hot
Spots’.
The following analyses were carried out based on compiled information:
1) The levels of environmental parameters were compared with the prescribed limits
suggested by Central Pollution Control Board (CPCB). This gave a clear idea that
special attention is paid in areas where the level of pollution is higher than desirable.
Those stretches, where the pollution level does not exceed the desired limits despite
widening of the road will be dropped from further study.
2) The sites where the impact is minimum or nearly absent has been identified. This
may help in selection of major storage sites during construction work.
3) The mitigation measures have been suggested to reduce the adverse impacts due to
the proposed widening and detailed environmental management plan have been
prepared covering both the phases i.e. construction and operation of highway.
The proposed project is the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in the
state of Assam/Meghalaya on NH-127B (Length: 20km) on EPC Mode under JICA. The
proposed project is transverse at 89°58'16.99"E & 26°1'34.63"N at Dhubri on North Bank
and Phulbari on South bank transverse at 90°1'49.99"E & 25°52'12.03"N at an Elevation of
35 to 42 m above Sea level.
3.1.8.1 Seasons
The climate along the proposed project is subtropical humid climate. The average annual rainfall of
the Dhubri District is 2,363 mm and 3300 mm in West Gharo District. The variation in the rainfall
from year to year is not large. The climate of the district is largely controlled by South west
monsoon activates from May and continues up to September - October with about 65% rainfall
occurring during the monsoon. The monthly evapo-transpiration is about 40% of the rainfall, the
highest in August and lowest in January. July/August is the hottest month when the
maximum temperature is about 30°C. December/January is the coldest month, as the mean
daily minimum temperature is recorded at 10 °C.
Wind speed/Direction:
Generally, light to moderate winds prevail throughout the year with speed ranging from 1 to
19 kmph. Winds were light and moderate particularly during the morning hours, while
during the afternoon hours the winds were stronger. The wind rose diagram developed
during March 2016) shown in Fig. 3.1 reveals that pre-dominant wind direction occurs in
north east direction in Dhubri district and the average wind speed is 2.1 m/s.
The following Table 3.1 shows the Meteorological Data Parameters at Dhubri district
(March 2016).
Min Max Avg Min Max Avg Min Max Avg Avg mm
March
13.3 35.9 24.6 47 67 57 1003.6 1008.4 1006.0 7.7 NE 42.7
2016
3.1.9.1 Minerals
Assam is rich in mineral resources which are providing raw materials to industries. The
important mineral resources of Assam are petroleum, coal, natural gas and lime stone. Coal
fields are at Nazira, Makum, Margharita, Ledo, among others Crude oil is the most
important mineral product of Assam oil deposits are in Naharkatiya, Moran, Lanka, Nazira,
among others Oil refineries are established at Digboi, Noonmati and Bangaigaon and other
at Numaligarh. The natural gas from the oil fields is another important resource of Assam.
But only a small amount of natural gas in utilized in Assam and the rest is wasted lime stone
which is used as raw materials for cement is found at Garampani and Koilajan among
others. A map showing the regions of Assam which yield different types of minerals is
given below in Fig. 3.2.
In this study area, the Gondwana coal deposits in the western most part of Garo Hills of
Meghalaya is extending into the Hallidayganj area, Dhubri district of Assam and is known
as the Singrimari Coal deposits with a total resources of 2.79 million tonnes of non-coking
coal including the Meghalaya part of the coal deposits. A map showing the regions of
Meghalaya which yield different types of minerals is given below in Fig. 3.3.
Granite and granite gneisses occurring along the northern hills of the Shillong Plateau in
Goalpara, Kamrup and Nagaon districts are being quarried for use as building stone and
road metals. The quarry near Jagi road is well known. A number of similar quarries are seen
at several places near Guwahati by the side of National Highway 31 and 37. The pink and
grey granite found in parts of Karbi Hills and Goalpara and Dhubri districts are suitable for
production of decorative stones.
Agriculture / Forest:
Assam's economy is fundamentally based on agriculture. Over 70 percent of the state's
population relies on agriculture as farmers, as agricultural labourers, or both for their
livelihood. Assam produces both food and cash crops. The principal food crops produced in
the state are rice (paddy), maize (corn), pulses, potato, wheat, etc., while the principal cash
crops are tea, jute, oilseeds, sugarcane, cotton, and tobacco. Although rice is the most
important and staple crop of Assam, its productivity over the years has not increased while
other crops have seen a slight rise in both productivity and land acreage.
In Dhubri / South Salmara district, there are no major irrigation systems in the district.
However, minor irrigationschemes, such as lift irrigation schemes are mostly confined to the
selected areas.As per the land use pattern, the forest area is 291.55 sq. km, culturable waste
is 38.72 sq. km.
Source: http://cgwb.gov.in
West Gharo district has a forest area of 1650 sq. km., i.e. about 45% of the total
geographical area.The net area sown is 953.6 sq. km. and the total cropped area is 1207.4 sq.
km. Fallow land covers about 12%, net area sown is about 26%, while the total cropped area
is about 33%.Principal crops grown in the district are rice, maize, millets, oilseeds and
pulses. Horticulture products include orange, pineapple and banana. Vegetables like potato,
sweet potato, ginger, garlic etc. are also grown.
A map showing the regions of Assam and Meghalaya which yield different types of
agriculture / forest is given below in Fig.3.2 & 3.3respectively
STUDY AREA
STUDY AREA
STUDY AREA
STUDY AREA
STUDY AREA
STUDY AREA
STUDY AREA
Dhubri / South Salmara - mankachar district covers an area of 1664.10 sq. km. It is situated
in the extreme south-west corner of the state and has an international boundary with
Bangladesh on west and south west and is bounded by Kokrajhar district in the north,
Goalpara district on the east and north-east, GharoHills district of Meghalaya on the south
and Kochbehar and Jalpaiguri districts of West Bengal on the north-west.
Ground water conditions in the district can be described under two distinct hydrogeological
units, i.e. conditions prevailing in the consolidated formations and the conditions prevailing
in the unconsolidated formations. The net ground water availability estimated in the year
2009 is 1635.61 mcm. The existing gross ground water draft 181.12 mcm and the stages of
development are 11%only. Future provision for domestic and Industrial use is 65.35mcm
and for Irrigation useis 1432.85 mcm. A Hydro geological map showing the regions of
Dhubri and South Salamara - Manakchand given below in Fig. 3.6
Ground Water Quality in Dhubri / South Salmara - mankachar District:
The concentration of major, minor and trace element in the district is generally within the
limited range except iron. The iron distribution is abruptly high in and around Tamarhat and
Chapar area where it has exceeded the permissible limit of drinking.
The ground water is suitable for agricultural and industrial usages.
Ground Water Related Issues and Problems:
Frequent floods devastate the district every year during the monsoon months from May to
September. Flood accompanied with soil erosion and sand deposition cause maximum
damage to standing crops to the agricultural lands. Other than high iron content, most of the
chemical constituents are within the permissible limit.
Source: http://cgwb.gov.in
Recommendation:
Existing hydro geological set up and availability of huge ground water resources indicate
that there is much scope for the development of ground water with the construction of
abstraction structures in a planned and systematic way.
Surface Water source in West Gharo District:
The topography controls the drainage system as it divides the state into two water sheds
namely the Brahmaputra system in the North and Meghna /Surma system in the South.
The Tura ranges from watersheds in the West Garo Hills district from which the rivers flows
toward Bangladesh plains in the south and the Brahmaputra valley in the north and the
west. The important rivers of the north group are the Kalu, Ringgi and the Didak. The
important rivers of the southern group are the Bhogai, Dareng etc. River Simsang
(Someswari), one of the major rivers of Meghalaya (longest river in the Garo Hills districts),
whose valley is of the most important feature in the South Garo Hills and its chief tributaries
are Chibok, Rongdik, Rompa and Ringdi rivers. River Jinjiram starts from Derek village and
its main tributary starts from Upot Lake. It is the. River Ganol or Kalu starts from Tura peak
its chief tributaries are Dilni and Rongram rivers. River Didak stars from Anogre village and
runs through Gharo Hills district before it enters into Goalpara district. River Bugi, Rongai
and Dareng have their source in Nokrek Mountain. A River map showing the regions of
West Gharo district is given below in Fig. 3.7
inwater (higher than permissible limit prescribed by BIS, WHO), so the water supply
agencies should take precautionary measures to provide Iron free water for domestic and
industrial.
Source: http://cgwb.gov.in
Recommendation:
As ground water is poorly developed /exploited, dug wells are the preferred structures as of
now in low-lying areas and valleys. Hydrogeological studies indicate that lineament, joints,
fractures and fault are the main controlling factors for the occurrence and distribution of
ground water. These structures can be tapped for ground water development.
Springs play a major role in feeding water requirement of the people in rural areas. It is
found that the location of the spring is mainly restricted to foothills and intermontane
valleys. As the people in the rural areas of the district are totally dependent on springs, there
is an urgent need for scientific approach for proper development and management of it. It
may be recommended that the development of springs will help in mitigating the water
requirement of the people to a large extent.
Source: http://cgwb.gov.in
River
&
Hydrogeological map
Source: http://dhubri.gov.in/DMPLan&http://cgwb.gov.in
Source: http://cgwb.gov.in&http://bhuvan.nrsc.gov.in/
Physiographically, the district constitutes the vast alluvial plains of Brahmaputra River
system. The monotony of the flat alluvial tract is interrupted by the presence of Archaean
inliers in the form of disconnected hillocks referred to as inselbergs and these occur
specially in the eastern and southern parts of the district. These hillocks are joined by the
offshoots of Shillong plateau and are found on the north bank near Diple beel, Sitdanga beel
and east of Bilasipara and on the south bank of the foothill portion of Garo Hills along the
district boundary. The level difference between the valley and the peaks of the inselbergs
ranges from 25 to 455 m. These hillocks are covered by a thick lateritic mantel and are
occupied by evergreen mixed forest. Terraced alluvial deposits occupy80% of the district
with conspicuous occurrence of buried channels, back swamps, etc.
Soils in greater part of the district are sandy and silty loam, or clayey loam. It is found to be
highly acidic to slightly alkaline in nature and is moderately permeable and characterised by
the presence of low organic carbon and low soluble salts. Soils restricted to inselberg areas
are more clayey, lateritic and less permeable and are highly acidic in nature. From
EIA and EMP Report 37 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
agriculture point of view, the soils in major part of the area are suitable for all sorts of crops
cultivation. A Soil map showing the regions of Dhubri and South Salmara district is given
below in Fig. 3.8.
Source: http://cgwb.gov.in
Geomorphology and Soil in West Gharo district:
Geomorphologically, the district is an undulation one, with the E-W trending Garo hill
range of Central Upland zone and plains fringing the northern, western and the south-
western borders. The altitude of the Garo Hills District ranges from 23 m amsl to 1631 m.
amsl. The Garo Hills area comprises of the Tura Range, the Arbella Range and the Ranggira
Range .The Tura range is one of the most important mountain ranges in the West Garo Hills
which comprises of many peaks. Broadly, the district can be divided into the following
geomorphic units. A Soil map showing the regions of West Gharo district is given below in
Fig. 3.8.
§ Denudation Low and High Hills: It occupies the major part of the district comprising
of hard rocks like granite and gneiss.
§ Dissected Plateau: It is found in the southern portion of district comprising of soft
and friable rocks like shale, sandstone and quartzite.
§ Deep Gorges: In the southern parts of the district, Tertiary rocks comprising
sandstone, shale and limestone are dissected to form deep narrow elongated
intermountain valleys of tectonic origin along major lineaments.
§ Alluvial Plain: It is exposed in the northern, western and the south-western parts of
the district comprising fluviatile sediments.
Source: http://cgwb.gov.in
As per the plate tectonics, Assam& Meghalaya is in the eastern-most projection of the
Indian Plate, where the plate is thrusting underneath the Eurasian Plate creating a subduction
zone and the Himalayas. This led the state of Assam& Meghalaya fall under the seismic
zone V making the entire State prone to earthquake of moderate to very high intensity. The
State has experienced two major earthquakes in the year 1897 and 1950. The intensities of
these two earthquakes were 8.7 and 8.5 on the Richter scales respectively.
Combined with this hazard, is the vulnerability profile of the towns and cities where the
growth is haphazard and uncontrolled. Huge urban population combined with poor quality
and ill-maintained infrastructure, low quality building stock, and lower resilience of the
high–density society increases the risks to earthquakes in the urban centres. Moreover, urban
infrastructure is often designed and constructed without satisfying minimum safety
standards. A map showing the seismic zones of India is provided as Fig. 3.9.
STUDY AREA
There is no major source of Air pollution along the proposed project. The proposed project
covers settlements areas at, ChagalChora, Savodari, Motichora and Chaitarchar. The
ambient air quality was measured during March, 2016 at the above mentioned
locations/villages and results are presented in Table 3.2-3.5. The Results show that all the
parameters are well within the National Ambient Air Quality standards, 2009. Fig. 3.10,
3.11, 3.12 & 3.13 below shows the Ambient Air Quality concentrations at Village
ChagalChora, Motichora, Savodari and Chaitarchar respectively.
Table 3.2: Value of Ambient Air Quality Results at Village Chagal Chora
Results: In this study area the minimum concentration of PM10 is 54.9µg/m3 found at
village Chaitarchar and maximum concentration is 90.3µg/m3 found at village Chagal
Chora. The concentration is well within the National Ambient Air Quality Standards
(NAAQS).
The minimum concentration of SO2 is 5.9 µg/m3 found at village Savodri and NOx is 8.3
µg/m3 at village Chaitarchar whereas maximum concentration of SO2 is 10.2µg/m3 found
at village Chagal Chora and NOx is 22.2µg/m3 at village Chagal Chora. The concentration
is well within the NAAQS.
The noise levels are monitored at four locations during March, 2016 along the proposed
project to assess the baseline status of noise environment along the project. The Results are
presented in Table 3.6. The Noise levels are below as per National Ambient Air quality
standard w.r.t. Noise, 2000.
Table 3.6: Value of the Noise along the proposed project locations
The Water Quality was monitored at five locations along the proposed project, three ground
water & two surface water samples were collected. The results are presented in Table 3.7:
Results: In this Study area, the concentrations of Water quality are well within the desirable
/ permissible limit prescribed by the CPCB standard for drinking water except for
Bacteriological parameters for surface water.
The Soil Quality was monitored at four locations along the proposed project. The nutrient
values are good in soil and soil is predominately sandy clay in texture. The results are
presented in Table 3.8:
Borrow Soil:
The project road is passing through Dhubri / South Salmara Mankachar district of Assam
and West Gharo district of Meghalaya and plenty of soil is available adjacent to proposed
bridge / road side, which can be used as borrow materials after suitable testing. The details
of available source, location, average lead distance to the project roads and approximate
Table 3.9: Details of Available Sources, Location and Distance for Borrow soils
Approx.
Approx.
Sr. Type of Distance of
Name of Village Quantity Type of Land Remarks
No Material project
(Cum)
road (Km)
Clayey
1 Motichor 0.9 25000 Open Area
Silt
Chagolchora-1 Clayey
2 1.2 22500 Open Area
(Plashkhandi) Sandy Silt
Owner was not
Clayey interested to
3 Motichor 0.7 15000 Open Area
Silt share the rate &
mob No.
Owner was not
Adabari-1 Clayey interested to
4 1 10000 Open Area
(NabazotiGao) Silt share the rate &
mob No.
Clayey
5 Adabari-2 1.2 45000 Open Area
Silt
Open Area and
Clayey
6 ChagolChara 1.25 30000 Agricultural
Sandy Silt
Field
The land use in the proposed project area is mixed. The project corridor passes through
mostly water body / agricultural land along with barren lands. There are also some
settlements along the project road. Proposed Project Bridge / road is passing through Plain
terrain. Clay & sandy soil are mostly in along the project area. The land use pattern along
the proposed project bridge / road is given in the Table 3.10. The land use map based on
satellite imagery is given in to Fig. 3.15.
IRS-P6 LISS III (linear Imaging Self Scanner) Satellite imageries with spatial resolution of
23.5 meter GSD (ground sampling distance) at nadir, 4 band multi-spectral (0.52-0.59,
0.62-0.68, 0.77-0.86, 1.55-1.70) & 7 bit radiometric accuracy has been procured from
NRSA, India for the project road. General remote sensing data interpretation techniques
have been used and the colours and tone of features (relative brightness or colour of
objects) (e.g. like agricultural land is in red colour, Forest in dark red to deep red colour,
water bodies is in dark blue/black, settlements in cyan and wasteland is in greyish green)
identified. The pattern of the feature is spatial arrangement of visibly discernible objects.
(eg. Urban streets with regularly spaced houses, industries in square shape, water bodies in
amorphous shape etc.). After interpretation of all the features, the outer boundary of all the
features (Agricultural land, Forest land, Barren uncultivable waste land & Settlement
Urban & Rural) have been digitized and marked in the project area of 5km on either side of
the project road. The area percentage was then calculated and a graph generated
A land use map of the study area based on the satellite imagery in a scale of 1:25000
delineating the crop lands (both single and double crop), agricultural plantations, fallow
lands, waste lands, water bodies, built-up areas, forest plantation and other surface features
. Distribution of various land uses in the study area is shown in Table. 3.10.
Class in %
.1%
26%
2%
2%
2%
0.9%
3%
41%
2%
21%
STUDY
AREA
STUDY
AREA
Dhubri district is situated in the extreme western corner of Assam. This district is located
on the globe between 89.42 to 90.12 degree East longitude and 26.22 to 25.20 degree
North latitude. The district is situated at 30 meters above the sea level on average. The
river Brahmaputra flows through the district. On the Northern side of the river Dhubri and
Bilasipara Sub-Divisions are situated and on the Southern side newly carved South
Salmara-Mankachar District. The district of Dhubri is surrounded by the Kokrajhar district
in the north, Meghalaya & Bangladesh in the south, Bongaigaon & Goalpara district in the
east, West Bengal and Bangladesh in the west. The total area of Dhubri district is 2270
sq.km having a distance of about 290 km. from the State capital, Guwahati/Dispur. It has
two urban areas [Dhubri (Sadar), Bilasipara with a total urban population of 160939.
