WEEKLY CONSTRUCTION PROGRESS REPORT

Construction of additional staff residence two rooms and safe house


Reporting Period: 1st to 7th October 2022

Contract Data
Location Pinyudo UNHCR Field Office Compound,
Project Name Construction of additional staff residence two rooms and safe house
Contract No. 16/UNHCR – GAMBELLA/SUP/2021
Employer United Nations High Commissioner for Refugees (UNHCR)
Contractor Mehari Alemayehu General Contractor
Commencement Date 01/01/2022
Contract Duration 5 Months (150 Days)
Original Completion Date 31/05/2022
Revised Completion Date 31/08/2022
Time Elapsed (Days) 277 days
Time Elapsed (%) 184%

Physical Progress of Works

Works completed during the week:


1. Parapet wall construction and capping (safehouse & Staff residence two rooms)
2. Roof slab & internal wall gypsum chalking (Staff residence two rooms)
3. PPR installation for shower rooms
4. Internal finishing and edge works

Works on progress during the week:


1. Roof slab & internal wall gypsum chalking (Staff residence two rooms)
2. Roof slab top (external) cement screeding
Works completed up to the end of the reporting week:
1. Installation of electricity conduits (safehouse & Staff residence two rooms)
2. Internal plastering (Safe house)
3. Installation of metal doors (safehouse & Staff residential two rooms)
4. Parapet wall construction (Staff residence two rooms)
5. Roof slab internal plastering (Staff residence two rooms)
6. Installation of aluminum doors (safehouse & Staff residential two rooms)
7. Parapet wall construction (safehouse)
8. Roof slab gypsum chalking (Staff residence two rooms)
9. PPR installation for shower rooms

Planned Major Activities for Next Week


1. External finishing and edge works
2. Gypsum works ((safehouse & Staff residence two rooms)
3. External wall pointing (safehouse & Staff residence two rooms)

Incidents
1. No incident.

Challenges / Risks / Constraints & Mitigation measures


1. The work progress is slow. Only one skilled labor team available. The contractor should escalate the
workforce.

Comments on the Project


No comment

Labour / Manpower Onsite


Designation No. on Site Remarks
Site Engineer/Foreman
Mason 03
Steel Worker
Laborers 06
Security guard

Equipment Onsite
Equipment Name No. on Site Remarks / Condition
Dump Truck 0
Hand Compactor - Not needed
Total Station - Not needed
Light Vehicles 0
Water Pumps (4”) - Not needed

Weather Report
Weather
Day Time Lost
Morning hours Afternoon Hours
Friday Sunny Sunny
Saturday Sunny Sunny
Monday Sunny Sunny
Tuesday Sunny Rainy
Wednesday Sunny Sunny
Thursday Sunny Rainy

Hours lost this week due to weather constraints 2 hours


Appendix: Site Pictures with Descriptions

Photo1: Internal finishing works (safe house)


Photo2: Parapet wall & steps work (safehouse)

Photo3: Internal finishing work (staff residence rooms) Photo4: Parapet wall capping (Staff residence rooms)