Daily Progress Report

UPGRADATION TO INTERMEDIATE LANE OF NH-301 KARGIL-ZANASKAR ROAD FROM KM 98+524 TO 117+180 IN


PROJECT NAME:
THE STATE OF JAMMU & KASHMIR ON EPC MODE (Design Length-18.656 Km)

CLIENT: National Highways and Infrastructure Development Corporation DPR Date - 15-06-2022
CONSULTANT: TASPL Reporting Date - 16-06-2022
CONTRACTOR: Skylark Infra Engineering Pvt. Ltd. Weather -
Planned / Achieved

For the Day For the Day For the Month For the Month Cumulative Cumulative Overall
Particulars
Planned achieved Planned Achieved Planned Achieved Progress in %

Total Amount in
0.28 0.72 7.83 11.29 64.87 64.92
Cr.
Percentage
42.78%
261% 144% 100%
Achieved
Main Activities for the Day

Structure Work
1.MJB rast casting completed at Ch 114+050 unit 6
2. MJB slab shuttering and wall plate fixing work in progress at Ch- 114+050 unit 2
3.Excavation completed for bpx culvert at Ch-109+551
4.Massonry work completed for return wall of box culvert at CH-109+180,109+300.

Highway work
1GSB top layer completed at Ch-100+740 to 100+950 BHS

Hindrances / Reason of Lag

1. Concrete pump- water mixed in hydraulic oil


2.DG (5kv) -Starting problem
3.Eicher Tipper-2803- leaf broken
4.Eicher Tipper 9133-clutch plate problem
5..Eicher Tipper-5053- leaf broken