Weekly Progress Meeting

 Project Title: Marquee Tent Construction Activity


 Duration :11th May – 28th July 2020

NO ITEM REMARK STATUS


1. Plan V Actual: This Week

 Installation of BRC on floor  Complete 100%


 Formwork activity  Complete 100%
 Pouring the ready-mix concrete  On-Going 25%
and levelling the floor for
finishing

2. Plan for Next Week

 Levelling and finishing the floor  1-2 days


 Curing the floor.  1 Week
 Loading of tent material.  3-4 Days

3. Issue & Concerns

 Delay in ramp work.  Work to Levelling


Floor and
Formwork for ramp
delayed due to
waiting pipe
relocation work
finished.
 Working schedule change during  SHE prohibits any
PKP period. construction work
for Ramada on
Weekend (Saturday
& Sunday) and
working time until
5.45pm.

 Heavy rain with


 Adverse weather condition strong wind at
evening cause work
to stop early.

4. Recovery Plan

 Perform other activity ahead  Start the activity


from the schedule while waiting with Y12 metal
for the pipe to finish relocate. stick and
framework activity.

 Catch-up other activity on  Since now PKPP


weekend. have start and SHE
allow contractor to
work on weekend,
Contractor planned
to extend daily
working time until
7pm and working
on weekend.