PE296-BUHASA TIE- IN ACTIVITY ( FROM 23.08.2021 TO 19.11.

2021)

TOTAL WORKING Days / NO ENGINEERS INVOLVED ENGINEERS


ACTIVITY ACTIVITY DOCUMENT NUMBER SCOPE INPUT RECEIVED DATE SUBMITTED DATE HOURS INVOLVED NAME

Prepared the connection design ,STAAD


NOT PROVIDED output and calculation Report with Monorail 23.08.2021 26.08.2021 3 Days 2 Suguna & Asar

NOT PROVIDED Prepared theConnection Drawing 26.08.2021 26.08.2021 0.5 Day 2 Ragu& Ramesh

1 CHEMICAL INJECTION PLANT


Prepared the connection design ,STAAD
NOT PROVIDED output and calculation Report without 27.09.2021 27.09.2021 0.5 Day 1 Asar
Monorail

NOT PROVIDED Prepared theConnection Drawing 27.09.2021 27.09.2021 0.5 Day 1 Ramesh

DESIGN CALCULATION FOR CROSSOVER AND ACCESS PLATFORM -OFF PAD WATER SUPPLY
WELL -REV-B P12516-12-20-83-1601

DESIGN CALCULATION FOR CROSSOVER AND ACCESS PLATFORM - OFF PAD OIL PRODUCER Prepared the REV-B STAAD Analysis ,output
2 WELL WITH GAS LIFT P12516-12-70-83-1651 and calculation Report 03.09.2021 05.09.2021 2 Days 2 Suguna & Asar

DESIGN CALCULATION FOR CROSSOVER AND ACCESS PLATFORM -OFF PAD OIL PRODUCER P12516-12-70-83-1656
WELL WITH GAS LIFT

3 DESIGN CALCULATION FOR TYPICAL PIPE SUPPORTS AND PIPE SLEEPERS DETAILS -ON PAD OIL NOT PROVIDED Prepared the REV-A STAAD Analysis ,output , 02.09.2021 4.09.2021 2 Days Suguna & Asar
PRODUCER WELL WITH GAS LIFT Foundation Design and calculation Report

DESIGN CALCULATION FOR TYPICAL PIPE SUPPORTS AND Prepared the REV-A STAAD Analysis ,output ,
4 PIPE SLEEPERS DETAILS - OFF PAD OIL PRODUCER WELL NOT PROVIDED 9.09.2021 10.09.2021 2 Days 2 Suguna & Asar
WITH GAS LIFT Foundation Design and calculation Report

DESIGN CALCULATION FOR WELLHEAD CROSSOVER AND ACCESS PLATFORM - ON PAD OIL Prepared the REV-B STAAD Analysis ,output ,
5 P12516-12-28-83-1601 14.09.2021 15.09.2021 2 Days 2 Suguna & Asar
PRODUCER WELL WITH GAS LIFT (SINGLE/DUAL) Foundation Design and calculation Report

Design Calculation for crossover and access platform - ON-PAD OIL PRODUCER WELLS
(SINGLE/DUAL) P12516-12-28-83-1611

Prepared the REV-B STAAD Analysis ,output ,


6 Foundation Design and calculation Report 15.09.2021 16.09.2021 1 Day 2 Suguna & Asar

Design Calculation for crossover and access platform - ON-PAD WATER INJECTORS
(SINGLE/DUAL) P12516-12-28-83-1621

Prepared the REV-A Foundation Design and


7 DESIGN CALCULATION OF SINGLE WHCP FOUNDATION NOT PROVIDED calculation Report 22.09.2021 28.09.2021 1 Day 1 Suguna

DESIGN CALCULATION FOR PIPE SUPPORTS AND PIPE SLEEPERS - ON-PAD OIL PRODUCER WELLS
(SINGLE/DUAL) P12516-12-28-83-1612-REV-A

DESIGN CALCULATION FOR PIPE SUPPORTS AND PIPE SLEEPERS - ON-PAD WATER INJECTORS Prepared the REV-A STAAD Analysis ,output ,
8 (SINGLE/DUAL P12516-12-28-83-1622-REV-A Foundation Design and calculation Report 22.09.2021 23.09.2021 1 Day 2 Suguna & Asar

DESIGN CALCULATION FOR PIPE SUPPORTS AND PIPE SLEEPERS - OFF PAD WATER SUPPLY WELL P12516-12-20-83-1602-REV-B

DESIGN CALCULATION OF ACCESS PLATFORMS & CROSS OVER OIL PRODUCER WELL ON PAD-
(SINGLE & DUAL) P12516-12-70-83-1601-REV_A

Design Calculation of ACCESS Platforms & CROSS OVER WATER INJECTION WELL OFF PAD- P12516-12-70-83-1604-REV_A
(single & dual)

9 Design Calculation of Wind Sock Foundation P12516-12-99-83-1637-REV-B Prepared the STAAD Analysis ,output , 24.09.2021 25.09.2021 2 Days 3 Suguna , Asar & Gowri
Foundation Design and calculation Report

