Professional Documents
Culture Documents
CLIENT: National Highways and Infrastructure Development Corporation DPR Date - 15-06-2022
CONSULTANT: TASPL Reporting Date - 16-06-2022
CONTRACTOR: Skylark Infra Engineering Pvt. Ltd. Weather -
Planned / Achieved
For the Day For the Day For the Month For the Month Cumulative Cumulative Overall
Particulars
Planned achieved Planned Achieved Planned Achieved Progress in %
Total Amount in
0.28 0.72 7.83 11.29 64.87 64.92
Cr.
Percentage
42.78%
261% 144% 100%
Achieved
Main Activities for the Day
Structure Work
1.MJB rast casting completed at Ch 114+050 unit 6
2. MJB slab shuttering and wall plate fixing work in progress at Ch- 114+050 unit 2
3.Excavation completed for bpx culvert at Ch-109+551
4.Massonry work completed for return wall of box culvert at CH-109+180,109+300.
Highway work
1GSB top layer completed at Ch-100+740 to 100+950 BHS