WEEKLY

Repair and ACCOMPLISHMENT


Improvement-Extension REPORT
and Room for MIC-B (JANUARY 29,2020)

By: RV LABORTE BUILDERS


MIC-B
ACCOMPLISHMENT (January 29,2020)

• COMMENCE DATE : FEBRUARY 08 2019


• COMPLETION DATE : NOVEMBER 15 2019
• CONTRACT DURATION (MONTHS) : 10 MONTHS
• CONTRACT DURATION (DAYS) : 280 days
• NUMBER OF DAYS ELAPSED : 336 days

• TARGET ACCOMPLISHMENT : 55.61%


• ACTUAL ACCOMPLISHMENT : 61.29%
• VARIANCE : 5.68%
• NUMBER OF DAYS DELAY/AHEAD : 22 days
See approved revised project schedule
MANPOWER LOADING

Previous ( As of Jan 21 ) Present ( As of Jan 28 )


Project Manager 1 Project Manager 1

Project In-Charge 1 Project In-Charge 1

Safety Officer 1 Safety Officer 1

Foreman 1 Foreman 1

Skilled Workers 1 Skilled Workers 1

Laborer Laborer

Warehouse Man Warehouse Man

Electrician 2 Electrician 2

Plumbing 2 Plumbing 2

Ducting 3 Ducting 3

FirePro 3 FirePro 3

Total Total
ACCOMPLISHMENT ( As of Jan 28 )

Weekly
Previous This Period To Date
Accomplishment

Target
54.00% 1.62% 55.61%
Accomplishment

Actual
54.00% 7.29% 61.29%
Accomplishment

Variance +5.67% +5.68%


SCHEDULE OF WORK THIS WEEK

Date Date
Description Status
Started Finished
Pouring of ramp @ third floor Pending
Ceiling Layout @ GF Jan 20 Jan 31 On-going
Plastering works and CHB
Layering main entrance @ 2nd & Jan 27 Jan 31 On-Going
3rd floor
Arranging of pipe layout enter in
Jan 27 Jan 31 On-going
the Electrical Room
Fabricate of duct layout for aircon
Jan 20 Jan 31 On-going
@ 2F and riser going up
Clear and grub the soil for main
layout pipes of firepro going to Jan 20 On-going
pump room
Create manhole for downspout Jab 20
PROGRESS PHOTOS

CHB layering and plastering


@ main entrance
Ducting works @ 2F and
riser up
Firepro main
pipes layout
going to pump
room
Arranging of
pipe going to
electrical room
THANK YOU