Project Name:- Construction of Four Lane Realignment of old NH 207 (new NH 648) from TN/KA Border to Hoskote under

Bharatmala Pariyojna as part of Bangalore Ring Road in


Karnataka on Engineering Procurement and Construction (EPC) Mode.
Task List

Sr. No. Task Deadline Action taken Remarks

Today we discussed with the landowner, they will


1 Balance 3 acre land behind Camp Land should be in our possession till tomorrow 15.06.2022
start the tree cutting work as soon as possible.

Met with the land owner i.e. opposite side of our


camp area, 4 acre land available, out of this the
2 4 acre land in front of camp land should be in possession till tomorrow and level it 15.06.2022
owner of 2 acre was not available today, he will
come on Saturday,Then will settle and Finalize

3 Camp fencing material order

4 Pre-fab subcontractor finalise

5 Plan plant foundation

6 Setup office in containers in camp area

7 Find out Pond area for earthwork soil in all nearby villages

8 Apply for electricity connection of 700 KV in Camp area and 500 KV in crushing area

Miscellaneous Work

1 Met with SLAO Madam regarding the updated land Acquisition data, they are now working with the additional land & will be processed within 10-15 days.

2 We will give one more copy of JMC Map to LA team, they will fill the map with the current status as per our requirement.

3 Camp Topo is completed by survey Dept & already sent the data to group for further review and proceedings.

4 One jcb & tipper is received today from assam project

5 Searching of New guest house for staff in Doddadunnasandra is in progress

6 Security Guard has been mobilized in Camp area from Today itself.

7 Maintainace and Repairing of Available machinery going on,Tool box quotation sent to HO for Review and finalize.