Previously, It had four urban areas [Dhubri (Sadar), Bilasipara, South Salmara and
Mankachar] covering an area of 27.24 sq. km., with a total urban population of 190546.
South Salmara-Mankachar is newly formed district has been carved out of Dhubri District
in 2015.
Administrative Division:
Administratively, Dhubri has three sub-divisions namely Dhubri, Bilasipara, along with
eight revenue circles (Tehsils) with fourteen blocks. The total number of revenue villages
in the district is 1133. The total number of Gram Panchayats is 168 covering these villages.
According to the 2011 Census, the total rural population of the district stands at 1444043
covering a rural stretch of 2810.76 sq. km.
Population:
As per the Census data 2011, 1,949,258 persons lived in Dhubri out of which about 88 per
cent are rural. About 70 per cent of the total population is from Minority communities of
which more than 95 per cent are Muslims. The population density of the district is 896
persons per sq Km, which is much higher than the state density of population i.e. 340
persons as per 2011 Census. The total male population of the district is 997848 and female
population is 951410.The total literate population of the district is 922341 out of which
about male literate population is 511551 and female literate population is 410790. The total
worker population in the district is 669819 out of which about total male worker population
is 524898 and female worker population is 144921.
Source: Census of India 2011, District Census Handbook, Dhubri
Dhubri is positioned at the bottom in the HDI list of Assam with considerable lags in the
development procedure of the district. The major HDI components of Dhubri district are
shown in the following Table 3.11
Relating to Gender related Development Index (GDI) also, Dhubri ranks at the lower part
of the list having 21st rank, just before Karimganj and Nagaon.
Economy:
Dhubri district is primarily dependent on agriculture and forest products. Main source of
income is paddy with surplus production along with cash crops including Jute and mustard
seed. From forest mainly timber and bamboo add to the income though boulder and sand
also available. Fish, milk, meat and egg have small contribution to the economy. Land
revenue collection is very small in amount whereas excise duty occupies a lion's share of
the Government exchequer. Devoid of any industrial production the district is considered
as one of the poor districts of Assam.
Livestock and Diary:
Livestock farming and dairying practices are common in the rural households of Dhubri
district. However, such activities have not properly been developed to be called for
commercial ventures
Transport and Communication:
The district mostly relies upon road transport. Air and water transport system have not
been well developed in Dhubri. Besides, railway connectivity is not sufficient to meet the
transport need of the people.
Besides housing standard of the rural people, the standard of living is also judged based on
the availability of certain basic community institutions in the rural locality along with easy
access to these. Safe drinking water, facilities for basic education and health, and social
security are some of the important elements of these basic requirements. There has been
development in the fields of education and public health in the district. However, the
development process has not so far been sufficient as per the requirements of the
households living in the district.
Administrative Division:
The name South Salmara-Mankachar comes from the Legislative constituency South
Salmara and Mankachar. South Salmara-Mankachar District was created by bifurcating
Old Dhubri district in 2016. On 15th August, 2015 Assam's Chief Minister Tarun Gogoi
announced 5 new administrative district in Assam; South Salmara Mankachar was one
among those. On 9th February, 2016 Commissioner inaugurated South Salmara-
Mankachar as an administrative district. At present there is only one sub-division. South
Salmara-Mankachar, Hatsingimari (Sadar).The district has 2 revenue circles and 2 tehsils.
It has 3 police stations and 1 census town namely Mankachar. There are two Assam
Legislative Assembly constituencies in this district: 21 Mankachar, 22 South Salmara. All
two are in the Dhubri Lok Sabha constituency. According to the 2011 Census, the total
rural population of the district stands at 528952 covering a rural stretch of 240.32 sq. km.
Population:
As per the Census data 2011, 555114 persons lived in South Salmara-Mankachar out of
which about 95 per cent are rural. About 70 per cent of the total population is from
Minority communities of which more than 95 per cent are Muslims. The population
density of the district is 977 persons per sq.km, which is much higher than the state density
of population i.e. 340 persons as per 2011 Census. The literacy rate of the South Salmara-
Mankachar district is 40 per cent as against 72.19 per cent of the state total. Of this, the
male literacy rate is 55.26 per cent and female literacy is 44.74 per cent.
Source: Census of India 2011, District Census Handbook, Dhubri
South Salmara-Mankachar district (old Dhubri district) is positioned at the bottom in the
HDI list of Assam with considerable lags in the development procedure of the district. The
major HDI components of South Salmara-Mankachar (old Dhubri district) are shown in the
following Table 3.12
Relating to Gender related Development Index (GDI) also, Dhubri ranks at the lower part
of the list having 21st rank, just before Karimganj and Nagaon.
Economy:
The district mostly relies upon road transport. Air and water transport system have not
been well developed in South Salmara-Mankachar district. There is no Railway station in
this district. There is no National Highway in the district. Transportation takes place
through state maintained pwd roads, which are full of potholes.
Besides housing standard of the rural people, the standard of living is also judged based on
the availability of certain basic community institutions in the rural locality along with easy
access to these. Safe drinking water, facilities for basic education and health, and social
security are some of the important elements of these basic requirements. There has been
development in the fields of education and public health in the district. However, the
development process has not so far been sufficient as per the requirements of the
households living in the district.
3.3.3 Socio-Economic Profile of West Gharo District (Meghalaya)
West Garo Hills, as the name suggests, is located in the western part of the State of
Meghalaya. The Garo Hills district was divided into two districts, viz. the West Garo Hills
district and the East Garo Hills district in October 1976. The erstwhile West Garo Hills
district was further divided into two administrative districts of West and South Garo Hills
on June 1992. The district headquarters of West Garo Hills is Tura, which is the second
largest town in Meghalaya after Shillong. The total area of the district is 3714 sq. km. As
the name suggests the district is mostly hilly with plains fringing the northern, western and
the south-western borders. West Garo Hills has three important mountain ranges viz. Tura
Range, Arbella Range and Ranggira Range.
Administrative Division:
Administratively the district is divided into three subdivisions viz. Tura, Phulbari and Dalu.
There are seven revenue circles and eight community development blocks (CD) in the
district. The total number of villages in the districts is 1507 of which 1469 are inhabited.
Under Article 244(2) of the Indian Constitution the provisions of Sixth Schedule is
applicable to the district.
Population:
As per the Census data 2011, the demographic profile of the district shows that 79.54
percent of the total rural population in the district belongs to the minority community, of
which Christians comprise 66 percent. The population density in the district which stands
at 175 persons per sq.km is significantly higher than the state average of 132 persons as per
the 2011 census. As per the Census data 2011, 643291 persons lived in West Gharo district
out of which about 324159in male population and 319132 is female population. The total
literate population of the district is 358702 out of which about male literate population is
193438 and female literate population is 165264. The total worker population in the district
is 255693out of which about total male worker population is 151914 and female worker
population is 103779.
Sex Ratio:
An important indicator of gender equality is the number of females per thousand males. As
per the 2011 census data, the sex ratio of West Garo Hills stands at 984 females per
thousand males while the child sex ratio for (0-6 years) is 960. Significantly, the sex ratio
for rural areas in the district stands higher than the district total. The sex ratio data shows
that gender parity among the Hindus is least among all the religious groups
Literacy:
The literacy rate in the district as per the Census, 2011 is lower (67.58) than the state
average (74.43). Although the female literacy rate in the urban areas of the district is more
than 80 percent, however in rural areas of the State female literacy rate is very low. The
rural literacy rate in the district is significantly lower than the State averages.
Economy:
The economy of West Gharo Hills district is basically agrarian in nature with about 80
percent of the population dependent on agriculture. Paddy is the major crop. The agro
climatic conditions of the district are conducive for various agricultural activities.
Agriculture in the district is characterized by dependence on rainfall, predominance of
seasonal crops and traditional methods of cultivation.
Tura, the headquarters of the district, is well connected by road with other places in the
district as well as with the rest of the Meghalaya and Assam. Bus services by Meghalaya
Transport Corporation and other private transport services connect Tura with all important
places in the districts of Garo Hills and also to Shillong (323 kms), the capital of the State.
The district headquarter is connected to Guwahati (220 kms), the capital of Assam, which
is also the nearest railhead and also to Siliguri in North Bengal. The town is connected to
Dhubri in Assam by road and river transport. Helicopter services are available from Tura to
Shillong and Guwahati. The National Highway 51 connecting Paikan on National Highway
37 in Assam with Tura, the district headquarter which extends further to Dalu, near the
Bangladesh border is the main road link for the district. However, rural road connectivity
in the district is fairly low as only 29 percent of the rural areas are reported to have paved
roads
Besides housing standard of the rural people, the standard of living is also judged based on
the availability of certain basic community institutions in the rural locality along with easy
access to these. Safe drinking water, facilities for basic education and health, and social
security are some of the important elements of these basic requirements. There has been
development in the fields of education and public health in the district. However, the
development process has not so far been sufficient as per the requirements of the
households living in the district.
3.3.4 Biological Environment
Biodiversity refers to the variety of life forms at all levels of organization, from gene
through species to higher taxonomic forms and also includes the variety of ecosystems and
habitats as well the processes occurring therein. Biodiversity is fundamental to the
fulfilment of human needs - a biodiversity rich region offers wide options and
opportunities for sustaining human welfare including adoption to changes.
India is one of the 17 Mega bio diverse countries in the world and accounts for 7-8 % of
the recorded species. The State of Assam is a constituent unit of the Eastern Himalayan
Biodiversity Region; one of the two biodiversity “Hot Spots” in the country .The climatic
condition and wide variety in physical features witnessed in Assam have resulted in a
diversity of ecological habitats such as forests, grasslands ,wetlands, which harbour and
sustain wide ranging floral and faunal species placing
However, today, Assam is not only more fancied, but also known for its ecological
diversity, for the range of floral and faunal species and for the conservation successes
achieved. Kaziranga, Manas, Pobitora, Orang, Dibru-Saikhowa are names recognized
world over and bring laurels to the people of this magnificent State.
Meghalaya is situated in the North East India Bio-geographic zone (along with Assam,
Nagaland, Manipur, Mizoram and Tripura) which is a significant region as it represents a
transition zone between the Indian, Indo-Malayan, Indo-Chinese bio-geographic regions as
well as a meeting place of Himalayan mountains with that of Peninsular India. The region
is one of the richest in biological values with vegetation types ranging from tropical rain
forest in the foothills to Alpine meadows and cold deserts.
The state also represents an important part of the Indo-Burma biodiversity hotspot which is
one of the 4 bio-diversity hotspots present in India and 34 in the world.
The state of Meghalaya has been identified as a key area for biodiversity conservation due
to its high species diversity and high level of endemism.
Diverse Plant Communities:
In the “Revised Survey of Forest Types in India”, Champion and Seth categorized as many
as fifty one different forest types/ sub types for this region. But, the species diversity is so
spectacular that it becomes often difficult to clearly identify separate riche to existing plant
formations. However, broadly speaking the forest in Assam can be described into
following types/ sub types.
§ Tropical Wet Evergreen Forests.
§ Tropical Semi Evergreen Forests.
§ Tropical Moist Deciduous Forests.
§ Sub-tropical Broadleaf Hill Forests.
§ Sub-tropical Pine Forests.
§ Littoral and Swamp Forests.
§ Grassland and Savannahs.
Moist Deciduous Forests can further be described as Sal Forests and Mixed Deciduous
Forests. Sal Forests occupy considerable forest area in the Central and Lower parts of
theState in the Districts of Nagaon, Morigaon, Kamrup, parts of Nalbari and Barpeta,
Darrang, Dhubri, Kokrajhar and Goalpara.
In these forests, Sal grows in association with Lagerstroemia species (Jarul, Ajar),
SchimaWallichii (Ghugra), Stereospermumpersonatum (Paruli), Adina cordifolia (Haldu),
Artocarpus species ( Sam), Ficus species( Bor, Dimoru, Dhupbor, Bot, Athabor, tengabor,
Lotadioru, Khongaldimoru), Bischofiajavanica (Uriam), Gmelinaarborea (Gomari),
Micheliachampaca (Teetachampa), Terminalia species (Hilikha, Bhomora, Bohera). Toona
ciliate (Poma) etc.
The floral diversity of Meghalaya is well reputed for its richness and has been a centre of
attraction for many botanists. The presence of a large number of primitive flowering plants
has prompted Takhtajan (1969) to call it the Cradle of Flowering Plants’. Meghalaya
harbours about 3,128 species of flowering plants and contributes about 18% of the total
flora of the country, including 1,237 endemic species (Khan et al 1997). A wide variety of
wild cultivable plants, edible fruits, leafy vegetables and orchids are found in the natural
forests of Meghalaya. However due to overexploitation, deforestation and habitat
destruction many endemic and threatened species are now mainly confined to the protected
areas and sacred groves.
According to Champion & Seth (1968), major forest types in the state of Meghalaya are:-
§ Assam Sub-tropical Hill Savanna
§ Khasi Sub-tropical Hill Forests
§ Assam Sub-tropical Pine Forests
§ Assam Sub-tropical Pine Savannah
Haridasan & Rao (1985-87) recognized the following major categories of vegetation in
Meghalaya based on altitude, rainfall and dominant species composition:
Tropical Moist and Dry Deciduous Forest: This is a very prominent vegetation of
Meghalaya covering a large part of East and West Garo Hills, Ri-bhoi districts etc, in areas
of annual rainfall less than 1500mm and high temperature. These forests are characterised
by seasonal leaf shedding and profuse flowering. The dominant tree species which are
valued economically are Shorearobusta, Tectonagrandis, Terminaliamyriocarpa,
Gmelinaarborea, Artocarpuschapsala, Lagerstroemia parviflora, Maoruslaevigata etc. Other
Of the total 3,331 plant species recorded in the state Meghalaya around 834 (25.04%) are estimated
to be employed in healthcare. These species are distributed in 548 genera and 166 families. The
family with the highest number of medicinal plant species is Rubiaceae followed by Asteraceae and
Fabaceae. These species are restricted mainly to sacred groves, community forests and reserved
forests and some to grasslands, roadsides, cults and fields, etc.
Fig 3.23: Forest Map of Dhubri / South SalmaraMankachar in Assam and West
Gharo District in Meghalaya
The district has vast potential for development of plantation and horticultural crops. There
has been an impressive growth of horticultural crops in the district in recent years. At
present horticultural crops are cultivated in 47150 with fruits and nut crops 20000 hectares,
vegetables 11000 hectares, root and tuber crops such as tapioca, colocasia, sweet potato
etc. in 6200 hectares. Besides, other horticultural crops are also cultivated in the district.
Most of these horticultural crops are cultivated in traditional ways. Therefore, the yield and
quality of these products are not up to the commercial grades available in 15 the market.
Government record reveals that there are about 19300 hectares of additional area which
can be brought under horticulture with minimum effort.
Source: http://www.icssr.org/Dhubri
The total forest cover in West Gharo Hills district is 2022 sq. km (54.42 percent) of the
total land area which comprises of 1040 sq. km of open forest and 607 sq. km of dense
forest. The district has a total of 19.21 sq. km of reserved forest comprising of Dibru Hills
(15.02sq.km) and Tura Peak (4.19 sq. km). The table below shows the forest type
classification for West Garo Hills district.
Source: http://www.icssr.org/
4.1.1 General
The Government of India has laid down various policy guidelines, regulations, acts and
legislations pertaining to sustenance of environment. The following Table 4.1 shows the
relevant environmental legislations and implementing agencies.
During the construction stage, some of the key statutory requirements that need to be
obtained by the Contractor as part of mobilization (pre-construction) have been listed in the
Table 4.2 given below.
1989
Dept. of Mining;
Quarries (in case of opening
4 Environment Protection Act, 1986 Concerned District
of new quarries)
Administration
The World Bank's environmental and social safeguard policies (ten of them) are a
cornerstone of its support to sustainable poverty reduction. The objective of these policies
is to prevent and mitigate undue harm to people and the environment in the development
process. These policies provide guidelines for the identification, preparation, and
implementation of programs and projects. The following Table 4.3 shows operational
policies are relevant in context of the Project from an environmental viewpoint:
The implementation of the policy ensures that envisaged forest sector activities and other
Bank sponsored interventions which have the potential to impact significantly upon
forested areas:
1. Do not encroach upon significant natural forest areas that serve important social,
environmental or local economic purposes.
2. Do not compromise the rights of local communities to continue their traditional use
of forests in a sustainable fashion.
3. Do not finance commercial logging operations, in the case of primary tropical
moist forest, nor any purchase of equipment for this purpose.
The World Bank Policy OP/BP 4.11 defines physical cultural resources as movable or
EIA and EMP Report 71 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
immovable objects, sites, structures, groups of structures, natural features and landscapes
that have archaeological, paleontological, historical, architectural, religious, aesthetic, or
other cultural significance. Physical cultural resources may be located in urban or rural
settings, and may be above or below ground, or under water. Their cultural interest may be
at the local, provincial or national level, or within the international community.
The Bank assists countries to avoid or mitigate adverse impacts on physical cultural
resources from development projects that it finances. The impacts on physical cultural
resources resulting from project activities, including mitigating measures, may not
contravene either the borrower’s national legislation, or its obligations under relevant
international environmental treaties and agreements.
The borrower addresses impacts on physical cultural resources in projects proposed for
Bank financing, as an integral part of the Environmental Assessment (EA) process.
The ADB’s Environment Policy mandates the consideration of environment in all aspects
of ADB’s operations. The “Environment Policy and Operations Manual (OM) 20:
Environmental Considerations in ADB Operations” outlines ADB’s environmental
assessment procedures and requirements. In 2003, ADB updated the old guidelines of 1993
and the contents are summarized as follows:
the impacts;
f. Recommend environmental mitigation measures and estimate the mitigation costs;
g. Prepare an EMP to be implemented by the executing agency during project
implementation, operation and abandonment;
h. Prepare the EIA and SEIA reports;
i. Conduct public consultation and ensure information disclosure; and develop plans
for public consultation and information disclosure during project implementation;
j. Assess the executing agency’s capacity to undertake an environmental review of the
environmental assessment report and EMP recommendations, and recommend
measures for capacity building if necessary;
k. Ensure that the proposed project, with EIA and EMP implementation, conforms to
the Government and ADB environmental assessment requirements, policies and
regulations.
l. Economic assessment that should be carried out includes i) the costs and benefits of
environmental impacts; ii) the costs, benefits, and cost effectiveness of mitigation
measures; and iii) for environmental impacts that have not been expressed in
monetary values, a discussion of such impacts, if possible, in quantitative terms.
The JICA guidelines, World Bank and ADB Operational Manual and Environmental
Safeguard policies, procedures & practices described in the Section 9.3.7 to 9.3.9 are
compared to the following Government of India’s guidelines in order to find the
differences and elaborate on a way to fill in the gaps if any.
Based on the above, a study on India’s laws and regulations, and comparing them to the
JICA/WB/ADB Guidelines is carried out in the following stages:
· The baseline environmental information in the study area such as; climate,
physiographic features, drainage, geology, flora, fauna, ambient air, water and noise and
socio-economic conditions.
· Reviews of the literature, laws and guidelines and discussions with concerned agencies
and organizations, National/State Authorities
· A reconnaissance survey along with public consultation that occurred from October
2016 to July 2017 and processes of public consultation continued until the completion of
the study to inform the people about the project and collect the information/suggestions
on environmental issues.
· The monitoring network with regard to air, water, soil and noise pollution.
· Assessment of the potential significant impacts and identification of the mitigate
measures to address impacts adequately.
· Field observations including public consultation.
· Screening, testing and monitoring of environmental factors like air, water, soil and the
noise level.
· Collection of secondary data from various departments.
· Compilation, analysis and presentation of the report.
Table 4-4: Comparison between JICA Guideline and Laws in India regarding EIA
Principle for this
No. Items JICA Guideline Laws in India
Project
1 Requirement Environmental and Projects requiring EIA EIA will be
of EIA social surveys at the (Category A projects) prepared as
EIA level (Category i) New National category A in
A projects) Highways accordance with
Proposed projects ii) Expansion of JICA Guidelines
likely to have National Highways though not required
significant adverse greater than 100km by Laws in India
impacts on the involving an additional
environment and right of way or land
society. Category A acquisition greater than
includes projects in 40m on the existing
sensitive sectors (ex. alignments and 60m on
Roads, railways, and re-alignments and
bridges), projects bypasses.
that have
characteristics that Projects whose
are liable to cause requirements of EIA
adverse are judged by the state
environmental level Environment
impacts (ex. Large- Impact Assessment
scale involuntary Authority (Category B
resettlement), and projects)
projects located in or i) State Highway
near sensitive areas. ii) State highway
IEE level (Category Expansion projects in
The proposed Dhubri-Phulbari Bridge has been initiated and is being carried out by the
National Highways and Infrastructure Development Corporation Limited (NHIDCL),
under the auspice of the Ministry of Road Transport & Highways (MORTH). Though the
primary responsibility of the Project rests with the NHIDCL, there are various institutions
involved in the Project and their level of responsibilities in the project implementation are
as follows:
The National Highway Authority of India (NHAI) and Regional Offices under the Ministry
of Road Transport and Highway (MORTH) promote the national highway development
project while the Border Roads Organization (BRO) under the Border Roads Development
Board (BRDB) has control over roads in border regions. The NHIDCL was established for
promoting the development of National Highways in North East and border areas of India,
and started operation from January 1st , 2015.
The NHAI has been established under the National Highways Authority of India Act of
1988. It is the main nodal agency responsible for developing, managing and maintaining
India’s network of national highways. It became an autonomous body in 1995. NHAI
maintains 70,934km of national highways and expressways across India.
The development of the Dhubri-Phulbari Bridge project has been promoted by NHIDCL,
which is a company fully owned by the Ministry of Road Transport & Highways of the
Government of India. The function of the NHIDCL is to promote the surveying, designing,
building, operating, maintaining and upgrading of national highways and the development
of strategic roads such as interconnecting roads in various parts of the country including
those in areas with international boundaries with the neighbouring countries.
The company also proposes to improve road connectivity and the efficiency of the
international trade corridors by expanding about 500km of roads in the North Bengal and
North-eastern Region of India.
Statutory authority attached to the MOEFCC, the main responsibilities of CPCB include
the following:
- Planning and implementing water and air pollution control programs;
- Advising the central government on water and air pollution control programs;
- Setting air and water standards; and
- Coordinating the various State Pollution Control Boards.
The role of the CPCB for this Project will only be in an advisory capacity while the Project
shall adhere to the norms and standards set up by the Meghalaya State Pollution Control
Board (MSPCB).
The Public Works Department (PWD) is the premier agency of the state government
engaged in planning, designing, construction, and maintenance of the government assets in
the field of infrastructure development. Assets in infrastructure development include roads,
bridges, urban centers, footpaths, new capital complexes, and airports. Assets such as
hospitals, schools, colleges, technical institutes, police buildings, prisons, and courts
among others are also under the PWD’s jurisdiction. PWD Assam / Meghalaya also
sustains and preserves these assets through a system of maintenance, which includes
specialized services such as rehabilitation works, roads signage, and aesthetic treatments
like interiors, landscaping etc.
MOEFCC has set up regional offices that cover the Northeastern Region including Assam /
Meghalaya. It is located in Shillong, Meghalaya. This office is responsible for collecting
and furnishing information relating to the EIA of various projects in respect topollution
control measures, methodology, and status, legal and enforcement measures and
environmental protection in special conservation areas such as wetlands, mangroves and
biosphere reserves.
(3) State Pollution Control Board, Assam / Meghalaya State Pollution Control Board
The State Pollution Control Boards have the mandate for environmental management at the
state level, with emphasis on air and water quality. It is responsible for the planning and
executing of state-level air and water initiatives, advising the state government on air,
water and industry issues, establishing standards based on the National Minimum
Standards, the enforcing and monitoring of all activities within the state under the Air Act,
the Water Act and other relevant acts pertaining to pollution control.
They also conduct and organize public hearings for projects as defined by the various Acts
and as stipulated by the amendment related to the EIA Act. It also issues No-objection
Certificates (NOC) for environment clearance for industrial development defined in such a
way as to include road projects’ quarrying etc., which usually relate to water and soil
contamination.
The Assam / Meghalaya Forest and Environment Department is responsible for the
protection and management of the forest areas in the states that are designated for
protection, conservation and production purposes. The Forest and Environment Department
follows what is laid out in the Forest Working Plans for the various forest divisions to
manage and protect the forest resources. These plans form the basis for managing the forest
resources. is the department is responsible for granting licenses for clearances of the forest
areas for various projects, according to the provisions of the Forest (Conservation) Act,
1980.The State Forest and Environment Department performs functions similar to those of
the MOEFCC at the state level but more specific to forestry activities including social
forestry and production forestry development and licensing.
Environmental Clearance is not required for this project as per the MoEFCC notification,
2013.
Other clearances required are as follows:
1) The Contractor has to obtain permits from State Pollution Control Board for setting
up hot-mix plants, batching plants, etc., under the Air and the Water Acts;
2) Clearance from the State Department of Mining is required for establishing
quarries;
3) Clearance from the Water resource department/Authorities is required for
establishment of new tube-wells/bore-holes in case they are required during construction
work;
4) The provisions as laid down in the Factories Act, 1948, Labor Act, 1988 and the
Building and Other Construction Workers (Regulation of Employment and Conditions of
Service) Act, 1996 with respect to hygiene and health during the construction stage would
apply to the project’s implementation works; and
5) The provisions of the Hazardous Wastes (Management and Handling) Rules, 1989
and the Chemical Accidents (Emergency Planning, Preparedness, and Response) Rules,
1996 may also be applied during the construction and the operation period.
Based on the Acts and Rules above, CPCB has set up various environmental standards as
follows:
Compared to the EHS guideline set forth by the International Financial Corporation (IFC) shown
in table 4.8-4 below, the Class A Water Quality Standard of India is lacking a few items such as
COD, Total Nitrogen, Total Phosphorus, Oil and Grease. Other parameters are set at equal level or
below the EHS Guideline of IFC.
Source: IFC
All road works in India are to be in accordance with the MoRTH specifications for Road
and Bridge works and guidelines of Indian Roads Congress (IRC). The MoRTH
specifications have special provisions towards protection of environment under Clause 501,
Annexure A and the contractor is to satisfy the provisions. Apart from the Annexure A to
clause 501, there are provisions for control of erosion, drainage, dust suppression, borrow
area and haul road management under relevant sections. Provisions of clause 501 Annexure
A, cover the environmental aspects as:
In addition to the above conditions, avoidance measures and control of activities having
potential for generation of environmental impacts are devised. These include:
Environmental issues during road construction stage generally involve equity, safety and
public health issues. The road construction agencies require complying with laws of the
land, which include inter alia, the following:
§ The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of
Forest Rights) Act, 2006. This act recognizes forest dwellers rights and makes
conservation more accountable.
§ The provision of (Extension to the Scheduled Areas) Act, 1996 (PESA). The PESA
provisions are intended to intrinsically protect the resources of the tribal
communities and empower them to act against the forcible acquisition.
§ Workmen's Compensation Act 1923: The Act provides for compensation in case of
injury by accident arising out of and during the course of employment;
§ Contract Labour (Regulation and Abolition) Act, 1970: The Act provides for
certain welfare measures to be provided by the contractor to contract labour;
§ Minimum Wages Act, 1948: The employer is supposed to pay not less than the
Minimum Wages fixed by appropriate Government as per provisions of the Act;
§ Payment of Wages Act, 1936: It lays down as to by what date the wages are to be
paid, when it will' be paid and what deductions can be made from the wages of the
workers;
§ Equal Remuneration Act, 1979: The Act provides for payment of equal wages for
work of equal nature to Male and Female workers and not for making
discrimination against Female employees;
§ Child Labour (Prohibition and Regulation) Act, 1986: The Act prohibits
employment of children below 14 years of age in certain occupations and
processes and provides for regulation of employment of children in all other
occupations and processes. Employment of child labour is prohibited in Building
and Construction Industry; Inter-State Migrant Workmen’s (Regulation of
Employment and Conditions of Service) Act, 1979: The inter-state migrant
workers, in an establishment to which this Act becomes applicable, are required to
be provided certain facilities such as housing, medical aid, travelling expenses
from home to the establishment and back, etc.;
§ The Building and Other Construction Workers (Regulation of Employment and
Conditions of Service) Act, 1996 and the Cess Act of 1996: All the establishments
who carry on any building or other construction work and employs 10 or more
workers are covered under this Act; the employer of the establishment is required
to provide safety measures at the building or construction work and other welfare
measures, such as canteens, first-aid facilities, ambulance, housing accommodation
for Workers near the workplace, etc.;
§ The Factories Act, 1948: The Act lays down the procedure for approval of plans
before setting up a factory, health and safety provisions, welfare provisions,
working hours and rendering information-regarding accidents or dangerous
occurrences to designated authorities;
§ Hazardous Wastes (Management and Handling) Rules, 1989: Occupiers generating
hazardous wastes given in the list shall take all practical steps to ensure that such
wastes are properly handled, i.e. collection, reception, treatment, storage, and
disposal of without any adverse effects to human health and environment (Rule 4
Such occupier shall apply for authorization in prescribed format to the State
Pollution Control Board)
§ Chemical Accidents (Emergency Planning, Preparedness and Response) Rules,
1996: The Rules provide for mandatory preparation of On-Site Emergency Plans
by the industry and Off-Site Plans by the district collector and the constitution of
four tier crisis groups at the centre, district, and local levels for the management of
chemical disaster.
4.9.3 Institutional Strengthening And Arrangement
Though rich in legal and regulatory instruments, the implementing agencies are unable to
regulate and monitor a sound environmental management plan due to lack of enforcement
capacity. Therefore, violations or missed mitigation commitments often go unreported. The
gaps and deficiencies pointed out can be removed by proper arrangements. Institutional
strengthening component has accordingly been identified. As such, the overall arrangement
is as follows:-
1. Organizational Arrangements
2. Environmental Training
Training of staff will be done at a number of levels. Some short-term training is required
for the Environment Manager, other staff members of the Environment Unit and the
contractor staff to raise their levels of environmental awareness. The Environment and
Natural Resources Division and the State Pollution Control Boards conduct the training
programs, and their help will be sought in this regard. In the long-term training, the
specialized training or special environmental issues will be examined and provided to the
Environment Unit
3. Environmental Monitoring
In order to ensure that the prescribed environmental norms are maintained during the
constructional and the operational phases, the regular monitoring is one of the most
important components of the institutional arrangement. The regular monitoring of Air
pollution, Water quality, Noise pollution, and maintenance of trees, etc. will be done at
regular intervals. The field reports of various environmental components will be received
at quarterly basis, and any lapse has to be taken care of.
Awareness training will be provided to the contractors and their personnel to ensure that
the EMP is implemented effectively. The project co-coordinator will assess the contractor
practices and, if high pollution levels are suspected, will government or private sector
laboratories check them.
1. Zero Option
No project intervention is implemented, i.e. present status i.e. transportation by boats, is to
be continued to be used;
Figure 5-1: The Alternative Route connects Dhubri and Phulbari by widening of
existing NH-31 B and SH-46 through existing bridge near Goalpara
Assam/Meghalaya on NH-127B (Length: 20km) with minimum PAPs. In this option, three
alternative alignments were compared in order to minimize the social and environmental impacts.
Figure 5-2: Alignment of Two / Four lane bridge between Dhubri and Phulbari
Others
- If it is worth implementing the project despite effects on
the natural/social environment, or economic conditions
- Technical viability of the bridge construction
a. Positive Impacts
- There will be no involuntary resettlement involved in the Zero Option
- No tree cutting and agricultural areas lost to the road / bridge construction works
- No construction works and no pollution
- No impact on Aquatic Fauna
b. Negative Impacts
- No road network between Dhubri and Phulbari
- Existence boat transportation takes more time and inconveniences the people
- No local area development
- No Economic development in project districts
a. Positive Impacts
- Provide transport connectivity to Dhubri and Phulbari
- Land acquisition and involuntary resettlement will be incurred but on a smaller scale
b. Negative Impacts
- Significant negative impacts on the ecosystem of the Brahmaputra River by the
dredging of ferry terminals
The Alternative Route connect Dhubri and Phulbari by widening of existing NH-31 B
and SH-46 through existing bridge near Goalpara
The Alternative Routes to connect Dhubri and Phulbari through NH-31 B and SH-46 and
utilize the existing bridge near Goalpara will have approximately 200km length.
a. Positive Impacts
- Better connectivity to villages / towns falling in the 200km alignment
- Overall economic development of the project area
- No impact on Aquatic ecology of Brahmaputra River
b. Negative Impacts
- Very high resettlement as settlements are all along the existing highway
- Acquisition of land and cutting of large numbers of trees
- Construction works likely to cause significant traffic jams throughout the construction
period, dust during dry season and muddy roads during rainy season.
- Very high construction cost due to long length
The proposed Bridge is the construction of two Four-lane bridges including approaches
over Brahmaputra River between Dhubri on the North Bank and Phulbari on the South
Bank in the state of Assam/Meghalaya on NH-127B (Length: 20km) with minimum PAPs,
This option is assessed as follows:
a. Positive Impacts
- Provide easy and short distance connectivity to Dhubri and Phulbari
- Less number of PAPs
- Overall infrastructure development.
- Overall economic development of the area
b. Negative Impacts
- Involuntary resettlement of the local residents will be reduced, however, in acquisition of
approximate 65 Ha of land and significant number of PAPs.
- Construction works should cause significant traffic jams throughout the construction
period, dust during dry season and muddy roads during rainy season.
- Increase of traffic volume including heavy load vehicles likely tocause noise and vibration
along the road while some traffic is diverted to bypasses.
- Impact on aquatic fauna in Brahmaputra River during construction phase.
Given the above analysis results, the results of comparing and examining each option were
ranked and are shown in the table below. Furthermore, the score was allocated according to
the rank, and the option with the highest total score was selected as the best. The main
objective of this project is to bring positive influence on the regional economy, so the
“impact on local economy” was given a double score. As a result, The Proposed Bridge
Option is recommended.
The methodology is adopted to review these three alignments by covering the following
aspects:
· Social Aspects
· Environmental Aspects
· Engineering Aspects
· Indicative Cost Aspects
For each aspect, the following parameters were used for assessment and comparison.
Social Aspects
The number of affected structures is considered as an equivalent to the scale of resettlement
expected from the Project. Size of Land to be acquired is indicative of the scale of possible
losses of livelihood considering that the population in the area is largely dependent on their
land. The length of alignment passing through Permanent Char Land is also included in the
parameters to evaluate the impact on Char people whose socio-economic status is lower
than that of the inland communities.
Environmental Aspects
Total length is indicative of negative impacts such as noise, vibration, and air pollution at
operation phase. As the total length increases, vehicles need to travel longer distances and
larger negative impacts are anticipated.
