Daily Activity Report

PROJECT: DATE:
Bayanihan Flats – Phase 2 August 14, 2019
LOCATION: WEATHER:
Pajac, Lapu-Lapu City Sunny Day
TO: FROM:
RDAK Land, Inc. CYC Construction
ELAPSED TIME: DAYS TO GO:
MANPOWER EQUIPMENT/ TOOLS
POSITION QTY. TYPE OPER. NON-OPER.
1. Project in Charge 2 Phase 2
2. Foreman 2 Backhoe √
3. Carpenter 16 Circular Saw √
4. Steel Man 12 Cut-off Machine √
5. Mason 10
6.
7.
8.
9.
ACTIVITIES ISSUES AND CONCERNS
Wednesday
Phase 1
- Cleaning up of Rough Cement Works in the Cistern
Tank
Phase 2
- Cleaning up and Arranging of the RMD Pieces
- Installation of the RMD Slab Formworks at Grids 1, 1’,
2, 2’, 3, 3’, 4, 4’, 5, 5’ and 6
- Fabrication of Rebars for the third floor suspended
slab
- Installation of the Formworks of the Stairs
- Continuation of the Installation of Rebars for the RC
Walls and Column
COMMENTS (To be filled up by Project Management Team)