Professional Documents
Culture Documents
CONSTRUCTION OF IKEMBA DRIVE SPUR ON OBA – OKIGWE – ROAD THROUGH PERMANENT SITE OF
NNAMDI AZIKIWE UNIVERSITY TEACHING HOSPITAL IN ANAMBRA STATE. CONTRACT NO. 6218.
2. The Engineer’s Representative forwarded the progress report on the above named contract for
the month ending June, 2018.
3. The current status of the project is detailed below:
PROJECT DATA
CONTRACTOR - M/S JIREH HABITATION NIG. LTD.
CONSULTANT - MOAT CONSULT.
CONTRACT SUM - N625,690,820.37
COMMENCEMENT DATE - 4TH DECEMBER, 2013
COMPLETION DATE - 3RD FEBRUARY, 2015.
COMPLETION PERIOD - 35 MONTHS
PROJECT LENGTH - 5.0KM
PREVIOUS PHYSICAL ACCOMPLISHMENT - 15.70%
PHYSICAL ACCOMPLISHMENT THIS MONTH - Nil
PHYSICAL ACCOMPLISHMENT TO DATE - 15.70%
LAPSE OF CONTRACT PERIOD - 385.71%
VALIDITY OF SECURITY - STILL VALID
ENGINEER’S REPRESENTATIVE - ENGR. I. U. ALUMONAH
FINANCIAL STATUS
VALUE OF PERMANENT WORKS EXECUTED TO DATE - N83,926,196.00
PLANT ADVANCE GRANTED - N93,853,623.05
PLANT ADVANCE RECOVERED - NIL
PLANT ADVANCE OUTSTANDING - N93,853,623.05
4. Progress photographs are on page 853 of file. The summary of the permanent works done to
date is shown in the table below:
5. The percentage of work done till date is 15.70%. Based on the progress report submitted by the
Engineer’s Representative, no meaningful work progress was achieved under the reviewed
month.
6. Also, find abc of file memos to the Director Highways (South East) and Director Highways
(Construction and Rehabilitation).
7. Above submitted for your information and further necessary action, please.
Engr. A. O. Aremu.
CE I H (SE).
……….July, 2018.
WR/14898/II/VOL.II/856.
CONSTRUCTION OF IKEMBA DRIVE SPUR ON OBA – OKIGWE – ROAD THROUGH PERMANENT SITE OF
NNAMDI AZIKIWE UNIVERSITY TEACHING HOSPITAL IN ANAMBRA STATE. CONTRACT NO. 6218.
2. The Engineer’s Representative forwarded the progress report on the above named contract for
the month ending June, 2018.
3. The current status of the project is detailed below:
PROJECT DATA
CONTRACTOR - M/S JIREH HABITATION NIG. LTD.
CONSULTANT - MOAT CONSULT.
CONTRACT SUM - N625,690,820.37
COMMENCEMENT DATE - 4TH DECEMBER, 2013
COMPLETION DATE - 3RD FEBRUARY, 2015.
COMPLETION PERIOD - 35 MONTHS
PROJECT LENGTH - 5.0KM
PREVIOUS PHYSICAL ACCOMPLISHMENT - 15.70%
PHYSICAL ACCOMPLISHMENT THIS MONTH - Nil
PHYSICAL ACCOMPLISHMENT TO DATE - 15.70%
LAPSE OF CONTRACT PERIOD - 385.71%
VALIDITY OF SECURITY - STILL VALID
ENGINEER’S REPRESENTATIVE - ENGR. I. U. ALUMONAH
FINANCIAL STATUS
VALUE OF PERMANENT WORKS EXECUTED TO DATE - N83,926,196.00
PLANT ADVANCE GRANTED - N93,853,623.05
PLANT ADVANCE RECOVERED - NIL
PLANT ADVANCE OUTSTANDING - N93,853,623.05
4. Progress photographs are on page 853 of file. The summary of the permanent works done to
date is shown in the table below:
5. The percentage of work done till date is 15.70%. Based on the progress report submitted by the
Engineer’s Representative, no meaningful work progress was achieved under the reviewed
month.
6. Also, find abc of file memo to the Director Highways (Construction and Rehabilitation).
7. Above submitted for your information and further necessary action, please.
C. Ottah
Senior Civil Engineer Highways (South-East)-I
……….July, 2018.
WR/14898/II/VOL.II/858.
CONSTRUCTION OF IKEMBA DRIVE SPUR ON OBA – OKIGWE – ROAD THROUGH PERMANENT SITE OF
NNAMDI AZIKIWE UNIVERSITY TEACHING HOSPITAL IN ANAMBRA STATE. CONTRACT NO. 6218.
2. The Engineer’s Representative forwarded the progress report on the above named contract for
the month ending June, 2018.
3. The current status of the project is as detailed on page 856 of the file.
4. The summary of the permanent works done to date are shown in the table on page 857 of the
file.
5. The percentage of work done till date is 15.70%. Based on the progress report submitted by the
Engineer’s Representative, no meaningful work progress was achieved under the reviewed
month.
6. Above submitted for your information and further necessary action, please.
Engr. C. D. Agbakoba.
Deputy Director Highways (South East) – I
For: Director Highways (South East).
…..….July, 2018.
WR/14898/II/VOL.II/854.
CONSTRUCTION OF IKEMBA DRIVE SPUR ON OBA – OKIGWE – ROAD THROUGH PERMANENT SITE OF
NNAMDI AZIKIWE UNIVERSITY TEACHING HOSPITAL IN ANAMBRA STATE. CONTRACT NO. 6218.
2. The Engineer’s Representative forwarded the progress report on the above named contract for
the month ending June, 2018.
3. The current status of the project is detailed below:
PROJECT DATA
CONTRACTOR -M/S JIREH HABITATION NIG. LTD.
CONSULTANT -MOAT CONSULT.
CONTRACT SUM -N625,690,820.37
COMMENCEMENT DATE -4TH DECEMBER, 2013
COMPLETION DATE -3RD FEBRUARY, 2015.
EXTENDED COMPLETION DATE -
COMPLETION PERIOD -35 MONTHS
PROJECT LENGTH -5.0KM
PREVIOUS PHYSICAL ACCOMPLISHMENT -15.70%
PHYSICAL ACCOMPLISHMENT THIS MONTH -Nil
PHYSICAL ACCOMPLISHMENT TO DATE -15.70%
LAPSE OF CONTRACT PERIOD -385.71%
VALIDITY OF SECURITY -STILL VALID
ENGINEER’S REPRESENTATIVE -ENGR. I. U. ALUMONAH
FINANCIAL STATUS
VALUE OF PERMANENT WORKS EXECUTED TO DATE - N83,926,196.00
PLANT ADVANCE GRANTED - N93,853,623.05
PLANT ADVANCE RECOVERED - NIL
PLANT ADVANCE OUTSTANDING - N93,853,623.05
4. Progress photographs are on page 853 of file. The summary of the permanent works done to
date is shown in the table below:
5. Based on the progress report submitted by the Engineer’s Representative, no meaningful work
progress was achieved under the reviewed month.
6. Also, find abc of file memos to the Deputy Director Highways (South East), Director Highways
(South East) and Director Highways (Construction and Rehabilitation).
7. Above submitted for your information and further necessary action, please.
Engr. C. D. Agbakoba.
Deputy Director Highways (South East) – I
For: Director Highways (South East).
…..….July, 2018.