WORK PLAN PROGRESS REPORT CLIENT : UPC / DIC
PROJECT ‐ 672100 DATE : 17‐AUG‐2017
SHIFT : NIGHT
DAY 27 THURSDAY
TOTAL TOTAL
TOTAL MANPOWER IN TIME OUT TIME EQUIPMENTS & Elec.DB AVAILABILITY
IDLE Hrs. Hrs.
SITE ENGINEER 1 MAN LIFT ‐
FOREMAN 1 EOT CRANE ‐
FABRICATOR 1 8hrs 30 MOBILE CRANE ‐
6:00 PM 2:30 AM ‐
WELDER 4 min DB AT BAY3 ‐
SEMI SKILLED 3
HELPER ‐
SL NO SCHEDULED JOB ACTIVITIES PRODUCTION ACHIEVED REMARKS CORRECTIVE ACTION
crane limit switch and manlift issues are not rectified.
1
Due to this reason don’t have wor at site.
general work ‐ 8.5 hrs for all workers
WORKING
NAME TEAM IDLE HRS
HRS
ANOOP R day
KARTHICK PR
ARAVINDAKSHAN B 9.5 ‐
SUBIN AK D 9.5 3.5
TOTAL HRS 85.5 14