GROUP ASSIGNMENT 1
(BOARD FENCE PROJECT)
PROJECT MANAGER
AMIDI BIN ADAM
DESIGN ENGINEER
SITE ENGINEER
WAN EMYRA ATIKA BINTI
DALILA BINTI BAKARI
WAN MOHD ROSLEE
SITE SUPERVISOR
UMAR BIN ABD AZIZ
WORKDONE AT SITE:
Note:
CLEAR
/ RAIN
Time 1st December 2015 – 31st December 2015
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
0800 - 0900
0900 - 1000 /
1000 - 1100 /
1100 - 1200
1200 - 1300
1300 - 1400
1400 - 1500
1500 - 1600
1600 - 1700
Total
Total time
N
CLEAR
/ RAIN
Table 1: Financial S-Curve
Table 1 illustrates the cost (RM) and cumulative cost (RM) of the project in seven weeks. In week 1, the
cost is the highest among the weeks. It causes a sharp increase rate in the cumulative cost of the project.
Starting from week 2, the cost per week drop dramatically and it maintain at a certain range for the rest
of the weeks. Therefore, the cumulative cost graph shows a gradually rising in the graph.
Table 2: Physical S-Curve
Table 2 shows the percent complete (%) and cumulative percent complete (%) for the first seven weeks
of the project. In the first seven weeks, week 2 has the highest percent of work completed which had
almost 20% of the project. However, the rest of the weeks in the first seven weeks has a low percent of
completing the project. Therefore, after seven weeks, only 49% of the project is complete.