DAILY REPORT

Project : AI Soepomo Date of Daily : 03 Maret 2021


Client : SHELL INDONESIA Day : Rabu
Contractor : MPE Type of Work : CONTRUCTION

A. Working Conditions
Working Hours Weather Condition
Remark
Start Stop Over-Time Morning Afternoon Evening
08.00 WIB 17.00 WIB - Cerah Cerah Cerah

B. Manpower & Description of Work

Management Supervisor HSE Suport Team Worker Total


0 1 1 2 6 10

Perbaikan Conblock Perbaikan Conblock Perbaikan Green Zone

Bobok Lantai Forecourt Bobok Lantai Forecourt Bobok Lantai Forecourt

C. List of Equipment and Tools


1 Jack Drill
2 Pengki
3 Cangkul
4 Sekop
5 Gerobak

D. Encountered Problem

E. Planning for Next Day :


1 Pembobokan Forecourt