Agriculture Land that overlaps with the alignment will be lost due tothe construction of
the bridge and cause negative environmental impacts such as loss of environmental
services.
Total Length over the Brahmaputra River is indicative of negative impacts of the
project on the river ecosystem and endangered aquatic species such as Gangas river
dolphins. The longer the length over Brahmaputra River is, the larger the damage on the
river ecosystem will be. A Specific report on Gangetic Dolphins and their management
has been prepared and attached as Annexure-1
Engineering Aspects
With regard to the total length of the bridge, because of higher construction technologies
and costs of bridges compared with embankments, a shorter bridge length is rated
favorable. With regard to the length of the approach, because of the necessity of new road
constructions of approaches to connect the bridge and the existing roads, a shorter
approach length is rated favorable. With regard to the number of curves, because of easier
drivability of roads with fewer curves, the fewer is rated favorable. With regard to the total
length of curves, because of the requirement of complex structures and higher construction
technologies, a shorter length is rated favorable.
Based on the above aspects, the parameter scores for various aspects and options are as
follows. The numerical score was calculated by the following equation:
Social Aspects
As for the social aspects, Option 1 has less impact with respect to the number of affected
structures and the size of the land to be acquired. Although Option 3 has less impact on the
poor, the total score shows Option 1 as the most favorable option.
Environmental Aspects
As for the environmental aspects, differences among the three options were relatively small
for the total length and the total length over Brahmaputra, but impacts on agriculture land
were most significant for Option 3.
Engineering Aspects
As for the engineering aspects, although Option 1 is unfavorable with respect to a longer
bridge length and approaches, it has a fewer curves and a shorter curve length deemed to be
favorable. The comprehensive rating gives Option 1 the highest score.
Conclusion
Based on the above, Option 1, i.e. proposed bridge over river Brahmaputra between Dhubri
on North Bank and Phulbari on South Bank in the state of Assam/Meghalaya on NH-127B,
alignment AD (Length: 20km), is recommended.
Depending on the scale and nature of works during the various stages of the project, there
are positive and negative impacts to the natural and social environment. These impacts are
different in the intensity, in the spatial reach, and in whether it is irrevocable or temporary.
The scoping matrix highlights anticipated impacts that occur on various environmental and
social components during the scoping stage of the project. The project may affect the
aquatic ecosystem in terms of the impacts to the natural environment. Also, the ROW for
this project is 60m in width, and social impacts such as land acquisition and resettlement
are anticipated.
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
Pollution
P: No impact is expected.
C: Some negative impacts are expected due to the
operation of construction equipment and vehicles. One
Air
D B- B- example is dust incidental to earthwork especially during
Pollution
the dry season.
O: Air pollution is expected to increase due to increase
traffic volume on the road.
P: No impact is expected.
C: Turbid water due to the earthworks, bridge pier
Water construction work and wastewater effluents from
D B- D
Pollution construction workers’ camps / yards are expected to pollute
the Brahmaputra river to some extent.
O: No impact is expected.
P: No impact is expected.
C: Waste will be generated from construction workers’
Wastes /
camps. Waste generated from construction and demolition
Hazardous D B- D
work may include hazardous materials that must be treated
Materials
before final disposal.
O: No impact is expected.
P: No impact is expected.
C: Impacts on soil from deposition of pollutants from
Soil construction materials in the construction site are expected
Contaminati D B- D to be small. Since there is no major industrial activity along
on the road, it is unlikely that soil along the road is already
polluted.
O: No impact is expected.
P: No impact is expected.
C: Noise and vibration generated by the operation of
construction equipment and vehicles, although they are
temporary. Construction schedule should take into account
Noise and the location of schools, hospitals and religious facilities
D B- B-
Vibration that require silence during parts of the day.
O: Noise and vibration level are likely to increase due to
greater traffic volume along the road. Specific measures
may be required to minimize impacts on schools, hospitals
and religious facilities.
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
Ground
D D D P/C/O: No impact is expected.
Subsidence
Offensive
D D D P/C/O: No impact is expected.
Odor
P: No impact is expected.
Bottom C/O: The piers may cause slight change in the
D C C
sediment hydrodynamics and cause erosion of bottom sediment.
Natural Environment
P: No impact is expected.
Wildlife
C: No protected area exists within 10km radius of project
Reserve/
D D D area.
protected
O: No protected area exists within 10km radius of project
area
area.
P: No impact is expected.
C: During the construction period, ecosystem in the project
Eco- area including local flora and fauna will be damaged to
system/Bio- D A- B- some extent.
diversity O: Increase of traffic volume will cause negative impacts
on the ecosystem including fauna and flora along the
project road.
P: No impact is expected.
Topography C: Changes in topographic conditions over the project area
D B- D
/ Geology takes place due to the need for cutting and filling work.
O: No impact is expected.
P: No impact is expected.
C: Construction work may cause minor and temporary
impacts on hydrology because of pier construction, or the
Hydrology D B- B-
local use of water.
O: Cutting and / or filling should result in minor changes of
local hydrology.
P: No impact is expected.
C: During the construction period, ecosystems in the
project area including local flora and fauna are damaged to
Eco-
some extent.
system/Bio- D A- B-
O: Increase of traffic volume will cause negative impacts
diversity
on the ecosystem including fauna and flora along the
project road.
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
Social Environment
P: The project will likely affect over 700 families.
C: Resettlement will be completed before construction
Involuntary
begins and thus no resettlement is expected during
Resettlemen A- D D
operation.
t
O: No impact is expected, as relocation will be completed
before construction begins.
P: Given the limited coping capacity of the poor, it is
necessary to assess their vulnerability and develop
appropriate mitigation measures.
C: The poor can benefit from employment opportunities
B+/
Poor People A- B+ during construction work.
B-
P: In the long-term, economic development in the region is
likely to benefit the poor. However, the poor may not be
able to receive benefits from the project due to the lack of
skills and coping capacity.
Ethnic
P/C/O: According to initial site survey, there are no
Minorities/
C C C ST/SCs in the project area. However, the presence of ethnic
Indigenous
minorities will be confirmed during the census survey.
People
P: Loss of income sources and livelihood due to
involuntary resettlement are expected to negatively affect
the local economy and livelihood.
C: Economic activity of fishermen may have negative
Local
impact during construction period. On the other hand,
Economy B+ B+
A- employment opportunities of various skill levels will be
and /B- /B-
created by the project.
Livelihood
O: Economic activity of boat operators may be affected.
On the other hand, by improving transportation network,
access to market and public facilities will be improved and
positive impact on regional development can be expected.
P: Land acquisition and involuntary resettlement are likely
to cause changes in the existing land use patterns.
C: Land use is expected to change for the construction of
construction yards and workers’ camps, however the
Land Use B- B- D impact is temporary.
O: Land usage along the alignment will be permanently
changed, however a negative impact is not expected.
Construction yard will be restored to their original
conditions by the contractors.
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
P: No impact is expected.
C: The use of local resources such as sand, crushed stone,
Utilization
etc. for the construction activities may have negative
of Local D B- D
impact on the local use.
Resources
O: No impact is expected as use of local resources is not
expected during operation.
Water
Usage,
Water
D D D P/C/O: No impact is expected.
Rights and
Communal
Rights
P: One school may be affected and require relocation.
C: If the school will be relocated to the area close to the
Social alignment, noise from increased traffic is expected.
Infrastructur B+/ O: If the school will be relocated to the area close to the
B- B-
e and B- alignment, noise from increased traffic is expected. In the
Services long term, the project is expected to improve access to
social infrastructure and services by providing a better
transport network.
Social
Institutions
P/C/O: Land acquisition and involuntary resettlement will
and Local
D D D be implemented based on existing social and local
Decision-
decision-making institutions so no impact will be expected.
making
Institutions
P: Land acquisition and involuntary resettlement will lead
to unequal distribution of benefits and damage between
those who are directly affected by the project and those
who are not.
Unequal
C: Those who are affected by Land acquisition and
Distribution
B- resettlement should have preference in access to
of Benefit B- B-
/B+ employment opportunities by the construction work.
and
O: There is a possibility of uneven distribution of benefits
Damage
between bridge connection site and Char land. In the long
term, the project is expected to have a positive impact on
the local economy through an improved transportation
network.
Local
D D D P/C/O: No impact is expected.
Conflicts of
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
Interests
Cultural and
P/C/O: The proposed bridge does not traverse or run near
Historical D D D
major cultural or historical heritage sites.
Heritage
Landscape D D D P/C/O: No impact is expected.
P: Involvement of women should be ensured during the
course of the land acquisition and resettlement process.
Gender B- B- D C: Equal opportunity should be sought for employment
during construction work.
O: No impact is expected.
P: One school playground will be affected by land
acquisition.
Children's
B- D D C/O: Child labor is unlawful according to Article 24 of the
Rights
Indian Constitution. Only adults are eligible for potential
employment opportunities created by the project.
Public P: No impact is expected.
Health C: Influx of construction workers is likely to increase the
(sanitation health risk, particularly that of STD / STI and HIV / AIDS.
D B- D
and O: No impact is expected.
infectious
diseases)
P: No impact is expected.
Occupation
C: Occupational health and safety of construction work
al Health
D B- B- should be properly managed through adequate EMP.
and Safety
O: Maintenance and repair work should take into account
(OHS)
the occupational health and safety of the workers.
Others
Accidents D B- B- P: No impact is expected.
C: Increased risk of accidents associated with construction
activities is expected due to the operation of heavy
equipment and vehicles.
O: Risks of accidents is expected to increase due to greater
traffic volume and speed.
Climate D D D P: No impact is expected.
Change C: The use of construction machines and operation of
vehicles will result in an increase of GHG emissions,
though the impact is small and short-term.
O: The new bridge will shorten the truck transportation
distance which reduces GHG emission. On the other hand,
Construction Stage
Pre-construction
Operation Stage
Item
Rational of the Impact Assessment
TOR of the Natural Environment and Socio-economic Survey is shown in the table below.
Items Subject to
Item Locations Investigation Method of Assessment and Estimation of Impacts
Sediment · Impacts during the construction period and operation and maintenance
period are qualitatively analysed based on construction plan and similar
projects
Ecosystem/ Entire Project Area · Presence/absence of rare · Field Survey
Biological species · Document survey
Diversity · Hearing Survey on local NGO/ experts.
· Impacts during the construction period and operation and maintenance
period are qualitatively analysed based on construction plan and similar
projects
Hydro Entire Project Area · Existing waterways such · Review of DPR environmental study
geography as rivers, streams and · Document survey
agricultural canals as · Field survey, map location study of the disaster-prone areas
well as sewage channels · Impacts during the construction period and operation and maintenance
period are qualitatively analysed based on construction plan and similar
projects
Geography/ Entire Project Area · Areas subject to cut and · Review of DPR environmental study
Geomorpholog fill slope creation · Document survey
y · Field survey
· Impacts during the construction period and operation and maintenance
period are qualitatively analysed based on construction plan and similar
projects
Involuntary Within ROW · Population, asset · Census Survey
Resettlement inventory, livelihood · Focused Group Discussion
· Resettlement and · Estimate the quantitative impact of affected households, land and
rehabilitation cost properties.
· Estimate the cost of resettlement and rehabilitation, restoration program
Poor People Within ROW · Livelihood and · Census Survey
employment status · Socio-economic Survey
· Literacy · Estimate the impacts based on result of Field Survey, Review of
Items Subject to
Item Locations Investigation Method of Assessment and Estimation of Impacts
Document plus Similar Examples
Ethnic Within ROW · Ethnicity, Language · Census Survey
Minorities/ · Livelihood · Socio-economic Survey
Indigenous · Estimate the impacts based on result of Field Survey, Review of
People Document
Local Economy Within ROW and · Regional economic · Census Survey
and Livelihood area surrounding situation · Socio-economic Survey
the proposed · Social structure · Focused Group Discussion
alignment · Income and livelihood · Estimate likely impacts on the local economy based on Review of
Document plus Similar Examples
· Estimate the impact on livelihoods based on the quantitative data of the
socioeconomic status of PAPs
Land Use Within ROW · Land utilization · Socio-economic Survey
· Extent of Impact by the · Review project content
project · Estimate the impacts based on result of Field Survey, Review of
Document plus Similar Examples
Utilization of Area surrounding · Volume of local · Socio-economic Survey
Local the proposed resource use · Review project content
Resources alignment · Extent of Impact by the · Estimate the impacts based on result of Field Survey and Review of
project Document
Social Area surrounding · Target facilities · Socio-economic Survey
Infrastructure the proposed · Distant from ROW, · Estimate the impacts based on information of utility infrastructure and
and Services alignment location public facilities (medical, school, religious facilities)
· Accessibility
Unequal Within ROW and · Livelihood of PAP and · Census Survey
Distribution of area surrounding surrounding area · Focused Group Discussion
Benefit and the proposed · Utilization of Affected · Estimate the impacts based on result of income sources of PAPs and
Damage alignment Land other villagers plus Similar Examples
Items Subject to
Item Locations Investigation Method of Assessment and Estimation of Impacts
Gender Within ROW and · Social Structure · Socio-economic Survey
area surrounding · Livelihood and · Focused Group Discussion
the proposed employment status · Documents and reports of similar projects in the neighbouring areas.
alignment · Literacy · Estimate the impacts based on result of Field Survey, Review of
Document plus Similar Examples
Children's Within ROW and · Number of students · Socio-economic Survey
Rights area surrounding · Facilities nearby · Estimate the impacts based on result of Field Survey plus Similar
the proposed Examples
alignment
Public Health 100m from the · Rate of disease, · Review of documents of the similar projects.
(sanitation and proposed alignment epidemic and tendency · Estimate the epidemic of diseases and tendency through Review of
infectious Document plus Similar Examples
diseases)
Occupational Area surrounding · Risk of Safety and · Review of documents including EMP of the similar projects.
Health and the proposed Health, countermeasure · Estimate the impacts based on Similar Examples
Safety (OHS) alignment
Accidents Area surrounding · Traffic demand · Review of documents including EMP of the similar projects.
the proposed · Accident risk and · Estimate accident risk, tendency and measures based on Review of Plan
alignment measures plus Similar Examples
Flora:
A. Construction Phase:
Construction of the proposed bridge is likely to affect some trees / plants. The removal of
these trees and the loss of vegetation cover will have some effect on local ecological
balance, such as the disruption of habitat for small birds, mammals, etc., that will be forced
to migrate to other areas. The removal of vegetation may also lead to minor climatic
changes such as altered surface hydrology, increased temperatures due to reduced shade
cover, etc.
B. Operation Stage:
In the operation phase no further impacts are likely on plantations along the project bridge.
Environmental quality will be considerably improved by adopting environmentally sound
engineering designs and by maintaining the aesthetic quality through appropriate
landscaping and arboriculture practices.
Fauna:
There is no impact on the Wildlife sanctuary from the proposed project as no sanctuary in
vicinity of the project area.
7.1.1 General
In the following pages impacts on each biophysical environmental component (like soil,
water, air, noise, flora and fauna) and socio-economic environmental component (like
removal of property, land acquisition, etc.) will be discussed
Through the above exercise, the following key issues were identified:
§ There is no critical issue in the natural environmental except cutting of some trees.
§ National Board of Wild Life clearances are not required as no sanctuary/National
park within 10 km from project alignment.
7.1.3 Link-up between Baseline Environmental Conditions with Proposed Project Intervention
Water Environment:
Physical and chemical quality of the river water and other surface water bodies is the crucial
for sustenance of aquatic habitat. Groundwater is the major source of drinking and irrigation
in the project area.
A. Construction Stage:
Medium negative impacts on surface water quality due to (i) dredging activities, (ii)
construction of main bridge and other structures over water bodies (and ii) construction
activities near Brahmaputra River. Further, accidental spillage of fuels, lubricants,
chemicals/solvents, and construction waste will contaminate surface and ground waters as
well as sedimentation caused by erosion.
During the construction phase, soil erosion can be increased due to the removal of trees,
vegetative cover, and the compaction of the surface soils. However, being dry during most
of the year, erosion is more of a concern during the monsoon season when water is flowing
within the water courses.
B. Operation Stage:
No significant impact. However there could be medium to high level risks due to accidental
spillage of fuels, lubricants, chemicals/solvents. Drainage congestion, soil erosion and
siltation impact can be significantly reduced through training of emergency personnel in the
procedures of spill control and clean-up, and the provision of emergency spills equipment in
selected emergency service stations.
Regular monitoring of morphological changes of river at the bridge locations and along the
RTW and formulate bank protection work immediately for implementation, particularly
during monsoon.
A. Construction Stage:
Ground water degradation can take place when contaminants are leached through surface
soils into the ground water table Contaminants such as fuel and engine oil handled in the
construction staging area and during equipment re-fuelling at construction site areas can
cause ground water contamination if spilled onto the ground and not properly cleaned up. In
addition, poorly installed sanitary facilities can also result in contamination.
B. Operation Stage:
In general, impacts to ground water during the operation stage of the project are limited to
potential contamination (direct or indirect) from the spill of contaminants, usually as a result
of vehicle accidents.
Increased Run-off:
Construction of the bridge will lead to an increased run-off both during the construction and
operation stages. During the construction stage, removal of vegetation and compaction of
soil leads to increased run-off during the monsoon. Similarly, the area of open ground lost to
built-up black top surface increases the run-off from the open ground.
Water quality may be degraded during construction due to the disposal of solid and liquid
waste from the labour camp, fuel and lubricant spills or leaks from the construction
equipment, fuel storage and distribution sites and from the bitumen and asphalt storage at
hot-mix plants. Major pollutants of concern due to above mentioned activities are suspended
solids, oil and grease, lead and other metals.
