MAHHSR
Jurisdiction
MAHSR
DPR
GM
GM S & T Operations
DGM
Dy CPM Elec Dy CPM C I Dy CPM C II Dy CPM C III DGM Admin
Finance
DGM C DGM C I
• The NIT was issued on 20.11.2019 but tender could not be opened due to the above
issues.
• TOD: 05.08.21
Shilphata Portal
Ghansoli Adit
Sawli Shaft
Vikhroli Shaft
Package C2
20.73 Km Tunnel from BKC (Ch 0.772) to ShilPhata ( Ch. 21.150) in Thane District
TBM
NATM
Package C2
• TBM; Ch 0km 772.86m to Ch 16km 232.50m i.e. 15.45km Tunnel
• NATM Ch 16km 267.50m to Ch 21km 150m i.e. 4.88km
• Proposed Shafts
• Shaft 01 at BKC (Exit Shaft)
• Shaft 02 at Vikhroli (entry Shaft for TBM 1 & 2)
• Shaft 03 at Sawli ( Entry shaft for TBM 3)
• Shaft 04 at Ghansoli (Adit shaft for NATM face 1 & 2 entry
• Tunnel Portal at Shil Phata, face 3 entry of NATM
• Tunnel Excavation Diameter = 13.1m; Finished tunnel diameter = 12.1m
Shaft 2 at Vikhroli
Ghansoli,
• MIDC Land Area -0.716 Ha, Acquired on 7th July 2019.
• Forest Land Area- 2.51 Ha, Awaiting Stage II Clearance. File is
with CM Maharashtra.
• Cutting of 1276 of trees (165nos in MIDC land + 1111nos in
Forest land).
• Permission for Cutting and Transplantation of 165nos trees from
MIDC land (0.716ha) received.
Land Acquisition at Tunnel Portal Area in Shilphata
Shilpahata
Thane HSR Station
Mathardi
Bharodi -Anjur
Thane Rolling Stock Depot
Land Acquisition Thane District including Depot
Category of Sub-District Total Acquired Balance Percentage Remarks
Land Required (Ha) (Ha) Progress
(Ha)
Bhiwandi JMR of 5Ha land for TSS and
58.26 35.17 23.08 60.38% additional road width
Private pending.
Thane
17.18 8.47 8.72 49.27%
Total 75.44 43.64 31.80 57.84 %
Bhiwandi 28.31 27.56 0.75 97.36%
Government Thane Out of this 0.39 ha land is
5.34 2.15 3.19 40.21% TMC land. Allotment
pending.
Total 33.65 29.71 3.94 80.29%
GRAND TOTAL 109.09 73.35 35.74 67.23%
MCGM / NHAI/ MOU signed for
RAILWAY 1.8632
Right of Way
Issues related to Land Acquisition
• Proposal for R & R scheme is under approval by commissioner,
Konkan division.
• Subsequently, R & R award for structures on government land to be
issued by R & R admin.
• Shifting of unauthorized secondary school building at government
land at Anjur. Land already transferred to NHSRCL.
• Slow progress of publication of land acquisition award. Especially for
land plot where structure exists. All awards need to be published by
Dec21 as validity of Section 19 is till Dec 21.
Package D1
Rolling stock Maintenance Depot and Stabling Yard in Thane
Issues
• Total progress of land is 46.50 ha out of 57.25 Ha. Remaining award
for 10.75 ha private land is to be published.
• DC Earthing/Grounding station of MSETCL is existing in 20.33 Ha of
land parcel of proposed Depot. Shifting of DC Earthing station on an
alternate location needs to be expedited by MSETCL. NHSRCL has
already made payment of Rs.14.45 Cr. to GoM treasury as per 7/12
records which was in the name of GoM.
• Consent of Grampanchayat Surai and Bharodi for diversion of a
existing road passing through depot.
• JMR of remaining 5 Ha of land in Bhiwandi Taluka.
MoEF&CC Clearances
Clearance Under Forest Conservation Act 1980
Clearance Under Wild Life Protection Act 1972
Coastal Regulation Zone Clearance:
Status of Various Clearances Required From MoEFCC
Environmental Clearance
• Not Required for this Project
Scope:
P-4(X)- Fabrication of 11 nos. steel truss bridges, qty of steel- 34780 MT TOTAL : 28 Bridges
P-4(Y)- Fabrication of 17 nos. steel truss bridges, qty of steel- 36085 MT & 70865 MT
Progress :
• 2 nos of workshops identified – Velmurugan for P-4(X) and Toolfab for P-4(Y) at Trichy and are under approval. Site visit
done on 21.06.21 and 22.06.21.
• Submission of Drawings and Contractual documents in progress:
o 1st set of Shop drawing for GAD 1134 for P-4(X) and GAD 61 for P-4(Y) submitted on 17.05.2021. This is the first
milestone and has been achieved.
Planning:
• Four workshops has been planned for fabrication of 70,865 MT of steel, the details are as under:
Package Description of UOM Workshop 1 Workshop 2 Workshop 3 Workshop 4 Total
Work (Velmurugan) (Toolfab)
P-4(X) Fabrication of Steel MT 16150 18630 34780
Bridge
P-4(Y) Fabrication of Steel MT 20000 16085 36085
Bridge
Total 70865
• The workshop-2 for P-4(X) and workshop-3 for P-4(Y) are yet to be finalized.
• Key Dates as per Construction Works Programme
As per CWP- P-4(X) As per CWP- P-4(Y)
Start of Fabrication for 1st Bridge 04.08.2021 07.08.2021
Check Assembly completion for 1st Bridge 05.11.2021 22.11.2021
Handing over to Installation Contractor for 1st Bridge 15.03.2022 12.04.2022
Detailed Project Report
FAD: Nagpur-Mumbai - 735 km
FAD: Mumbai-Pune-Hyderabad – 650 km
Nagpur Mumbai HSR FAD (LOA dt
09.11.2020)
• Site Reconnaissance Survey 18.12.2020
• Submission of Inception report-01.01.2021
• Establishment of GCP’s-25.02.2021
• Aerial LiDAR Survey-Dt 17.03.2021G
• Hydrological investigations- 31.05.2021
• Geological Study- 31.05.2021
• Final Alignment Design: In Progress
• Submission of Final Report (TDC 31.07.2021)
Mumbai-Pune-Hyderabad HSR FAD (LOA dt
31.12.2020