Professional Documents
Culture Documents
Sides
GRAND SUMMARY FOR PART-1: CONSTRUCTION PHASE WORKS AND PART -2: MAINTENANCE PHASE WORKS
Div 2 Earthwork -
Div 5 Structures -
Div 6 Incidentals -
Specified Provisional Sums (Included in Total of Bills 1 to 7) = (B) Err:509 Taka Two hundred two crore forty four lac forty thousand only
Notes on price adjustment: The amount for price adjustment shall be calculated according to Clause13.8 of Conditions of Contract which shall be added to / subtracted from the
total Contract amount/ Bills
Square
Div-2, Cl. 2.1 2/1/1 Clearing and Grubbing 734,400
Metre
Part. Spec. Div-2,
2/1A/1 Deduct Compensation for the cost of trees LS 1 Taka Sixty five lac only (6,500,000)
Cl 2.1
Roadway Excavation in Unsuitable Soil including
Cubic
Div-2, Cl. 2.2 2/2/1 stockpiling or disposal in a location agreed by 8,000
Metre
Engineer
Part. Spec. Div-2, Roadway Excavation in suitable Soil (cutting Cubic
2/2/2 2,987
Cl. 2.2 materials) Metre
Cubic
2/5/1 Excavation and Backfill for Structures 62,702
Metre
Div-2, Cl. 2.5
Cubic
2/5/3 Sand Backfill for Structures 3,631
Metre
Cubic
2/6/1(a) Embankment Fill from excavation on site. 2,987
Metre
Div-2, Cl. 2.6
Embankment Fill from Borrow pit in Contractor's Cubic
2/6/2 1,803,574
Arranged land Metre
Square
Div-2, Cl. 2.7 2/7/2 Preparation of Subgrade 450 mm Depth 646,964
Metre
Cubic
Div-2, Cl. 2.8 2/8/1 Improved Subgrade 177,092
Metre
Kilometre-
1/1/1 a Protection of Traffic during Construction Phase 816
Part. Spec. Div-1, Month
Cl 1.1 Maintenance of existing Road during Construction Provisional
1/1/1 b Taka Seven Crore only 70,000,000
Phase Sum
1/2/1 Engineer's Office and other Facilities
Provide Engineer’s Permanent
1/2/1a Square Metre 300
Office Building
Part. Spec. Div-3, Supplying, spreading & compacting Sub base Cubic
3/2/1a 148,796
Cl 3.2 materials. Metre
Linear
04/01/01(f) Bored cast in place piles (Dia 1200mm ) 35,312
Part. Spec. Div-4, Metre
Cl 4.1
04/01/04(a) High Yield Deformed Steel Reinforcing Bars Tonne 3,917
Bridge/Flyover/Rail Overpass
Square
Div-5, Cl. 5.1 05/01/01 Single Layer Brick Flat Soling 11,131
Metre
Cubic
05/01/02c Concrete Class 15 as per Drawings 1,113
Metre
Part. Spec. Div-5,
Cl 5.1 Concrete Class - 35 for the different component of
Cubic
05/01/02d bridges, flyover and pedestrian overpasses as per 53,199
Metre
drawing
Part. Sp. Div-6, Providing and placing paving tiles as shown in the Square
06/18/01 11,880
Cl 6.18 drawing. Metre
Cubic
06/19/01a Concrete Class C-15 as per Drawing 680
Metre
Part. Sp. Div-6, Concrete Class C-25 New Jersey Barrier and other Cubic
Cl 6.19 06/19/01b 4,610
ancillary work Metre
High Yield Deformed Steel Reinforcing Bars (500
06/19/01c Tonne 50
N/mm2)
Summary of Bill No - 6: Incidentals
M/2 Provisional Sum for Emergency Maintenance Works 100,000,000 Taka ten crore only
Div-3
Square
M/3/1 Bituminous Tack Coat 601,438
Metre