Ground water recharge areas may be reduced due (i) dredging activities, (ii) construction of
main bridge and other structures over water bodies (and ii) construction activities near river.
Further, to an increase in impervious soils resulting from compaction. Contamination of
ground water due to the runoff carrying pollutants is of major concern because most of the
domestic use is from ground water.
Air Environment:
A. Construction Phase:
Impacts to the air environment during construction will largely result from the generation of
dust. Dust will be generated as a result of site clearing and grading, heavy machinery
travelling over exposed soils, truck traffic, and the production of construction materials at
borrow pits and off-site quarries. Dust generation impacts will be most significant along
new bridge alignments. Elevated levels of SO2, CO and hydrocarbons are likely from hot
mix plant operations.
B. Operation Phase:
EIA and EMP Report 112 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
As all the shoulder will be paved shoulders and slopes of embankments shall be turfed, dust
generation is not a problem at this stage. The major impact on air quality will be due to
vehicles emission. The impacts on air quality will at any given time depend upon traffic
volume / rate of vehicular emission within a given stretch and prevailing meteorological
conditions.
Air pollution impacts arise from two sources: (i) inadequate vehicle maintenance; and (ii)
use of adulterated fuel in vehicles. Enforcement standards to meet better vehicle
performance in emissions and the improvement of fuel constituents can assist in improving
regional air quality.
Noise Environment:
Noise generated by the highway traffic depends on factors such as traffic intensity, the type
and condition of the vehicles plying on the road, acceleration / deceleration / gear changes
by the vehicles depending on the level of congestion and smoothness of road surface.
A. Construction Phase:
During the construction phase, the major sources of noise pollution will be movement of
vehicles transporting construction materials to construction yards and the noise generated by
activities at the yard itself. Concrete mixing, casting and material movement are primary
noise generating activities in the yard which will be uniformly distributed over the entire
construction period. Construction equipment will have high noise levels, which can affect
the personnel operating the machines, as well as nearby residents and commercial
businesses. The acceptable (average) noise level over an 8 hour shift is 90 dB (A).
The noise likely to be generated during excavation, loading and transportation of material
near the borrow areas will be in the range of 90 to 95 dB (A). This would occur only if all
equipment is operating simultaneously, which is unlikely.
During the construction period, residents along project road/bridge could experience
significant increase in night time noise levels if construction is conducted in the night time
hours to avoid vehicle diversion difficulties. This impact will be temporary and is largely
unavoidable to address through traffic issues.
Noise impacts due to various construction activities are likely but are expected to be
confined to the immediate vicinity of the project corridor. Increased noise levels are
expected due to the movement of construction machinery, concrete and asphalt plant
operations. The likely noise generated during excavation, loading and transportation of
material near the borrow areas will be in the range of 80 to 90 dB (A).
The potential impacts of noise pollution include deteriorated human health and reduced
quality of life (e.g. reduced enjoyment of outdoor amenity areas). However, due to the short
term nature of elevated noise levels during construction, hearing problems are not expected,
and reduced quality of life would be a short-term impact.
Physical Environment:
EIA and EMP Report 113 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
The improvement of the project is expected to cause changes in the land use. In this project,
areas presently under agriculture fields/ river bed may be diverted for development of other
usage. However, the status of such change will be insignificant. Changes in land use are
most likely to occur in some of the segments, as developed roadway/bridge access will
increase the desirability of the land for purposes such as residential and commercial /
industrial development. The increased attractiveness for these uses is likely to result in
increased land values, which in turn could lead to land speculation. Often agricultural land
which has been purchased for speculative purposes will not be managed with the same
degree of interest by the new owner/developer as it was by the farmer, and may not be
operated as agricultural land. The availability of cheaper labour in the rural areas combined
with increased access to urban markets could result in significant changes to land use and
community dynamics in the areas that were previously agricultural. Changes that might
occur would include residential / commercial and industrial development along the
roadway/bridge.
There are no important archaeological resources, or sites of cultural properties (like temples,
mosques, hospitals etc) exist along the project road.
A. Operation Phase:
Traffic volumes and vehicle speeds are expected to increase after the proposed bridge
development / construction. Construction of the bridge/road will result in alterations to
access roads/driveways to religious properties, shrines and other religious structures. In
addition, access and egress from these access points will be more difficult due to increased
vehicle movements and speeds. This in turn could result in increased risk of collisions,
especially at night.
Soil is one of the most important components of the natural environment. For bridge / road
development the soil is primarily needed for altered bridge / road embankment.
Erosion:
The soil along the proposed bridge / road is sandy clay in texture. The erosion factor of
present soil is less.
The two important eroding agents are, (i) the run-off water, and (ii) the wind. The run-off
dynamics are affected by the degree of slope, and the amount of water stored for irrigation.
Grasses and other herbaceous plant limit the surface erosion effectively.The degree of soil
erosion is noted to be less.
Some mitigation measures like:
§ Taking advantage of the period of monsoon,
§ Developing not too high and steep slopes,
§ Improving drainage,
§ Replantation of trees, and
These steps will reduce the severity of the issue and by the time the bridge / road starts
operating, the ecosystem will restore itself.
Excavations of soil borrow areas may lead to higher degree of erosion. However, care has
been taken that (i) many borrow areas are located on raised lands, earth mounds and heaps,
(ii) in some cases the owner or villagers want to develop the area into pond for rearing
fishes, (iii) re-plantation borrow pit areas will minimize the soil erosion.
Contamination of Soil:
In the present project, the contamination of the soil is negligible, as there is no use of
hazardous material which can contaminate the soil. However, at material storage site,
interceptor / HDPE sheets will be provided to avoid any soil contamination.
Use of Local Water Supply:
No local water supply will be used for construction purposes. Water will be taken from
nearby surface water sources as rivers Brahmaputra along the proposed bridge / road. New
hand-pumps will be bored to take out underground water at construction sites if required. As
the underground water table is moderate and water requirement is during construction phase
only, the crisis of water will not be there.
7.2.2 Impact on Environment Attribute due to project intervention and Environment Management
The impact on natural, biological and physical environments due to various project
interventions are given in the table below Table 7.1:
Table 7.1: Impact on Environment Attribute due to project intervention and Environment Management
Environmental Mitigation Institutional Responsibility
Project Activities Mitigation/Compensation Measures
Impacts Cost Implementation Supervision
CONSTRUCTION STAGE
A. Main Bridge
Large quantities of Exploration of · Environmental permits of suppliers from Included in Contractor CSC(Construction
material Import illegal source relevant authority civil works supervision
contract consultant),
MORT&H
Mobilization of Road Safety and · Ensure that all construction vehicles observe Included in Contractor CSC
equipment and Traffic speed limits on the construction sites and on civil works
Materials through Management public roads contract
road · Provide adequate signage, barriers, and flag
persons for traffic control.
· Fit audible warning devices in all vehicles to
alert during reversing.
Damage of local · Maintain all existing roads in traffic worthy Included in Contractor CSC
roads due to condition ensuring maintenance of civil works
movement of uninterrupted movement of traffic. contract
heavy axle loads · Temporary bypasses to be constructed and
maintained (including dust control) during the
construction period
· Form a grievance redress committee in
association with affected population before
starting the civil work and advance notice must
be given to the community about the
construction schedule.
· Repair the damaged local roads to their original
condition after project completion.
C. Approach Roads
Clearing of sites Loss of top-soils · Collect/strip top soil before earth-filling and Included in Contractor CSC
store and re-use it for final surfacing of road civil works
embankment and tree plantation contract
Cutting of trees · Tree plantation along roadside open spaces. Included in Forest CSC, Forest
plantation Department Department
budget
Loss of · Undertake agriculture development plan to RAP NGO CSC
agricultural lands boost up crop production
· Development of demonstration plots along with
training to farmers for high yield variety of crop
production.
Earth Filling by Loss of · Borrow soil will be procure from approved Included in Contractor CSC
borrowed material productive soil quarry. civil works
· IRC guidelines will be followed during contract
excavation
· care has been taken that (i) many borrow areas
are located on raised lands, earth mounds and
heaps, (ii) in some cases the owner or villagers
want to develop the area into pond for rearing
fishes, (iii) re-plantation borrow pit areas will
The key potential environmental issue that may result due to proposed project intervention is given in the following Table 5.2 and the analysis
of alternatives to the Key Potential Environmental issues has been presented in the Table 7.2.
The economic and social interaction of communities is going to be improved by the bridge /
road projects. However, the construction of bridge / road will cause disruption to local
interactions. All the likely affected assets and families were identified and head of the likely
affected households or representatives were interviewed through the structured
questionnaire followed by preparation of inventory of all the affected assets during the SIA..
7.4 Others
Accidents
During the construction stage, traffic volume of heavy equipment and construction vehicles
will increase. During the operation stage, increase of traffic volume and speed might
increase the risk of accidents.
Mitigation Measures
During the construction stage, the construction section should be properly demarcated and
signages should be placed. Notice and necessary information shall be shared amongst
surrounding villagers prior to the construction activities. During the operation stage, traffic
signs shall be installed, especially in the built-up areas as well as at the junction of the
existing road and approach road to avoid traffic accidents. Sidewalks and pedestrian
crossings will be equipped to ensure the safety and movement of pedestrians.
Public involvement is one of the most important methods for the success of any project. It is
useful for gathering environmental baseline data, understanding likely impacts, determining
community and individual preferences, selecting the alternative and for designing
sustainable mitigation and compensations plans.
In order to make the project sustainable and effective, communication with the stake-
holders, other affected people and interviews with individuals was made.
During public consultation, individually and field testing of questionnaire an effort was
made to create an awareness amongst the people about the proposed project. The positive
and negative impacts were explained so that affected people could raise their problems and
suggest some better alternatives in mitigating the negative impacts and make the project
successful.
The following benefits resulting from the project were pointed out:
§ Improvement of the road shall result in less travel time requirement for people and
goods.
§ This will benefit the public in general and shall lower the cost of commodities.
§ The problem of traffic jams will be reduced.
§ Due to the improved transport fruits, vegetables and other perishable goods could be
saved from early decay.
§ The availability of consumer items shall be ensured.
§ With this the improvement shall result in reduction in fuel consumption which, in
turn shall result in saving valuable foreign exchange
§ The road accidents shall decrease as a result of widening.
§ There shall be general economic improvement of the area and the living standard of
people will improve.
The following negative effects and mitigation measures of the project were explained for
PAPs awareness:
§ The implementation of the project shall result in necessary land acquisition and
dislocation of the people. Dislocated Project Affected Peoples (PAPs) shall be paid
compensation as admissible and shall be consulted to know their priorities regarding
the mode of compensation, for e.g., land for land, cash compensation, etc.
§ People below poverty line, or belonging to scheduled caste and scheduled tribe, or
physically handicapped, shall be given due care while planning for their
resettlement.
§ A general attempt shall be made to safeguard the sources of earning of the affected.
§ The efforts shall be made to save as many trees as possible. The proposal for dense
tree plantation shall be suggested in consultation with the people to improve the
environment.
§ The problem arising due to the shifting of electricity, telephone lines and other
utilities shall be solved with the co-operation of the respective departments.
EIA and EMP Report 137 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
§ Compensation will be paid for all the private trees going to be cut. This
compensation will be based on the species and their commercial value
The above points were raised to create awareness about the project. Suggestions were
sought from PAPs for improving the road alignment by raising following questions:
Definition of Stakeholder:
Stakeholders are the individuals or groups that are likely to affect or be affected positively
or negatively by a proposed project or activity. Stakeholders play a very important role in
deciding the course of project implementation.
It is very much essential to address the interests of the stakeholders in implementation of the
proposed project and also to modify/accommodate their views in the project plan or
programme. It is crucial to develop the co-operation between stakeholders & the project
team so as to ultimately achieve the successful completion of the project. Benefits of
reaching out to stakeholders through surveys and one-on-one meetings consultations are:
§ Quality input leads to quality decision-making. A broader perspective reduces
“group think,” helps to challenge traditional thinking, and sparks creativity in
problem solving.
§ Greater stakeholder satisfaction with the final planning product comes from their
involvement in shaping it.
§ The chances of successful implementation increase as more stakeholders feel
committed to the plan or project’s goals and take ownership of the plan’s design.
§ Good governance, transparency, and open communication are served when we
communicate and receive feedback from stakeholders, instead of being guided by
personal agendas.
In our present study, most important stake holders are the public living by or near the
project bridge, Road development/construction department officials including project
implementation unit, forest officials and NGOs working in the locality. These stakeholders
hugely influence the process of project decision making.
Stakeholders were identified to ensure as wide coverage as possible of the project area as
follows:
Public discussions were held to obtain background information and details of general
environmental issues that concern people in the project area. In addition, environmental
issues were discussed with relevant government officials, beneficiaries, and community
leaders.
7.5.6 Details about the Consultations Carried Out
The consultant has tried to consult for external input & tried to bring important new points
of view to planning.
The people living in the impact zone of the project road/bridge were consulted regarding
environmental issues in their area using structured questionnaire as well as unstructured
questionnaire. In addition issues such as any persisting problem people are facing due to
existing road/communication were also put in front before them. The inputs of stakeholders
on policy/plan development in respect to proposed project are very important. Stake holder
consultation process in the project ideally follows the following steps:
Survey: Surveys are mechanisms for dialog, creativity, and consensus building for to
identify the local stakeholders.
One-on-one/group meetings:
During the public consultation, it was observed that many of the people were aware of the
environmental conditions in and around their village. But for most of the people, the issues
of prime concern were proper compensation offered by the client. Also the major concern
for the villagers was the houses, schools, agricultural land etc which are going to be affected
due to the proposed project.
7.5.8 Particulars of the Consultation
On site discussion with affected stakeholders, and reconnaissance visits have also been
made to the project area. Following table Table 7.3 and Table 7.4shows the details of
consultation through questionnaire.
Table 7.3: Site discussion at different location
The interviews with groups of local people were carried out and the form viz. “Practical
view of the community about Environmental Scenario” was filled up at various locations.
The form is having details regarding Water quality, noise level, air quality, Archaeology/
historical importance in their vicinity, history of natural disaster, cultural activities etc.
Sample list of people interviewed during public consultation is attached below along with
photographs of the public consultation. The summary of the filled forms are as under:
Table 7.4: People’s Perception about Environment Degradation
7.5.9 Findings of the Stakeholder Consultation and Issues of Concern that need Attention
The General issues which were put forward before us during the public consultation were:
§ Proper Compensation offered to the affected villagers.
§ Houses which are going to be affected with the proposed project.
§ Risk of life of Aquatic Animals.
§ Land acquisition for bridge construction.
§ Improvement of socio economic condition due to proposed bridge.
§ Drainage of carriage way & drainage facility along the approach road side need to be
developed in order to prevent houses/shops getting inundated during heavy rains.
§ Road safety features need to be introduced specifically in approach area road so as to
reduce/bring down the frequency and number of accidents.
§ Restoration of livelihood for boat owners due to the proposed bridge.
Operation Stage
Construction
Construction
construction
construction
Stage
Pre-
Pre-
Pollution
P: No impact is expected.
C: Some negative impacts are expected
due to the operation of construction
equipment and vehicles. One example is
Air
D B- B- D B- D dust incidental to earthwork especially
Pollution
during the dry season.
O: Air pollution is expected to increase
due to increase in traffic volume on the
road.
P: No impact is expected.
C: Turbid water due to the earthworks,
bridge pier construction work and
Water wastewater effluents from construction
D B- D D B- D
Pollution workers’ camps / yards are expected to
pollute the Brahmaputra river to some
extent.
O: No impact is expected.
P: No impact is expected.
C: Waste will be generated from
construction workers’ camps. Waste
Wastes /
generated from construction and
Hazardous D B- D D B- D
demolition work may include hazardous
Materials
materials that must be treated before final
disposal.
O: No impact is expected.
P: No impact is expected.
C: Impacts on soil from deposition of
Soil
pollutants from construction materials in
Contaminat D B- D D B- D
the construction site are expected to be
ion
small. Since there is no major industrial
activity along the road, it is unlikely that
EIA and EMP Report 148 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
Impact Impact
Assessments of Assessments
Scoping of Study Result
Operation Stage
Operation Stage
Construction
Construction
construction
construction
Item Rational of the Impact Assessment
Stage
Stage
Pre-
Natural Environment
D D D P: No impact is expected.
Wildlife
C: No protected area exists within a 10km
Reserve/
D D D radius of project area.
protected
O: No protected area exists within a 10km
area
radius of project area.
D B- D P: No impact is expected.
C: During the construction period,
ecosystems in the project area, including
Eco- local flora and fauna, are damaged to some
system/Bio- D A- B- extent.
diversity O: Increase of traffic volume will cause
negative impacts on the ecosystem
including fauna and flora along the project
road.
Topography D B- D D B- D P: No impact is expected.
EIA and EMP Report 149 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
Impact Impact
Assessments of Assessments
Scoping of Study Result
Operation Stage
Operation Stage
Construction
Construction
construction
construction
Item Rational of the Impact Assessment
Stage
Stage
Pre-
Impact Impact
Assessments of Assessments
Scoping of Study Result
Operation Stage
Operation Stage
Construction
Construction
construction
construction
Item Rational of the Impact Assessment
Stage
Stage
Pre-
Impact Impact
Assessments of Assessments
Scoping of Study Result
Operation Stage
Operation Stage
Construction
Construction
construction
construction
Item Rational of the Impact Assessment
Stage
Stage
Pre-
Impact Impact
Assessments of Assessments
Scoping of Study Result
Operation Stage
Operation Stage
Construction
Construction
construction
construction
Item Rational of the Impact Assessment
Stage
Stage
Pre-
General
Greater development and improvement of economic in this region is not possible unless
construction or development of bridge/road between the two district/ state. The present
mode of boat transport is not capable to cater to increasing traffic demand due to rapid
development in project influence area.
