Bangalore Weekly ZooM Meeting MoM Sat, 18th Jun’22

Today MoM (Harender)

1. Camp land will be finalized till tomorrow

2. Camp fencing material will be ordered by Sanjay Sir on Monday

3.Camp fabrication subcontractor has been finalized and he will mobilize soon

4. Plant foundation drawings has been received by site planning team

5. Site team will be search out pond locations in next week

6. Site planning team will give a detailed site execution planning till Monday

7. Site team will share LAP in next week

8. Site team will share material requirement for casting of chainage marking
pillar
Tasks : Wed, 15th Jun’22

1. Balance 3 acre land behind Camp Land should be in our possession till
tomorrow

2. 4 acre land in front of camp land should be in possession till tomorrow and
level it

3. @Sanjay.Yadav.avp.proc.skylark Camp fencing material order

4. Pre-fab subcontractor finalise

5. Plan plant foundation

6. Setup office in containers in camp area

7.@Anupam.Tiwari.Blr.DPM.Skylark Find out Pond area for earthwork soil in all


nearby villages

8. @☺️Apply for electricity connection of 700 KV in Camp area and 500 KV in


crushing area

By: Harender