DESIGN CALCULATION OF ACCESS PLATFORMS & CROSS OVER GAS LIFT WELL ON PAD P12516-12-99-83-1652-REV-A

DESIGN CALCULATION OFACCESS PLATFORMS& CROSS OVER WATER INJECTION WELL ON PAD-
P12516-12-99-83-1653-REV_A
(SINGLE & DUAL)

Calculation for Pipe sleeper and Pipe supports-OPW-ON PAD P12516-12-99-83-1646Rev B

CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS-GLW-ON PAD P12516-12-99-83-1647Rev B

Prepared the STAAD Analysis ,output ,


10 Foundation Design and calculation Report 11.10.2021 13.10.2021 2 Days 3 Suguna , Asar & Gowri

Calculation for Pipe sleeper and Pipe supports-WI-ON P12516-12-99-83-1648-Rev B

CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS-OPW-OFF PAD P12516-12-99-83-1649-Rev B

DESIGN CALCULATION FOR CHEMICAL INJECTION SHELTER-OFF PAD OIL PRODUCER WELL P12516-12-70-83-1654 Rev B

Prepared the REV-B STAAD Analysis ,output


11 13.10.2021 14.10.2021 1 Day 1 Asar
and calculation Report

DESIGN CALCULATION FOR CHEMICAL INJECTION SHELTER-OFF PAD GAS LIFT WELL P12516-12-70-83-1659 Rev B

DESIGN CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS – GLW-OFF PAD P12516-12-99-83-1650-Rev B

DESIGN CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS – OPW - OFF PAD P12516-12-99-83-1649-REV-B
Prepared the STAAD Analysis ,output ,
12 MAT3D Foundation Design and calculation 28.10.2021 31.10.2021 4 Days 3 Suguna , Asar & Gowri
Report
DESIGN-CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS – WI –OFF PAD P12516-12-99-83-1651-REV-B

DESIGN CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS – WS –OFF PAD P12516-12-99-83-XXXX-REV-A

Man hours not claimed for Below activities (25.11.2021 To x.xx.2021)

CALCULATION FOR PIPE SLEEPER AND PIPE SUPPORTS-PLAT-1


P12516-12-28-83-1636-REV-B

DESIGN CALCULATION OF PLATFORMS - PLAT-1 P12516-12-28-83-1639-REV-B


Prepared the STAAD Analysis ,output ,
13 MAT3D Foundation Design and calculation 25.10.2021 26.10.2021 1.5 Days 1 Asar
Report
DESIGN CALCULATION OF PLATFORMS - PLAT-7 P12516-12-28-83-1640-REV-B

DESIGN CALCULATION OF PLATFORMS - PLAT-15 P12516-12-28-83-1641-REV-B


PE296-BUHASA TIE- IN ACTIVITY ( DURING - DEPUTATION)
TOTAL No. OF WORKING NO ENGINEERS INVOLVED ENGINEERS
ACTIVITY DOCUMENT NAME DOCUMENT NUMBER SCOPE INPUT RECEIVED DATE SUBMITTED DATE Days / HOURS INVOLVED NAME

DESIGN CALCULATION OF PLATFORM FOR MULTI- Prepared the REV-A STAAD


1 SECTOR MANIFOLD (MSM) Not Provided Analysis ,output and calculation Report 1.10.2021 1.10.2021 1 Day 1 Asar

Prepared the REV-C STAAD


2 DESIGN CALCULATION OF PLATFORMS - (SINGLE & DUAL) P12516-12-70-83-1602 Analysis ,output and calculation Report 4.10.2021 5.10.2021 1 Day 1 Asar

DESIGN CALCULATION FOR TELECOM MAST Prepared the REV-1 MAT 3D


3 FOUNDATION P12516-12-99-83-1622 Analysis ,output and calculation Report 1.11.2021 2.11.2021 1 Day 1 Asar

4 CHEMICAL INJECTION PLANT Revised the Document 11.11.2021 12.11.2021 1 Day 1 Asar

DESIGN CALCULATION FOR CROSSOVER AND ACCESS Prepared the STAAD Analysis ,output
5 PLATFORM Not Provided and calculation Report 12.11.2021 15.11.2021 2 Days 1 Asar

DESIGN CALCULATION FOR CROSSOVER AND ACCESS


PLATFORM -PLAT-1 -REV-A

DESIGN CALCULATION FOR CROSSOVER AND ACCESS Prepared the REV-A STAAD
6 PLATFORM -PLAT-7-REV-A Not Provided Analysis ,output and calculation Report 15.11.2021 17.11.2021 2 Days 1 Asar

DESIGN CALCULATION FOR CROSSOVER AND ACCESS


PLATFORM -PLAT-15-REV-A

Performed the REV-A STAAD Analysis &


7 DESIGN OF STOOL STRUCTURE Not Provided output 16.11.2021 16.11.2021 0.5 Day 1 Asar

Calculation for Pipe sleeper and Pipe supports-Plat-1

Performed the REV-A STAAD & MAT3D


8 Calculation for Pipe sleeper and Pipe supports-Plat-7 Not Provided Analysis & output 16.11.2021 19.11.2021 2 Days 1 Asar

Calculation for Pipe sleeper and Pipe supports-Plat-15