GNSS PROJECT (PHASE-II)

1 Project profile GNSS Package No: 7 Investigation, Design and


Earth work Excavation of GNSS Main Canal
from Km. 209.025 to KM 240.000 including
Construction of CM & CD works and Excavation
of Chitvel Branch Canal including construction
of CM & CD works for distributory system and
field Channels to feed an ayacut of 40,000 Acres
under Package -07/2006 of GNSS Phase-II in
Kadapa District
2 Utilization of water in TMC Nil
Administrative Sanction :
3 Rs. ECV value Rs. 155.46 Crores.
4 No of Packages 1
5 Agreement value of Package : RsRs. 117.99 Crs
(Pkgs 6 to 14)
6 Expenditure (Pkgs 6 to 14) : RsRs. 23.99 Crs
as on 31.03.2019

2
7 Progress of Work Total Completed % Balance
Qty of Earth work (L.Cum) : 1 17.40 13.04 Work is pre
closed

Qty of Concrete (L.Cum) : 0.35 000 0 work is pre closed

8 Land Acquisition (Ph-II 6 to 14) Required Requisitioned Acquired Balance


(Acres) 1230.80 1230.80 292.94 938.56

9 Forest (Ph-II 6 to 14) (Ha) Required Requisitioned Alienated Balance


0 0.000 0.00 0
IP Contemplated : 40000 acres
10

IP created as on 31.03.2019 : Nil-Acres (New), Nil- Acres (Stab)


11

3
12 Status of Land Acquisition 1. L.A is pending due to stiff resistance from the
formers as the canal is running in costly
13 Status of Forest horticulture lands.

(13)Canal alignment is not passing through forest

14 Structures (Nos) (6 to 14) Total Completed Progress Balance


(including Distributory :
System) (Revised Estimate is prepared and submitted for
Rs.552.81 Crores to the Government for approval)
15
Main Canal length (Km) : 30.975 9.00 0 21.975

Branch Canal length (Km) 67.00 0 0 67.00

4
Total Completed Progress Balance
16
National Highways (Nos) : 0 0 0 0
State Highways (Nos) :
9 - -- 9

3 0 0 3
Railway Crossings (Nos)
Tentative
17 R&R (for 6 to 14)

No. of villages affected Fully (Nos) : -----


No. of Housing units Shifted (Nos) : ------

No. of R & R Centers contemplated :


(Nos) ------
Exp. incurred :
-----
:
18 Irrigation Potential 40000
19 Kadapa - 40000
Districts benefited

20 Percentage of work done


(Physical) (6to14)
: 20.33(work is pre closed)

21 No of Lifts & Its details (if any) Nil


22 Target date of completion
: (subjected to approval of already submitted estimate)
5
23. Bottlenecks in detail : L.A is pending due to stiff resistance from the formers as the canal is running
in costly horticulture lands. Accouts are to be settled for the previous agency
for closure of contract. At present Peg marking from Ch.220.225KM to
Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in
Progress.

24 Any additional information (if any): The work is pre closed. Settlement of accounts is in progress. And
Estimate for balance quantities with current SSR 2018-19 is prepared and submitted to the Government
for approval for Rs.552.81 Crores.Total Land acquisition required is 1230.80 acres. Already acquired
land is 292.24 acres and the balance LA is 938.56 acres. Revised L.P schedules to an extent of 908.503
acres submitted to the Spl. Collector, GNSS kadapa on 16.05.2018. Field survey for LA is in progress.
Survey and peg marking completed for 176.45 acres. At present Peg marking from Ch.220.225KM to
Ch.220.825KM, 223.025KM to 223.925KM and 223.925KM to 225.025KM is in Progress.