FOR
CODE 3: NO COMMENTS
ISSUED FOR
0 07 NOV 2017 Y.S.KIM K.B.LEE Y.S.KIM B.H.SHIM H.S.HWANG
CONSTRUCTION
A 23 OCT 2017 ISSUED FOR REVIEW Y.S.KIM K.B.LEE Y.S.KIM B.H.SHIM H.S.HWANG
Joint Venture of Hyundai Engineering & Construction Co., Ltd., GS Engineering & Construction Co., Ltd., SK Engineering &
Construction Co., Ltd., and Hyundai Engineering Co., Ltd.,
Note :
a) Revision bar(vertical line) shall be placed in the right hand margin to indicate where the changes has been made
b) PRPD = Prepared by, CHKD = Checked by, REVD = Reviewed by, APPRD = Approved by, CONFD = Confirmed by
PROJECT PROCEDURE
REVISION HISTORY
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 3/12
PROJECT
Ref. FEED DOC.NO. : N/A
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. DEFINITION
4. REFERENCE STANDARD
5. HSE REQUIREMENT
7. WORK METHOD
9. ATTACHMENT
PROJECT PROCEDURE
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 4/12
PROJECT
Ref. FEED DOC.NO. : N/A
1.0 PURPOSE
The purpose of this work method statement is to establish a procedure for the padding works
of all foundations as guideline for the Subcontractor, EPC contractor and Company
representative. This document will serve as guide for the Construction management, HSE,
Quality and field personnel for the planning, control, installation and inspection in completing
the work in accordance to project requirements.
2.0 SCOPE
This method statement provides the instruction for levelling pad required for levelling pad
required for the erection of steel structures, pipe racks, pipe supports, static equipment and
rotating equipment on the Karbala Refinery Project.
3.0 DEFINITIONS
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 5/12
PROJECT
Ref. FEED DOC.NO. : N/A
5.1. General
1) Appropriate PPE must be used by personnel doing the task.
2) Pre-job tool box must be conducted and all personnel assigned to do the task must
understand the hazards associated with the job and the control measures in place.
3) Safety induction must be given to all personnel prior to entering the site and adequate
supervision by Safety Officer and Site Supervisor shall be provided to ensure the job is
carried out in a safer way.
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 6/12
PROJECT
Ref. FEED DOC.NO. : N/A
4) Chipping gun/chisel
5) Scaffolding
6) Generator set
7) Ladder
8) Trowel
9) Water container with measuring gauge
6.3. Workers
1) Foreman
2) Mechanic
3) Millwright
4) Mason
5) Surveyor
6) Helper
7) Scaffloder
8) Man lift Operator(s)
7.1. General
1) Contractor shall have a full understanding on the scope of work, method statements, tools,
manpower and temporary works necessary to complete the work.
2) Contractor shall ensure the availability of approved vendor documents such as general
arrangement drawing, foundation drawing and procedure to follow all specific
requirements from the equipment vendor. If a levelling pad lay-out drawing is provided by
equipment manufacturer/vendor ensure details are understood and correctly followed.
3) Reference bench marks required for checking the levels shall be established from project
survey monuments and located on secured points near the work area.
PROJECT PROCEDURE
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 7/12
PROJECT
Ref. FEED DOC.NO. : N/A
4) Levelling pads shall be installed to distributed loads without overstressing the base plate.
7.2. Materials
1) Non-shrink cement based grout shall be used to fix the levelling plates on top of the
foundation. Grout material must be of same or equivalent used for final base plate
grouting.
2) For levelling pads that are meant to be embedded in grout, the material is generally
carbon steel grade A36 steel or equivalent. Minimum cut size shall be 100mm, square or
rectangular shape and thickness may vary from 8mm to 25mm for embedded pad plate.
Surface must be smooth and plane particularly on top where base plate will be in contact.
3) Levelling pad materials may not be painted unless vendor specifies in the installation
procedure or supply the materials.
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 8/12
PROJECT
Ref. FEED DOC.NO. : N/A
Shouldn't be this
number 13?
PROJECT PROCEDURE
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 9/12
PROJECT
Ref. FEED DOC.NO. : N/A
PROJECT PROCEDURE
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 10/12
PROJECT
Ref. FEED DOC.NO. : N/A
Fig. 2 Padding
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 11/12
PROJECT
Ref. FEED DOC.NO. : N/A
KARBALA REFINERY
DOC. NO. : IONE-AA00-MS-MS-0014
Rev. 0 Page 12/12
PROJECT
Ref. FEED DOC.NO. : N/A
Static Equipment
At the top of pad
(Horizontal and Padding ±3mm
plates
Vertical)
Manufacturer’s
Package Item Padding
Instruction
9.0 ATTACHMENT
Activity: *Hot Work Project / Site location: Karbala Refinery Project / Iraq
Department Involved:
Description of Work: Chipping, Pad Plate Installation & Grouting Works.
Job Supervisor:
-HDGSK HSE Plan and safety procedures are to be followed at all times.
-Minimum PPE to be worn at all times.
-This JHA to be available at all points of work – operatives must be informed of this JHA and understand the risks involved in the
General safety condition
works.
requirements:
-Tool box talk / pre-job brief to be given at the start of each work shift and before starting a new task or activity.
-Summer and Ramadan working hours changes are to be observed and details posted at worksite.
-Paramedical or ambulance facilities to be available.
Minimum PPE required: Hard hat, safety glasses or goggles, hi-viz jacket, overalls, gloves, safety shoes
E – Environmental
LS Likelihood / Frequency
Consequence: H – Health
CS Severity of consequence
S - Safety
Prepared by: Sub- STL/STR Manager: Reviewed by: HSE Manager: Approved by: Discipline Manger:
Name: Name: Name:
Signature: Signature: Signature: