Saudi Aramco 2617-ENG (11/2010) 5 10 15 20 25 30 35 40 45 50 55 60 65 70 75 80 85 90 95 ##

DRAFTING OFFICE PERIOD ENDING DRAFTING SCHED. END OF LAST PERIOD PROJECT ENG. PLANT NO. BUDGET ITEM WORK ORDER NO. EWO NO. JOB ORDER NO.
PROGRESS
DRAWING START COMPL TO END OF THIS PERIOD SAPMT

CONTROL JACOBS ZATE 14-Sep-21 12/1/2019 12/30/2020


DRAWING IS CONSIDERED 65% COMPLETE
WHEN READY FOR CHECKING
DESIGN ENG. K04 103-262 10-00844-0001
JZ PM

STARTING COMPLETION TRANSMITTED


DRAWING SHEET REV. PERCENT COMPLETE HOURS REVISION
DRAWING TITLES DATE DATE* TO FIELD REMARKS
NUMBER NO. NO.
SCHED ACTUAL 10 20 30 40 50 60 70 80 90 SCHED ACTUAL SCHED ACTUAL NO DATE LETTER DATE

VA-688165 003 0A3 ELECTRICAL POWER PLAN - CONTROL VAN NO. 1, 2, 3


EAST/WEST PIPELINE PUMP STATION #3
DA-703475 005 0A3 120 VAC SERVICE PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-203-01 VAN #1
DA-703477 005 0A3 120 VAC SERVICE PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-203-02 VAN #2
DA-703479 005 0A3 120 VAC SERVICE PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-203-03 VAN #3
DA-727734 001 0A3 ELECTRICAL LOAD SCHEDULE - CONTROL BUILDING 6001
DA-727739 005 0A3 ELECTRICAL POWER PLAN - 4160V SWITCHGEAR BUILDING NO.4162
DA-727741 003 0D3 LIGHTING / RECEPTACLE PLAN - CONTROL BUILDING NO. 6001 - DEMOLITION
PA-00P103 001 C LIGHTING LAYOUT - CONTROL BUILDING NO. 6001
VA-688189 003 0A3 ELECTRICAL POWER PLAN - CONTROL VAN NO. 1, 2, 3
EAST/WEST PIPELINE PUMP STATION #4
DA-703675 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-204-01 VAN #1
DA-703677 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-204-02 VAN #2
DA-703679 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-204-03 VAN #3
DA-727887 001 0D2 ELECTRICAL ONE LINE DIAGRAM - DEMOLITION
DA-727887 001 0A2 ELECTRICAL ONE LINE DIAGRAM
DA-727893 001 0A3 ELECTRICAL PANEL SCHEDULES
DA-727899 005 0A3 ELECTRICAL POWER PLAN - 480V MCC BUILDING NO. 4804
DA-727900 003 0D3 LIGHTING/RECEPTACLE PLAN - CONTROL BUILDING NO. 6001 - DEMOLITION
PA-00P104 001 C LIGHTING LAYOUT - CONTROL BUILDING NO. 6001
PA-00P112 001 B POWER LAYOUT - CONTROL BUILDING NO. 6001
PD-00P120 001 B CABLE & CONDUIT SCHEDULE
VA-291001 001 0A2 ELECTRICAL LOAD SCHEDULE - CONTROL BUILDING NO. 6001
VA-688213 003 0A3 ELECTRICAL POWER PLAN - CONTROL VAN NO. 1, 2, 3
PE-04PCAL 001 B LOW VOLTAGE CABLE SIZING CALCULATION
EAST/WEST PIPELINE PUMP STATION #5
DA-703875 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-205-01 VAN #1
DA-703877 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-205-02 VAN #2
DA-703879 005 0A3 120 VAC DISTRIBUTION PANEL SCHEDULE - (ACD1) 480V MCC-VE-10-205-03 VAN #3
DA-728047 001 0D2 ELECTRICAL ONE LINE DIAGRAM - DEMOLITION
DA-728047 001 0A2 ELECTRICAL ONE LINE DIAGRAM
DA-728054 001 0A3 ELECTRICAL PANEL SCHEDULES
DA-728060 005 0A3 ELECTRICAL POWER PLAN - 480V MCC BUILDING NO. 4804
DA-728061 003 0D3 LIGHTING/RECEPTACLE PLAN - CONTROL BUILDING NO. 6001 - DEMOLITION
PA-00P105 001 C LIGHTING LAYOUT - CONTROL BUILDING NO. 6001
PA-00P113 001 B POWER LAYOUT - CONTROL BUILDING NO. 6001
PD-00P121 001 B CABLE & CONDUIT SCHEDULE
VA-291076 001 0A2 ELECTRICAL LOAD SCHEDULE - CONTROL BUILDING NO. 6001
VA-688237 003 0A3 ELECTRICAL POWER PLAN - CONTROL VAN NO. 1, 2, 3
PE-05PCAL 001 B LOW VOLTAGE CABLE SIZING CALCULATION

LEGEND: NOTES: REVISION VALIDATION


SAUDI ARABIAN OIL COMPANY
A- GENERAL / CIVIL / PROCESS / PIPING 1) LIST DRAWINGS BY INDEX IN NUMERICAL ORDER. THIS REVISION NO. C IS COVERED, FOR ALL APPROVAL AND CERTIFICATION
B- FIRE ALARM AND FIRE PROTECTION
D- VESSELS 2) *NORMALLY THE FIELD ETA OF DRAWINGS CAN BE OBTAINED BY REQUIREMENTS, PER SAEP-334, UNDER DRAWING COMPLETION CERTIFICATE NO: DRAWING TYPE
DRAWING CONTROL SHEET
G- LIQUID HANDLING EQUIPMENT ADDING 2 TO 3 WEEKS TO THE SCHEDULED COMPLETION DATE ABOVE. DSC
H- PAINTS / COATINGS
10-00844-0001-001
J- INSTRUMENTATION
K- HVAC REPLACE HALON SYSTEM EAST/WEST PIPELINE PUMP STATIONS
L- PIPING
DESIGN CERTIFICATION REVIEW FOR KEY DRAWINGS
M- STEEL STRUCTURE OTHER
O- SECURITY (DESIGN AGENCY) REQUIRED (SAUDI ARAMCO)
P- ELECTRICAL EAST/WEST PIPELINE PUMP STATION #1
ENGG./DATE CERT. BY/DATE CONST. AGENCY/DATE OPERATIONS/DATE BY/DATE
Q- CONCRETE STRUCTURE
R- ARCHITECTURE
S- PLUMBING / CIVIL / UTILITY SERVICES / LANDSCAPING
YANBU SAUDI ARABIA
T- COMMUNICATION
REV. NO. DATE REVISION DESCRIPTION PLANT NO. INDEX DRAWING NO. SHEET NO. REV NO.
X- CATHODIC PROTECTION
U- SPECIAL EQUIPMENT C 07/01/2021 ISSUED FOR 100% - PP
Z- PROCESS CONTROL SYSTEMS
JOB ORDER/EWO NO. THIS REVISION IS NOT TO BE USED FOR CONSTRUCTION UNTIL CERTIFIED AND K04 A PD-00ADCL 010 C
10-00844-0001 DATED

EKRD/2617-1110.XLS