CONSTRUCTION OF BRIDGE ACROSS RIVER BENUE TO LINK LOKO (NASARAWA STATE) AND OWETO ( BENUE STATE) ALONG ROUTE

F238.

SIRAJ NIGERIA LIMITED ITEMISED PERCENTAGE PROGRESS AGAINST TIME LAPSE (BEME-AUGMENTATION)

FOR THE MONTH ENDING: APRIL, 2016.

SCHEDULE % 5% 10% 15% 2O% 25% 30% 35% 40% 45% 50% 55% 60% 65% 70% 75% 80% 85% 90% 95% 100%
COMPLETION
SITE CLEARANCE 201

EARTHWORKS202,203,204

STONE PITCHING 209,210

GRASSING AND
UNSUITABLE 207,208

CULVERTS/DRAINS /RIP
RAP 301-323

SHAPE FORMATION 401

SUB BASE 403

PRIME COAT 405,406

BINDER COURSE 407

TACK COAT 408


WEARING COURSE 409

SURFACE DRESSING TO
SHOULDERS 410

KILOMETER
POST/KERBS /GUARD
RAILS 411-416
PILING 501-509

BRIDGE PILE CAPS 601-604

BRIDGE PIER STAGE 1 607

BRIDGE STAGE 2 AND


SUPERSTRUCTURE 610-
808

Lapse of contract period.

Actual progress of works.

Consultant (Chief Resident Engineer)