Development/construction in the proposed project bridge/ road will result in the following
benefits:
§ Providing better level of service in terms of improved riding quality and smooth
traffic flow and reduction in travel time between Dhubri and Phulbari.
§ Faster transportation will ultimately lead to massive savings in the form of reduced
wear and tear of vehicles, reduced vehicle operating costs (VOCs) and total reduction
in transportation costs etc. Approximately 26 lakh people of the Dhubri (Assam),
West Gharo (Meghalaya) will get benefitted by this.
§ With the Development/construction of the proposed project bridge/ road, the traffic
congestion due to obstructed movement of vehicles will be minimized and thus
wastage of fuel emissions from the vehicles will be reduced.
§ Introduction of additional safety measures like crash barrier, road illumination, retro-
reflective boards, delineators etc. will result in lesser accidents.
§ Increased passenger comfort due to construction of bridge/ road shall be an added
benefit.
§ It will increase access of the villages and other small settlements to urban areas, thus
providing connectivity of rural produce to urban markets, thereby enhancing the reach
and export of perishable farm-goods, leading to better remuneration for the producer.
§ The reach and export of perishable farm-goods will have quite a positive impact and
this will prove to be a boon for the rural agricultural sector.
§ Providing connectivity to the urban infrastructure.
§ Rural industrial produce, whether from Commercial industries, small-scale industries
or medium-scale industries will have easy access to the urban markets.
§ Strengthening of rural economies: The rural sector / economy are sure to get
strengthened, though at a gradual pace.
§ Higher education: Provision of easy access to higher education can be directly linked
to the improved educational scenario.
§ Access to medical facilities: Villages in the project region are not yet well-equipped
with all types of medical facilities and services like Public Health Centres (PHCs),
dispensaries, hospitals. Due to inaccessibility, reaching even the nearest health centre
sometimes becomes a colossal task. Even the doctor's reluctance will be converted
into willingness to visit these areas after construction of the project bridge/road.
§ By reducing the transportation costs, it will be more feasible to transfer construction
materials which are important for many economic activities (house building, school
building, small hydro-electric, projects etc) to hinterland. This will in turn, lead to
direct as well as indirect strengthening of local economies.
§ During the execution of the project, i.e. during the construction period, employment
will be provided to workers from the local communities.
§ The educated as well as uneducated people from villages will obtain access to new
employment centers.
§ The construction/development of bridge/ road will reduce the number & frequency of
collisions. This would be very beneficial from the safety point of view and will thus,
reduce accident rate.
§ Overall improved quality of life for the lesser developed areas in the neighbourhood.
EIA and EMP Report 154 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
Value Addition:
§ Enhanced connectivity between rural & urban population which will benefit the all
sections of the society like general population, small-medium-large scale industries,
farmers, businessmen etc.
§ Improved access to higher education facilities & modern health facilities.
§ Strengthening of both rural & urban economies which in turn will improve
economic scenario of the state and country.
§ Improved bridge / road connectivity helps in better implementation and
management of government schemes.
§ With improvement in economy, more generation of employment opportunities.
9.1.1 General
I. Visual observation,
II. Selection of environmental parameters at specific locations, and
III. Sampling and regular testing of these parameters.
Responsibility
Sl. Standards Location Frequency
No Item Project Stage Parameters Guidance Implementation Supervision
M1 Air Construction PM10, • Dust sampler to be Air (P&CP) Hot mix Thrice a Contractor PIU
SO2,NOx, located 50m from the Rules, plant/ year for 8 through
CO, plan in the downwind CPCB, 1994 batching years approved
direction. plant, monitoring
• Use method specified Sampling agency
by CPCB for analysis locations
Specified in
M2 Operation PM10, • Use method specified EIA report
Air(P&CP) Sampling Thrice a PIU PIU
SO2,NOx, by CPCB for analysis Rules, locations year for
CO, CPCB, 1994 Specified in four years
EIA report
M3 Water Construction pH, Turbidity, • Sample collected from Water Sampling Thrice a Contractor PIU
BOD, COD, source and analyzed as quality locations year for 8 through
TDS, TSS, per Standard Methods Standards by Specified in year approved
DO, Oil & for Examination of CPCB EIA report monitoring
Grease and Water and Waste agency
Pb water
M4 Operation pH, BOD, • Grab sample collected Water Sampling If spillage is PIU PIU
COD, TDS, from source and quality locations reported
TSS, DO, Oil analysed as per standards by specified in due to
& Grease and Standard Methods for CPCB EIA report accident
Pb Examination of Water etc.
and Waste water
Responsibility
Sl. Standards Location Frequency
No Item Project Stage Parameters Guidance Implementation Supervision
M5 Noise Construction Noise levels • Free field 1m from the Noise At equipment Thrice a Contractor PIU
on dB(A) equipment whose noise Standards by yard year through
scale levels are being CPCB /construction for 8 years approved
determined. site. required monitoring
agency
M6 Operation Noise levels • Equivalent Noise Noise At maximum 4 Thrice a PIU PIU
on dB(A) levels using an standards by sites listed in year for 4
scale integrated noise level CPCB EIA report for years
meter kept at a distance noise
of 15m from edge of monitoring
Pavement locations
M7 Ecology Construction Frequency of • Observation from river Dhubri, Thrice a year NGO, PIU PIU
and operation dolphin bank (from sunrise to Phulbari for 8 years
sightings sunset, 10 days) during
construction
and 4 years
during
operation
M8 Livelihood Construction Sample Evaluate based on the Census Within ROW Twice a NGO PIU
and operation interview internal and external survey year
survey monitoring results on the carried out
effectiveness of RAP during the
conducted by NGOs. RAP
preparation
The responsibility for the implementation and supervision of EMPs are vested with three
agencies, namely, Contractors, PIU, and Supervision consultants (SC). The Contractors
herein mean the agency hired for the execution of the construction works for the respective
contract packages. PIU would be the implementation agency with the support of PWD.
Figure 9.1 indicates the implementation structure of the EMP.
Figure 9-1: The organizational framework for implementation of the EMP and EMoP
It has been proposed that the Executive Engineer (environment) based in Dhubri will be in
charge of the implementation of EIA and EMP for this project. Such an engineer will be
assisted by the Assistant Engineer (Environment), who will be assisted by Supervision
consultant (and Environment Specialist) and contractor.
The construction supervision consultants are expected to have in-house capacity to advise on
and supervise the implementation of the EMP including suggesting enhancement design
options and modifications, as necessary. For this purpose, the supervision consultant will
employ a full-time environmental specialist.
Compensatory plantation, maintenance and protection of vegetation will be required as part
of environmental mitigation and enhancement works. Likewise, spoiled soil shall be used,
where possible, to create community assets such as playgrounds, as per request of the
community. In these types of works, the project may engage NGO, Consultant or experts
from local universities to liaise with the local community for effective implementation of the
project.
An integrated grievance and redress mechanism (GRM) for environmental and social action
plans is needed to be established for the project. The GRM provides a system for receiving,
evaluating and facilitating the resolution of affected people’s concerns, complaints, and
grievances about the project’s social and environmental performance. Due to the scale of
the project with one end of the bridge located in an urbanized section of Dhubri and adverse
impacts are anticipated, issues like poor legal records, voluminous titles and sometimes
conflicting holdings, intensive construction activities located near communities, traffic from
construction vehicles, and conflict between migrant and host communities are to be
expected.
Grievances related to the implementation of the project, will be acknowledged, evaluated,
and responded to with corrective action proposed using understandable and transparent
processes that are gender responsive, culturally appropriate, and readily accessible to all
segments of the affected people. Records of grievances received, corrective actions taken
and their outcomes will be properly maintained.
The nature and significance will be evaluated by the receiving party. Any complaint which
concerns project construction activity, poses imminent serious risk to life and property, or
will result to irreversible damage to wildlife (dolphin) will be immediately forwarded to the
PIU- for action within 24-hours from receipt of complaint.
The following Tables indicate JICA’s standardized monitoring form. Monitoring works
should be carried out every six months unless otherwise specifically noted.
Table 9-2: Environmental Clearance
Monitoring Item Conditions During the Reporting Period
Response to State
Department’s Comments/
Guidance for Obtaining
Environmental Clearance
FOR BIODIVERSITY
Monitoring Item/Parameter Conditions During the Reporting Period
Observation of Gangatic river
dolphin (dolphins/hour)
Name of the Species:
Location of the Observation
Odour
Identification of the Source of Location of the source/Emitting extent of the area
Offensive Odour
FOR SOLID WASTE
Monitoring Item Conditions During Remarks(Location、Frequency
the Reporting Period and Method of Measurement)
Disposed Waste Wastes are separated and
disposed according to
Construction and Demolition
Waste Management Rules, 2016
Source: Study Team
EIA and EMP Report 160 June 2018
Feasibility Study and Detailed Project Report
for Two / Four Lane Bridge including Approaches over River Brahmaputra between
Dhubri on North Bank and Phulbari on South Bank in the State of Assam / Meghalaya Final Detailed Project Report – Vol. IVA
on NH-127B (length 20 km) DELD15021-CAL-40-PH04-S-1042-R1
9.5.1 General
Environmental Management Plan (EMP) is prepared for all the identified environmental
impacts during pre-construction, construction and O&M stages due to implementation of
various Project activities and associated development. The methodology followed for
preparing the EMP is given in Figure below and consists of the following steps:
Fig. 9.2: Framework for Preparation of EMP during Construction and O&M
The EMP will be included in all the bid documents of the Project and will become a part of
the civil works contract. The strict implementation of the EMP and project management’s
strict enforcement of the adequate construction practices and standards will greatly reduce
the negative impacts of the Project.
section 6.0. Environmental monitoring program is presented in Table 6.1in EIA report –Vol.
IV.
A cost estimates are prepared for all the mitigation and monitoring measures proposed in the
EMP. The details of the cost estimates and the budget during construction stage and first
five years of operation stage for the mitigation measures are given in Table 9.8. The cost
estimates for some of the mitigation measures that were already part of civil works contract
or Resettlement Action Plans (RAP) are not included in the EMP.
The cost estimates also includes the budget for environmental monitoring, consultants for
EMP implementation, institutional strengthening and capacity building of CSC / MORT&H
and environmental enhancement/compensation measures. The total budget for EMP
implementation is estimated to be about INR 1, 04, 15,900.00.
9.5.3 Institutional Framework for Implementation of EMP
Various institutions will be involved during implementation of the project as shown in Fig.
9.4.
Each Contractor procured under this Project (especially the contractors for main bridge /
road) will be recommended to be a compliant of Environmental Management System (EMS)
certification. Further conditions of compliancy for OHSAH 18000 (2007) related
Occupational Health and Safety (OHS) and SA 8000 (Social Accountability) could also be
imposed on the Contractors. Each contractor will be recommended to have one
Environmental Specialist and one Occupational, Health and Safety (OH) Specialist, who
will be working in close coordination with the environmental staff of CSC.
CSC will be responsible to monitor all activities of all contractors procured under the
project. As several contractors will be working simultaneously for timely and speedy
implementation of the project, it is important that CSC has an Environmental Specialist to
effectively supervise and monitor the environmental activities being implemented in the
field. The CSC is also responsible to update or make necessary changes to the EMP if
required based on the revised designs and locations.
Environmental Responsibility
Sl. No Mitigation Measures Location Time Frame Implementation Supervision
Impacts/Issues
Air Pollution · Hot mix plants and batching plants shall be All hot-mix and During Setting Up Contractor PIU, SC
P1 placed at least 500m away from habitation and batching plants
agricultural fields. of Such Plants.
Water Pollution · Camps shall be located at least 500m away All construction During Contractor PIU, SC
from the nearest built-up area.
· Sewage system for a construction labourer’s campsites Establishment of
P2 camp shall be designed, builtand operated so Identified by the Such Camps.
that no pollution to ground or adjacent water contractor and
bodies/ watercourses takes place. of the
relevant norms and the Engineer. approved by SC
Wastes · Garbage bins shall be provided in all All construction During Contractor PIU, SC
construction camps. campsites Establishment of
P3 Identified by the Such Camps.
contractor and
approved by SC
Ecology · Utilize the baseline data of already carried Proposed bridge To be completed NHIDCL, NGO PIU
out study under the project Gangetic Dolphin site near before
P4 Research and conservation programme.
Brahmaputra construction starts
River
Resettlement of · All requirements of the RAP as applicable All areas Before Government of PIU, SC
Project Affected shall be complete before start of construction construction Assam /
stage.
Persons (PAP) / · The activities broadly include acquisition of begins Meghalaya,
local economy land and structures, rebuilding of common District Revenue
P5 and livelihoods properties, payment of compensation and
provision of assistance authorities and
District
Authorities,
NGO/Consultant
Environmental Responsibility
Sl. No Mitigation Measures Location Time Frame Implementation Supervision
Impacts/Issues
Land use / • If requested, location of relocation sites shall Near the Before District PIU
be identified in consultation with
Identify and district/village authorities and PAPs. original construction stage Authorities
P6 prepare • Sites to be developed including the provision villages
relocation sites of necessary utilities such as water and
electricity.
Unequal • Support measures will be planned to provide Within Before District PIU &
distribution of employment opportunities to those directly ROW construction stage Authorities, , NHIDCL
benefit and affected with priority. NGO
P7 • Support measures for the char people will be
damage planned with the assistance from NGO and
other experts so that they can receive
maximum benefit from the project.
Local conflicts • Appropriate explanation shall be given to the All areas Before District PIU &
of interest residents of the target area as well as the construction stage Authorities, , NHIDCL
P8 PAPs to gain their understandings on the
contents of the impact, compensation and NGO
support measures and the conditions.
Poor people / • Ensure the participation of the poor and Within Before District PIU &
Gender women in the process of land acquisition and ROW construction stage Authorities, , NHIDCL
resettlement.
• Livelihood restoration plan will be NGO
considered taking in to account the limited
P9 skills of the poor people (including illiterate
population).
• Information shall be shared to women and
representatives of women with the assistance
from the village heads and NGOs.
Environmental Responsibility
Sl. No Mitigation Measures Location Time Frame Implementation Supervision
Impacts/Issues
Setting up • Camps shall be located at least 500m away All During Contractor PIU,
construction from the nearest built-up area. construction Establishment, SC
camps • Sewage system for a construction labourer’s campsite Operation and
camp shall be designed, built and operated identified by Dismantling of
so that no pollution to ground or adjacent the contractor Such Camps.
water bodies/ watercoursestakes place. and approved
Garbage bins shall be provided in the camps by SC
and regularly emptied and the garbage
disposed off in a hygienic manner, to the
satisfaction of the relevant norms and the
P10 Engineer.
• In relation to underground water resources,
the contractor shall take all necessary
precaution to prevent interference with such
water resources.
• All relevant provisions of the Factories Act,
1948 and the Building and other
Construction Workers (regulation of
Employment and Conditions of Service) Act,
1996 shall be adhered to.
Setting up hot • Hot mix plants and batching plants shall be All hot-mix and During Contractor PIU, SC
located sufficiently away from habitation Erection,
mix plants batching plants Testing,
and agricultural fields. Operation
• Where possible such plants will be located at and
P11 least 1000m away from the nearest Dismantling of
habitation. Such Plants.
Environmental Responsibility
Sl. No Mitigation Measures Location Time Frame Implementation Supervision
Impacts/Issues
Finalizing sites • Location of dumping sites shall be finalized. All areas During Contractor PIU, SC
for surplus soil The sites shall meet following conditions: identified as mobilization
dumping i) dumping does not impact natural drainage
P12 potential
courses;
ii) no endangered/rare flora is impacted by dumping sites
such dumping
Identification of • The contractor shall identify All area During Contractor PIU, SC
hazard-prone locations sensitive to aquatic species and mobilization
P13 shall duly report these to the Supervision
locations
Consultant (SC) and to PIU.
Identify and • Location of relocation sites shall be Near villages PIU PIU
prepare identified in consultationwith district/ with
relocation sites village authorities and PAPs. large-scale
P14 • Sites to be developed including provision
of necessary utilities such as water and resettlement
electricity.
C23 Local • Construction workers shall be employed by Construction Construction Contractor and PIU
economy and giving priority to PAPs (including women, poor work site stage Supervision
livelihoods / people). The information shall be widely shared Consultant,
within the region so that the local residents can
Unequal obtain maximum employment opportunities. NHIDCL, NGO
distribution of • NHIDCL, with assistance from NGOs, shall
benefit and provide vocational training that can meet the
damage / qualification for local residents to become
Local conflicts workers.
of interest
C24 Water use • Mitigation measures such as installation of a silt Construction Construction Contractor and PIU
fence close to the residential area to minimize work site stage Supervision
river pollution during construction. Consultant
C25 Gender • Consider types of occupation and working hours Construction Construction Contractor and PIU
for women to provide equal employment work site stage Supervision
opportunities based on the needs and aptitude, Consultant
social background of women in target area.
Disruption to Users
C35 Loss of Access • The Contractor shall provide safe and Throughout During Contractor Engineer
convenient passage for vehicles, pedestrians and the project Construction.
livestock. area,
• Work that affects the use of side roads and
existing accesses shall not be undertaken particularly in
without providing adequate provisions. built-up areas
• The works shall not interfere
unnecessarily or improperly with the
convenience of the public, or the access to use
and occupy public or private roads, or access to
any other footpaths or properties whether public
or private.
O3 Air quality • Monitoring shall be carried out as specified in As specified As per PIU, SPCB PIU
degradation due the Monitoring plan in the monitoring
to increases in • Share air quality data with SPBC and relevant monitoring plan
agencies and discuss options for mitigate air quality
traffic volume degradation associated with greater traffic volume. plan
O4 Increases in • Monitoring shall be carried out as specified in the As specified As per PIU, SPCB PIU
noise and Monitoring plan in the monitoring
• Install noise barrier (wall etc.) in sensitive areas, if
vibration due to monitoring plan
necessary
greater traffic • Carry out proper road maintenance to reduce noise
plan
volume and vibration.
Responsibility
Sl. No Environmental Location Time Frame
Implementation Supervision
Mitigation Measures
Impacts/Issues
O5 Ecology • Monitor the population of endangered species. As specified As per PIU, NGO PIU
• Enhance research and conservation of Gangatic river in the monitoring
dolphins. monitoring plan
plan
O6 Local economy • Change of income source and income of PAPs shall be Within ROW As per PIU, NGO PIU
and livelihoods/ monitored. monitoring
Poor people plan
O7 Unequal • Conduct interviews to DCs and village heads about All area When issues District PIU
Distribution of dissatisfaction or conflict of residents of the target area are identified Authorities,
Benefit and and explain and take measures as necessary. PIU, NGO
Damage/ Local
conflicts of
interest
O8 Accidents • Ensure the safety through traffic rules such as speed All area As per PIU PIU
limit. monitoring
plan
A proposed EMP implementation schedule and Graphs for the Dhubri Bridge is shown in Figure
9.4 and 9.5.The timing of each process of the implementation schedule is assumed as follows:
The procured consultant will assist NHIDCL with PQ (Pre-Qualification) and then with each step
of the bidding of civil works process. Following the tendering, it is assumed that the contract
agreement of civil works will be signed in August 2019.The C/S (Construction Supervision) service
the consultant will provide is assumed during eight years of the construction, following one year of
defect liability.
191
PEER – REVIEW
OF
EIA REPORT (DOLPHIN PART) ON DHUBRI – PHULBARI BRIDGE
IN THE STATE OF ASSAM / MEGHALAYA ON NH-127B
Peer-Review by:
Dr. Sunil K. Choudhary
University Dept. of Botany
T. M. Bhagalpur University
Bhagalpur - 812 007
192
PROJECT: Two / Four Lane Bridge Including Approaches Over River
Brahmaputra Between Dhubri On North Bank And
Phulbari On South Bank In The State Of Assam /
Meghalaya On NH- 127B (Length: 20km)
IMPLEMENTING AUTHORITY:
Background Information
The Government of India (GOI) has launched in recent years the “Special Accelerated Road
Development Program for Northeastern Region” for which improvement of the road network
is of great importance. As per Twelfth Five Year Plan (April, 2012 to March, 2017)” of The
GOI, the improvement of national highways in the Northeastern Region should interconnect
major cities within the region. However, the severe natural conditions of the Northeastern
Region featured by steep mountains and a prolonged monsoon season are major obstacles
for appropriately developing the road network. Economic growth in this part of the country has
therefore been much delayed. The GOI aims to promote regional connectivity of the road
network in Northeastern Region which will help in cross-border trade and commerce, thus
safeguarding India’s international borders. It is within this context that on the request of the
GOI, the Government of Japan has been providing assistance in carrying out of the design
work of two/four lane bridge including approaches over river Brahmaputra between Dhubri on
the north bank and Phulbari on the south bank in the State of Assam / Meghalaya on NH-
127B (length of 20km).
193
Proposed Two/Four Lane Bridge Project including Approaches over River
Brahmaputra between Dhubri and Phulbari in the State of Assam/ Meghalaya
The proposed project is the construction of Two / Four lane bridges including approaches
over River Brahmaputra between Dhubri on North Bank and Phulbari on South Bank in
the state of Assam/Meghalaya on NH-127B (Length: 20km) on EPC Mode under JICA.
The project proponent is Ministry of Road Transport and Highways (MORT&H), / National
Highways and Infrastructure Development Corporation (NHIDCL). AECOM Asia
Company Limited has been engaged as consultant for preparing DPR including EIA, SIA
and RAP for the proposed project.
The proposed project covers an area in between Dhubri on north bank at 89°58'16.99"E
& 26°1'34.63"N and Phulbari on south bank at 90°1'49.99"E & 25°52'12.03"N and at an
Elevation of 35 to 42m above Sea level.The construction site for the proposed Dhubri
Bridge extends over two states, the Dhubri District on the north bank and the South
Salmara-Mankachar District on the south bank belonging to Assam State and the West
Garo Hills Distrct belonging to Meghalaya State. The proposed bridge connecting Dhubri
and Phulbari across the Brahmaputra river is supposed to improve the connectivity of the
road between southwestern region of Meghalaya State and other parts of India by
expanding the transportation network of this region. The proposed bridge length is 18.36
km and the proposed ROW is 60m. No Sanctuary or National Park, no major wildlife
migrant route and no historical monument protected by Archaeological Survey of India
(ASI) are located within 10 km radius of the proposed project site.
1. As per the MOEF & CC, GOI EIA Notification, dated 14.09.2006 (as amended in
August 2013), any highway project falls under Category A if the project entails:
i. New National Highways; and
ii. Expansion of National Highways greater than 100 km involving additional right of
way or land acquisition greater than 40m on the existing alignments and 60m on
re-alignments and bypasses.
The proposed Dhubri-Phulbari Bridge project does not require additional land acquisition
beyond 60m and has length of approximately 20km and therefore, does not attract the
provisions of the EIA Notification of 2013.
194
2. Although the project does not require environmental clearance from MOEF & CC, GOI,
the project has been classified as Category A as per JICA’s Guidelines for the
Environmental and Social Considerations and the project requires a full EIA study
including SIA and RAP surveys.
Though the proposed Dhubri-Phulbari Bridge project does not attract the provisions of
the EIA Notification of 2013, but it has been classified as Category A as per JICA’s
Guidelines for the Environmental and Social Considerations. The project site does not lie
within a Wildlife Sanctuary or Protected Area but the Dhubri stretch of Brahmaputra river
has reported population of Gangetic dolphins (Lal Mohan, 1993; Lal Mohan et. al., 1997;
Wakid, 2005, 2009, 2012; Wakid et al., 2014).
AECOM Asia Ltd. has made Environmental Impact Analysis (EIA) as part of the DPR in
respect to this project and JICA has reviewed the EIA report prepared by AECOM Asia
Ltd. JICA has also made its own EIA along the areas to be affected directly and indirectly
during design, construction, operation and maintenance in the proposed Dhubri-Phulbari
Bridge project. In both the EIAs prepared by AECOM Asia Ltd. & JICA, documentation of
baseline data on dolphins is based on secondary information. In AECOM’s EIA report,
dolphin finds no place in the Table listing potential environmental impacts on valued
ecosystem components (Table 1.7, FINAL DPR (Volume IVA) (DOC. NO. DELD15021-
CAL-40-PH04-S-1042), prepared by AECOM Asia Company Limited. In the Section 3.3.4
of the Final DPR pertaining to Biological Environment, Forest and other components
have been given due consideration but the details of River Environment including river
dolphins are missing. Probably this is the reason that dolphins are not included in TOR of
Natural and Socio-economic environmental survey suggested by the AECOM consultant.
However, JICA’s EIA report acknowledges the presence of river dolphins in Dhubri area
(project site lies within this area) all year around (Refer to Wakid’s Report 2012).
Gangetic dolphin Platanista gangetica gangetica is an endangered species and has been
given legal protection under Indian Wildlife (Protection) Act 1972. It has been categorized
as Endangered on the International Union for Conservation of Nature (IUCN) Red List,
included in Appendix I of the Convention on International Trade in Endangered Species
of Flora and Fauna (CITES); and in Appendix II of the Convention on Migratory Species
(CMS). This is why any water development project in a river inhabiting Gangetic dolphin
195
needs proper EIA study on dolphins and its habitat. This is also in accordance with the
Environmental Safeguard Policies of World Bank, Asian Development Bank and JICA
funding a project. Even AECOM responsible for preparing DPR of proposed Dhubri –
Phulbari project has acknowledged that EIA for this project will be prepared as category
A in accordance with JICA Guidelines though not required by Laws in India.
Keeping above facts into consideration, it was decided by the Project Proponent
(National Highways & Infrastructure Development Corporation Ltd. (NHIDCL) in
consultation with JICA that a River dolphin expert should be engaged to peer-review the
existing dolphin part of the EIA report submitted by AECOM and to detail the anticipated
adverse impacts on dolphins due to this project, and also to suggest mitigation measures
and a monitoring plan for implementation of mitigation measures during construction,
operation and maintenance period of the proposed Dhubri – Phulbari project.
1. Peer Review of the part of Final EIA Report (submitted with Final DPR) pertaining to
Dolphin:
a) Preparation of Draft Peer Review Report
b) Finalisation of Peer Review Report in consultation with AECOM EIA
specialist.
2. Preparation of Mitigation proposal based on the EIA pertaining to Dolphin
a) Preparation of mitigation proposal
b) Finalisation of mitigation proposal in consultation with AECOM EIA specialist.
3. Preparation of the cost estimate based on the mitigation proposal pertaining to
Dolphin:
a) Preparation of cost estimation
b) Finalisation of cost estimation in consultation with AECOM EIA specialist.
4. Attending Meeting with NHIDCL/JICA and incorporate all observations made by
NHIDCL/JICA/AECOM.
196
Potential Impacts on River dolphins due to construction of Dhubri –
Phulbari Bridge over River Brahmaputra
Ganges river dolphin Platanista gangetica gangetica has been included in Schedule
I of the Indian Wildlife (Protection) Act 1972; categorized as Endangered on the
International Union for Conservation of Nature (IUCN) Red List; included in Appendix I
of the Convention on International Trade in Endangered Species of Flora and Fauna
(CITES); and in Appendix II of the Convention on Migratory Species (CMS). The
Ganges river dolphin is discontinuously distributed in the Ganga-Brahmaputra-
Meghna and Karnaphuli- Sangu river systems of South Asia from the base of the
Himalayan foothills to the Bay of Bengal (Choudhary et al., 2006). Gangetic dolphin is
primarily piscivorous and strictly inhabits the freshwater ecosystems, chiefly rivers.
They generally wander to different parts of the river in the monsoon, but congregate at
meander bends in the river course where an eddy counter-current is prevalent and
there are greater water depths during winter months. In recent years, Ganges river
dolphin population has declined in both its range and population size. Ganges river
dolphin has been declared as National Aquatic Animal of India. The endangered
Gangetic dolphin is a unique, blind mammal that relies entirely on the use of ultrasonic
sound production to forage and navigate in murky river waters of the Ganga-
Brahmaputra river system with the use of echolocation, i.e. production and hearing of
echoes from ultrasonic-frequency sounds.
The Gangetic river dolphins face many threats and those include competition with
humans for food and water resources, physical alteration, degradation and loss of
habitats, deliberate killing for dolphin products such as meat and oil, and collision with
powered vessels. These dolphins are also threatened by the enormous pollutant load
of the river affecting the immune and reproductive system adversely and by
destructive fishing activities, which results in high mortality from by-catch (accidental
entanglement in fishing gears) and reduced availability of prey. These animals are
perhaps more vulnerable to these threats because their habitat requirements often
place them in areas where human activities are most intense.
197
Why should the Gangetic Dolphin in India be conserved?
The Gangetic dolphin is locally called ‘Phoo’, ‘Susu’, ‘Sishu’ in southern Assam. Few
studies are available on the population estimates and distribution of Gangetic dolphins
in the Brahmaputra River (Mohan et al., 1997; Biswas et al., 1997; Choudhary, 1997;
Wakid, 2005, 2009; Wakid et al., 2014). In the Brahmaputra River mainstem, Mohan
et al. (1997) sighted altogether 266 dolphins in 1993, although they estimated the
population at around 400. They made downstream to upstream survey from India-
Bangladesh border to Assam-Arunachal border in February-March, 1993 and
recorded 28 dolphins in Sadiya to Burhidihingmukh, 45 dolphins from Burhidihingmukh
to Dholpur, 34 dolphins from dholpur to Tezpur, 58 dolphins from Tezpur to Guwahati,
54 dolphins from Guwahati to Goalpara and 47 dolphins from Goalpara to South
Salmara (India-Bangladesh border) with an encounter rate of 0.44 dolphin/km. Highest
sighting of dolphins were recorded in river stretch between Tezpur and Guwahati.
Wakid (2005) recorded altogether 197 dolphins with 27 calves with an encounter rate
of 0.23 dolphin/km. Maximum dolphins were sighted in Brahmaputra river stretch from
198
Goalpara to India-Bangladesh border. Altogether 212 dolphins were recorded by
Wakid (2008) with an encounter rate of 0.24 dolphin/km. 2012 survey conducted by
Wakid (Wakid et al., 2014) resulted into the occurrence of total 635 dolphins in
Brahmaputra river system. Both Mohan et al. (1997) and Wakid (2005) have recorded
maximum dolphins in Brahmaputra river stretch from Goalpara to India-Bangladesh
border, and the proposed Dhubri-Phulbari Bridge project site lies within this stretch,
199
likely reduced the amount of dolphin prey (Mohan et al., 1997; Biswas &
Baruah, 2000, Wakid & Biswas, 2006). Fish species recovered from the
undigested stomach contents of dead dolphins in River Ganga include
Setipinna brevifilis (known locally as phasia), Osteobrama cotio cotio (pithari),
Puntius sophore (pothia), Crosochelius latius (gahuma), Mystus cavasius
(palwa), Heteropneustus fossilis (singhi), Parambassis ranga (chanda),
Macrognathus pancalus (gainchi) and Sperata seenghala (Sinha et al., 1993;
Choudhary et al., 2006). JICA’s EIA report also mentions dolphin prey species
(fish species) Mastacembelus armatus, Mystus cavasius and Puntius spp. in
the river stretch within the proposed Dhubri-Phulbari project site. Although
using very small mesh-sized gill nets (current jal) for fishing is banned in Assam
from May to 15th July, Wakid observed this banned activity throughout the
year.
4 Fragmentation, degradation & loss of dolphin habitat: Although there is no
dedicated study on impacts of water development projects on dolphins but
water development projects in the river such as construction of dams are major
threats to the long-term survival of dolphins. It may isolate the dolphin
population and will restrict its migration. River bank erosion, sand mining and
destruction of riparian vegetation are causing the loss of dolphin habitat as well
as loss of spawning ground for fishes.
5 Pollution of the River: Agricultural practices are the main land-use in the river
floodplains. Residues of agro-chemicals including the synthetic fertilizers and
pesticides are channelized to the river main course with runoff resulting into
pollution of the river and those impact adversely to river biota including
dolphins.
A lot of water development projects have been done and still are going on in rivers but
few reports are available on positive and negative impacts of construction work and
associated activities on riverine habitats and biodiversity. Mostly morphological
changes in large alluvial rivers due to dredging activities have been assessed. The
construction of Dhubri – Phulbari Bridge over River Brahmaputra may include several
activities such as drilling and some dredging for fixing the bridge piers (169 Nos.,
200
some of them over well foundation and some on pile foundation), other engineering
works leading to increased turbidity and chemical pollution of the river, increased river
traffic (movement of vessels and barges), anthropogenic noise as well as noise and
vibrations produced by operation of machineries (including dredgers), These activities
are likely to impact dolphins and habitat of dolphins. Main impacts and their mitigation
measures are detailed below.
1 Impacts of Dredging and movement of vessels & barges: Only limited
information is available on the actual overall effects of dredging activities on
species, habitats and ecosystem processes. To date, the positive and negative
effects of dredging on marine flora, benthic fauna, and the seabed are relatively
well documented (Reviews by Newell et al., 1998).
The main impacts of dredging activities on marine/riverine habitats and species
can be summarised as follows (OSPAR, 2009):
Direct Impacts
10
201
affects stream bank structure and stability, thus negatively impacting riparian
vegetation and animal species dependent on those habitats. The condition of
the stream bank and riparian zone is closely linked to quality of fish habitat.
The magnitude of most of the dredging activities for fixing piers on well
foundation appear to be low and confined to bridge construction site in the river,
hence any impact on river bank structure and stability will be temporary and
insignificant which is reversible.
Impact on Fish: Fish eggs, fry, larvae and juveniles can be sucked up
(entrainment) and displaced by dredging, which can cause death. If they do
survive, they can experience higher mortality rates due to increased predation,
injuries, physiological stressors, disorientation, abrasions and infections.
11
202
that the risk of a collision occurring and the likelihood that it will result in
severe or lethal injury increases when vessels exceed 10–14 kn (Gende et
al., 2011). The knot (kn) (/nɒt/) is a unit of speed equal to one nautical mile
(1.852 km) per hour, approximately 1.151 mph. Calves and juveniles are
most prone to collisions and are struck most commonly. Resting or
feeding dolphins are deemed more at risk. This is due possibly to the fact
that feeding animals are distracted, and less focused on vessel
movements.
Collision with dredgers and other vessels used for river engineering
works is possible but the likelihood of collision varies, depending on a
number of factors, including vessel type, speed, location, species, and
behaviour. Motor boat traffic is frequent in the proposed bridge
construction area. There has not yet been any report of collision between
dolphin and vessels. Dolphins have strong auditory sense allowing them
to detect and avoid vessels/boats, especially where the vessels/boats are
travelling at lower speeds. At the same time, dolphins show adaptive
behaviour against such disturbances in their habitat, the addition of
dredging and other vessels is unlikely to increase the collision risk. If
dredging activity and speed of vessels is well managed, risk of collision
between dolphins and active dredgers and vessels is minimal.
12
203
happen at large distances from the source, and may be costly biologically,
as they could affect energy expenditure, or limit the amount of time spent
feeding or resting. It has been hypothesized that noise impacts have the
potential to induce stress. Stress could reduce the foraging efficiency of
dolphins or increase their susceptibility to disease.
