Professional Documents
Culture Documents
It was analyzed that there are high security risks associated with the operations from BVS11 to
BVS35 due to the proximity of this section with the Niger, Nigeria and Benin borders.
According to the security personnel allocation plan for the operation period, in the Niger section,
for the high-risk RTU BVSs (BVS-19, BVS-22, BVS-29, BVS-35),10 FPD should be allocated.
For other BV stations, there should be 2 watchmen (1 watchman for 12-hour day duty and 1
watchman for 12-hour night duty).
According to the security agreement with the Niger government, WAPCO should provide duty
rooms for them. Including 10-person duty rooms for 4 high-risk RTU BVS (BVS-19, BVS-22,
BVS-29, BVS-35), monitoring stations, drinking water supply points, and storage. the monitoring
stations will be carried out in HESCOs which is based on two (02) containers (20 feet). Storage
stores (food, ammunition, armament, and auto spare parts) will be in a container (40 feet) set up.
The water supply will be solved by digging a well in the station and can be transported to a 3-
meter-high water storage tank through a solar water pump. The solar power storage device is
configured to store electricity for 24-hour use for the camp. And place balking in front of camp
gates to stop vehicles.
And for the other BV stations, it is recommended to build a 2-person duty room for each one of
the left 21 BVSs.
II. PROJECT ORGANIZATION
2.1 Project Team
Personnel Requirements
Driller 1 Diffa
Water Well Drilling Assistant Driller 6 Diffa
Hydrogeologist 1 Diffa
Mason 8 Diffa
Excavator Operator 2 Diffa
Loader Operator 1 Diffa
Carpenter 4 Diffa
Duty Room Steel workers 8 Diffa
Construction Brick Layers 8 Diffa
Electrician 2 Diffa
Plumber 2 Diffa
Welder 2 Diffa
Laborers 16 Diffa
Project Manager
Ari Hassane
Construction Engineer
QHSE officer
Maman Saley
Assoumana Bankoula
DURATION
N° ACTIVITIES START DATE END DATE WEEK1 WEEK2
(DAYS)
DURATION
N° ACTIVITIES START DATE END DATE WEEK1 WEEK2 WEEK3 WEEK4 WEEK5 WEEK6 WEEK7 WEEK8 WEEK9 WEEK10 WEEK11 WEEK12 WEEK13 WEEK14 WEEK15 WEEK16 WEEK17
(WEEKS)
Quantity
Categories Brand Name Specification To be Degrees of Location
Own Rental
Purchased depreciation
Trailer BENZ ACTROS 6x6 10 - - 10% Jaouro-Diffa
Wheel Loader SEM SEM653D 2 - - Brand new Koulele
Excavator CAT CAT320GC 2 - - Brand new Koulele
Concrete mixer DIECI L4700 4 - - 22% Koulele
Dump Truck HOWO 2 - - Brand new Diffa
Roller Compactor XGMA XG6201 1 - - 50% Diffa
It is expected that the project will be constructed in 5 phases based on planning programme
and operations requirements:
1. Phase 1 will comprise of the preparation and materials procurement needed for the project
execution
2. Phase 2: Water well rig and team mobilization: Because water is the pre-requisite, the
four water wells will be first drilled and equipped with electric pumps for the drinking water
by the workers and for works.
3. Phase 3: Construction Teams and equipment Mobilization: In order to meet the deadline,
4 construction teams will be deployed and will work simultaneously and independently to the
different sites according to operations plan. It is planned that the first section be completely
finished before moving to section 2 of the project.
4. Phase 4: Pre-Construction: At this phase the sites are visited and cleared and all the
permanent materials needed for the construction such as concrete blocks, Steel bars molding
are made in required quantity.
5. Phase 5: Construction It is intended that each room will be constructed in the following
sequence:
➢ Excavation for foundation
➢ Foundation and sub-structure work
➢ Masonry Elevation
➢ Framing and Roofing
➢ Decoration-Doors-Windows
➢ Water-Electricity-Plumbing-Furniture
➢ Site Cleaning
6. Phase 6: HESCO&Store, Water tank and solar equipment installation
7. Phase 7: Commissioning
VI. HEALTH & SAFETY
• All fuel and chemicals to be stored in designated areas, with deliveries of hazardous
materials supervised.
• Storage tanks and container facilities will be appropriately bunded.
• In the case of spills or discharges, remedial action will be taken as soon as possible in
accordance with company procedures.
• Personal protective equipment (PPE) suitable to the pertaining conditions will be used
by all site personnel.
6.3 Environmental, Emergency and Accident Procedure
Measures will be carried out to avoid environmental incidents, however if these occur then the
following types must be reported to the responsible person in the construction team as per the
Site Accident & Emergency Procedure. The overall strategy in the event of a spillage will be
to ‘Stop-Contain-Notify’ in the event of:
1. Spills or discharge to the atmosphere, water supplies, sewage systems, rivers and
other watercourses, or to the ground:
• Any chemical products
• Oils or fuels
• Effluent/fumes and gases
• Waste or contaminated materials
2. Damage to existing:
• Trees and wildlife
• Flora and existing local habitats
Emergency routes and procedures will be continuously adapted to suit the construction
sequence and stage. An Emergency & Evacuation Plan will be prepared following the
guidelines detailed below and updated on a regular basis during construction:
First aid facilities will be established and at least one trained first aider will be present on-site
at all times.