13
204
et al., 1995). In other words, the noise produced by dredger or by vessels
and machines is not expected to significantly interfere with the
echolocation ability of the Ganges river dolphin at the proposed bridge
construction site. Biologically important behaviours such as foraging,
breeding and resting may potentially be affected up to 850m from the
source of the noise, while sustained avoidance behaviour is predicted to
occur up to 60m.
Indirect Impacts
Damage of refuge and breeding area: The River is one of the most
prime sites for the breeding and larval ground for many of the commercial
valuable fishes. Dredging practice changes the bottom condition and
water quality which is most crucial part of larval survival and breeding.
Poor water quality: The dredging condition may mix the sediment particle
embedded with nutrients and minute particles in water in the construction
area (near piling sites). The increase in turbidity in combination with
nutrients may change the water quality rapidly in the dredging area in the
river resulting into many alternations in physiological quality of surface
water and rhythmic activities of the dolphins. The process if continues for
long time is supposed to affect indirectly the whole River system.
14
205
Available information indicates that there will be temporary and
insignificant impact which is reversible.
15
206
Table 1: Potential Impacts of Proposed Dhubri-Phulbari Bridge Project Activities on Gangetic Dolphins
Taxa/Potential impacts Scope Type of Impact Degree of Impact Potential significance prior to mitigation
(Environmental issues)
General
Dredging
Sediment plume Short- Positive effect Low Release of organic nutrients from the
term/Temporary sediment plume enhances diversity and
abundance of benthic fauna near dredged
site; potential to increase the amount of food
available temporarily to river dolphins
16
207
Dredged material from riverbed Long-term Positive effect High Dredged material – valuable resource for
Significant future use & applications
Substrate removal Short- Negative effect Low Alteration of bottom topography &
term/Temporary hydrography resulting into loss of habitats &
the risk of physical & mechanical stress to
benthic communities
Turbidity Local effect Negative effect Moderate Interference with the photosynthesis and
Increased turbidity in Active Short-lived feeding of zooplankton due to turbidity and
dredging zone near bridge Not significant general effects in the plankton, nekton and
construction site
benthos
Fish Long-term Negative effect Moderate Possible regime shift in fish species, alteration
in fish-foraging ability and spawning due to
increased turbidity, entrainment of fish eggs &
yolk sac fry
Gangetic dolphins
Collision / Temporary/Short- Negative effect Very low Dolphins likely to temporarily move away from
Interaction between dolphin and term active dredge area i.e. well foundation site at
dredge or vessel head commencement of dredging works
Hearing damage due to underwater Negligible Negative effect Very low Hearing damage predicted to occur only within
noise associated with dredging, a few meters from the dredger or operational
operation of machines & river traffic machines whereas sustained avoidance
behaviour is predicted to occur up to 60 m
from the dredger
Masking of communication, and Significant Negative effect Moderate Not a significant issue in Active dredging
behavioural responses due to area near well foundation site as Gangetic
dredger noise or noise produced by dolphin has dominant energy around 65 kHz
river engineering works well above the dominant frequency range of
17
208
most man-made noise including dredger and
other noise. However in Indirect Impact Zone
(500 m circumference area from the bridge
alignment), potential impact in biologically
important behaviours of dolphins such as
foraging, breeding and resting due to masking
of echolocation signals
Decline in prey base of dolphin due Short-term Negative effect Low Dolphins likely to compensate for small-scale
to dredging or disturbance due to changes in prey abundance by switching prey
movement of vessels & barges species and moving to alternative foraging
grounds
* Impact Qualification Criteria Low: Hardly perceptible effect; Moderate - Perceptible effect without much importance; High – Perceptible significant effect
18
209
Mitigation and Management Plan
19
210
2. Disposal of dredge spoils
Discharge of residual liquid into the river not allowed as it results into river
water contamination.
3. Fish
Installation of fish exclusion curtain / environmental windows to reduce
suction of fish eggs & yolk sac fry from Dredger.
No dredging activity from 1st May to 15th July as this is the time period for
fish spawning as notified by the State Govt.
4. River dolphins
Maintain speed of dredger while moving at 1-3 knots and speed of other
vessels/barges at 4-5 km/h in upstream and at 9-10 km/h in downstream
movement to minimize the risk of collision.
20
211
All sightings during river engineering works both in Direct Impact Zone and
Indirect Impact zone should be reported.
5. General
Ensure all personnel performing activities related to environmental
management of dredging and other river engineering works for construction
of the bridge are trained, qualified and competent.
21
212
With the implementation of recommended mitigation measures and EMP,
direct or residual impacts on river biodiversity including dolphins due to
dredging (although low in magnitude) and river engineering works/activities
under Dhubri – Phulbari Bridge project will be negligible.
22
213
Dhubri – Phulbari Bridge Project Environmental Management Plan
Environmental Impact Parameter to be monitored Responsibility Executing Agency Frequency Cost INR
Construction phase
1. Dolphin abundance Dolphin abundance estimation PIU/Contractor Local Dolphin Expert, NGO, 02 in a year 12, 00000
estimation/Dolphin count in 5 km upstream & 5 km Local University
survey ( Downstream downstream of the river from Dry peak season (April- @75, 000/each
Single/Double observer the proposed bridge site May) & Post-monsoon survey X 16 surveys
Survey method season (Last week in 8 years
recommended) Oct.-Nov.) during
construction phase, for
consecutive 4-years
2. Fish & Fishery survey & Fish diversity, catch PIU/Contractor Fishery expert/Local 02 in a year 8, 00000
assessment of depletion of composition at landing & University
prey base market sites adjacent to bridge Pre-monsoon season @50, 000/each fish
construction site, fish catch (March, April, May & & fishery survey X
per unit effort, trend in decline June = 4 months) & 16 surveys in 8
of prey base Post-monsoon season ( years
Oct, Nov, Dec & Jan =
4 months) =Total 8
months per year for 8 -
years
3. Monitoring of fishing Monitoring of destructive PIU/Contractor State Forest Dept., Local Throughout the 4, 00000
pressure & threats to fishing nets, gears and NGOs & Local year
@50, 000/each
23
214
fishery & dolphins practices, Monitoring for community year X 8 years
involving local fishing dolphin mortality &
community dolphin entanglement in
fishing nets
4. Measurement of ambient Measurement of effects of PIU/Contractor External acoustic expert 02 (2 set of acoustic 30, 00000
noise level/underwater external noise level on with local dolphin expert data generation in
@5, 00000/for
noise & vibration at project dolphin movement, space pre –monsoon &
one set of
site use, diving behavior and post-monsoon acoustic data
stress-related behaviours; period) every year for generation X
develop a database of 2-years two sets every
dolphin echolocation clicks year for 3 years
types across a range of
+
habitats and ecological
conditions 5, 00000
For data
analysis
5. Capacity building Capacity building of field PIU /Contractor Local Dolphin expert, Twice in a year 8, 00000
researchers, local State Forest Department
@50000/each
community, NGOs, Forest
year X 16 nos.
Dept. Staff of capacity
building
workshop in 8-
years
6. Environmental Education Education & Awareness PIU /Contractor State Forest Department, Throughout the year 8, 00000
& Awareness outreach activities: Village Local NGOs, Local
@1, 00000/year
meetings, Workshop, Poster
24
215
exhibition, Preparation & University X 8 years
distribution of handbills,
pamphlets & other
education material
Environmental Impact Parameter to be monitored Responsibility Executing Agency Frequency Cost INR
Operation Phase
1. Dolphin abundance Dolphin abundance PIU/Contractor Local Dolphin Expert, 02 in a year 6, 00000
estimation/Dolphin count estimation in 5 km upstream NGO, Local University
survey (Use of & 5 km downstream of the Dry peak season @75, 000/each
Downstream Single/Double river from the proposed (April-May) & Post- survey X 8
observer survey method, bridge site, monsoon season surveys in 4 years
recommended) (Last week Oct.-Nov.)
during construction
phase, for
consecutive 4-years
2. Fish & Fishery survey & Fish diversity, catch PIU/Contractor Fishery expert/Local 02 in a year 4, 00000
assessment of depletion of composition at landing & University
market sites adjacent to Pre-monsoon season @50, 000/each
prey base
bridge construction site, fish (March, April, May & fish & fishery
catch per unit effort, trend in June = 4 months) & survey X 8
Post-monsoon surveys in 4 years
decline of prey base
season ( Oct, Nov,
Dec & Jan = 4
25
216
months) =Total 8
months per year for 4
-years
3. Monitoring of fishing Monitoring of destructive PIU/Contractor State Forest Dept., Local Throughout the year 2, 00000
pressure & threats to fishing nets, gears and NGOs & Local community
fishery & dolphins involving practices, Monitoring for @50, 000/each
local fishing community dolphin mortality & dolphin year X 4 years
entanglement in fishing nets
4. Compensation to Compensation to fishermen PIU/Contractor State/Local Forest Throughout the year 3, 00000
fishermen in case of net cuts for Department
release of dolphins (if & (consolidated
when required) corpus fund for 4-
years of
operation)
5. Capacity building Capacity building of field PIU/Contractor Local Dolphin expert, Thrice in a year 4, 80000
researchers, local State Forest Department
community, NGOs, Forest @40, 000/each
capacity building
Dept. Staff
workshop X 12
workshops in 4-
years
6. Environmental Education Education & Awareness PIU/Contractor State Forest Department, 3 – in a year for 4- 6, 00000
& Awareness outreach activities: Village Local NGOs, Local years
meetings, Workshop, Poster @50, 000/each
University
exhibition, Preparation & outreach activity X
distribution of handbills, 12 outreach
26
217
pamphlets & other activities in 4-
education material, years
Preparation of video
documentary & its
demonstration
The cost calculation for EMP activities has been done for 8-years for construction phase and for 4-years for operation phase. Cost does not include
VAT/GST. Cost is inclusive of EMP Consultancy services.
27
218
BIBLIOGRAPHY
Sinha, R. K., N. K. Das, N. K. Singh, G. Sharma & S. N. Ahsan (1993): Gut content
of the Gangetic dolphin, Platanista gangetica. Invest. Cetacea, 24: 317-321.
Bairagi, S.P. (1999): Oil bait fishery of catfishes in Brahmaputra River affecting river
dolphin populations in Assam, India. Journal of the Bombay Nat. Hist. Soc., 96: 424-
426.
Biswas, S. P. & R. G. Michael (1992): Fishery characteristics and the present status
of fisheries of the river Brahmaputra. Proc. Seminar on Conservation of River
Dolphin in Indian Sub-continent, 18-19 August, New Delhi. (Abst.)
Choudhary, S.K., B.D. Smith, S. Dey, S. Dey & S. Prakash (2006): Conservation and
biomonitoring in the Vikramshila Gangetic Dolphin Sanctuary, Bihar, India. Oryx,
40(2): 189-197.
Mohan, R.S.L. & K.V.M. Kunhi (1996): Fish oils as alternative to river dolphin,
Platanista gangetica (Lebeck) oil for fishing catfish Clupisoma garua in the River
Ganges, India. Journal of the Bombay Natural History Society, 93: 86–88.
Motwani, M.P. & Srivastava, C.B. (1961): A special method of fishing for Clupisoma
garua (Hamilton) in the Ganges River system. Journal of the Bombay Natural History
Society, 58: 285–286.
Wakid, A. (2010): Initiative to reduce the fishing pressures in and around identified
habitats of endangered Gangetic Dolphin in Brahmaputra river system, Assam. Final
Technical Report submitted to CEPF. 34 pp.
S.P. Biswas, A. Baruah, R.L.S. Mohan (1997): Current status of river dolphin
(Platanista gangetica) in the river Brahmaputra. Int. J. Ecol. Environ. Sci., 23: 357-
361.
28
219
AECOM (2011): Underwater noise impacts on Ganges River Dolphin (Bhagalpur
Water Supply Project – Trench 1, 24 pp.
29
220
Annexure A
Smith, B.D. & Reeves, R.R. (2000b): Survey methods for population assessment of
Asian river dolphins. In Biology and Conservation of Freshwater Cetaceans in Asia.
Occasional Paper of the IUCN Species Survival Commission No. 23 (eds R.R. Reeves,
B.D. Smith & T. Kasuya), pp. 97–115. IUCN, Gland, Switzerland.
Vessel based visual survey should be done during the low water season and the ideal
weather is from late winter to summer (November – April/May). Though the Monsoon
season is of three months (July – September), it takes another two month
approximately for the water to recede to a conducive level suited for river dolphin
surveys. A minimum of 5 individuals are required for river dolphin surveys. The primary
observers one each on the right and left side of the vessel should search by eye in a
90° cone in front of the vessel. A third observer should serve as the data recorder and
also search for dolphins when not filling out data forms.
Two independent observers positioned behind the primary observers record any
sightings missed by primary team. A schedule for rotating through the three positions
can help reduce fatigue, but extra care should be taken to ensure that dolphins are not
missed during rotations. Surveying when environmental conditions are suboptimal can
lead underestimating abundance. Rain, high winds, sand or dust storms, sun glare, and
severe heat (causing inattention and fatigue) can impair sighting efficiency and the best
way to deal with this problem is to suspend survey effort whenever environmental
conditions are below certain threshold of acceptability. A GPS is an essential tool to
record the distance travelled and the geographical coordinates of a dolphin sighting. A
Laser rangefinder is required to record the distance of the boat and the river bank. This
is important as it help in estimating the area of the river the dolphin is frequenting during
the time of the day. Close communication is essential between the primary and
independent observers to avoid chances of double count. Sightings made by the
primary and secondary teams should be pooled together for calculating encounter rates
and the best minimum abundance estimate. Survey method has to be standardised and
221
made rigorous, otherwise it will be difficult or impossible to detect trends in population
abundance and ultimately make management recommendation based on credible
information.
Group size should be estimated using best, high, and low estimates. High and low
estimates are used to reflect the confidence of observers in accuracy of the best
estimates. The low estimate should be considered a minimum count and the high
estimate a maximum count. Identical best, high and low estimates indicate a high level
of confidence in the best estimates. For some sightings, a low, and even a best
estimate of zero can be used to reflect the possibility of double counting. Sighting that
cannot be substantiated by subsequent surfacing of confirmation by a second member
of the survey team can be given a best and low estimates of zero and high estimate of
one. Estimates should be agreed upon by a consensus of the survey team. If observers
do not agree, the lowest estimate by any team member should be used for the low, the
highest estimate for the high, and the best estimate by either the observer with the most
experience or the observer who first sighted the animal(s) for the best.
The survey should be carried out till there is good visibility and the sighting effort should
be stopped after that and survey team proceed to the next halting station. The next day
the survey should start from the point where the last day survey was stopped and then
proceed further from there.
The size of the dolphins are categorised into three types, Adult (> 1.5 meter), Sub-adult
(<1.5 meters) and Juvenile/Neonate (< 1 meter). Sex determination of Ganges river
dolphins should not be attempted during the surveys as the length and shape of the
rostrum is not the most definitive identification feature, and is certainly not
distinguishable during most of the surfacing, which will be encountered during the
survey.
222
Effort Log & Sighting Form
The Effort log and the Sighting form are designed to incorporate the most essential
observational inputs required during the survey. They are designed to be quickly filled
without distracting the observers from their primary job of sighting dolphin surfacing.
223
EFFORT LOG: GANGES RIVER DOLPHIN SURVEY
FROM:
TO: DATE:
START ODOMETER
EVENT TIME BEGIN TIME END END POSITION OBSERVER
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
START ODOMETER
EVENT TIME BEGIN TIME END END POSITION OBSERVER
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
START ODOMETER
EVENT TIME BEGIN TIME END END POSITION OBSERVER
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
224
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
START ODOMETER
EVENT TIME BEGIN TIME END END POSITION OBSERVER
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
START ODOMETER
EVENT TIME BEGIN TIME END END POSITION OBSERVER
POSITION READING
RAIN/
SIGHT LEFT DIST. RIGHT DIST. CHANNEL TYPE WIND GLARE HUMAN ACT
FOG
CHANNEL TYPE: WSS = (>200M) WIDE SINGLE STRAIGHT. WSM = WIDE SINGLE MEANDERING, MCI = MID-
CHANNEL ISLAND. (WSS = 1, WSM = 2, MCI = 3)
HUMAN ACTIVITIES: BTH = BATHING, BS = BOATS ON SHORE, MFC = MOTORISED FERRY CROSSING,
OFC = OAR POWERED FERRY CROSSING, GNF = GILL NET FISHING, TF = TRAP FISHING, HLF = HOOK AND LINE
FISHING, AG = AGRICULTURE, IND = INDUSTRY, SM = SAND MINING.
BHAGALPUR – 812007
225
SIGHTING FORM: GANGES RIVER DOLPHIN SURVEY
FROM:
TO:
SIGHT TIME OBSERVER NUMBER OF DOLPHINS NUMBER OF EACH SIZE CLASS NAME OF POSITION DISTANCE CHANNEL HUMAN
AREA FROM TYPE ACTIVITY
BEST HIGH LOW ADULT SUB-ADULT NEONATE UNCLASS. LAT./LONG. SHORE
226
CHANNEL TYPE: WSS = (>200M) WIDE SINGLE STRAIGHT. WSM = WIDE SINGLE MEANDERING, MCI = MID-CHANNEL ISLAND. (WSS = 1, WSM = 2, MCI = 3)
HUMAN ACTIVITIES: BTH = BATHING, BS = BOATS ON SHORE, MFC = MOTORISED FERRY CROSSING, OFC = OAR POWERED FERRY CROSSING, GNF = GILL NET FISHING, TF =
TRAP FISHING, HLF = HOOK AND LINE FISHING, AG = AGRICULTURE, IND = INDUSTRY, SM = SAND MINING.
BHAGALPUR – 812007
227
228