Professional Documents
Culture Documents
S-curve and PDM- 24FJ0064
S-curve and PDM- 24FJ0064
B.5
A.1.1(8)
(72)
902(1)a1 506(1)
(23) (20)
CONTRACT ID: 19FJ0013
PROJECT TITLE: Local Program, Local Roads and Bridges - Local Roads - Local Infrastructure Program, 102(1)
B.9 104(2)a B.9
Construction of Concrete Road - Concreting of Junction Cabangcalan-Luna Road, Placer, Masbate A B C D 105(1)a E 200(1) F 311(1)b G H
0 0 2 24 4 7 7 27 27 50 50 70 7272
LOCATION: Brgy. Cabangcalan, Placer, Masbate (2) (2) (3)
(20) (23) (20)
(2)
CONTRACTOR: IGLEN SIA CONSTRUCTION
CONTRACT AMOUNT: P 13, 961, 930.31
START DATE: - 101(4)a1 500(1)a3
EXPIRY DATE: - (23) (20)
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT % 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
WT. 18 C.D. 18 C.D. 18 C.D. 18 C.D.
PART A FACILITIES FOR THE ENGINEER
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 2.40 month 11,235.00 26,964.00 0.193
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 each 4,914.00 9,828.00 0.070
B.7(2) Occupational Safety & Health Program 1.00 l.s. 147,420.00 147,420.00 1.056
B.8(1) Traffic Management 2.40 month 16,852.50 40,446.00 0.290
B.9 Mobilization / Demobilization 1.00 l.s. 512,103.81 512,103.81 3.668
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees (Small a, 150-300mmØ) 25.00 each 1,265.16 31,629.00 0.227
101(4)a1 Removal of Actual Structures / Obstruction (610mmØ RCPC) 24.00 l.m. 2,512.90 60,309.60 0.432
102(1) Unsuitable Excavation 2,187.20 cu.m. 432.28 945,482.82 6.772
104(2)a Embankment from Borrow (Common Soil) 2,070.33 cu.m. 755.21 1,563,533.92 11.199
105(1)a Subgrade Preparation (Common Material) 8,000.00 sq.m. 105.16 841,280.00 6.026
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 2,450.10 cu.m. 882.79 2,162,923.78 15.492
PART E SURFACE COURSE
311(1)b1 PCCP (Unreinforced, 200mm, 14 days) 5,000.00 sq.m. 1,424.11 7,120,550.00 51.000
PART G DRAINAGES AND SLOPE PROTECTION STRUCTURES
506(1) Stone Masonry 45.20 cu.m. 4,294.42 194,107.78 1.390
500(1)a3 Pipe Culverts, 910mmØ 40.00 l.m. 7,633.79 305,351.60 2.187
TOTAL 13,961,930.31 100.000
LEGEND: CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
S-CURVE
FOR THE MONTH OF 1ST QUARTER 2ND QUARTER 3RD QUARTER 4TH QUARTER
18 C.D. 18 C.D. 18 C.D. 18 C.D.
PERIODIC 23.921 9.433 20.747 45.898
PHYSICAL ACCOMPLISHMENT
COMMULATIVE 23.921 33.355 54.102 100.000
PERIODIC 3,339,899.77 1,317,077.95 2,896,728.68 6,408,223.91
CASH FLOW SCHEDULE
COMMULATIVE 3,339,899.77 4,656,977.72 7,553,706.40 13,961,930.31
PROJECT ENGINEER 1.00 1.00 1.00 1.00
MATERIALS ENGINEER 1.00 1.00 1.00 1.00
CONSTRUCTION FOREMA 1.00 1.00 1.00 1.00
MANPOWER UTILIZATION CONST. SAFETY & HEALTH 1.00 1.00 1.00 1.00
SCHEDULE FIRST AIDER 1.00 1.00 1.00 1.00
SKILLED WORKERS 6.00 6.00 7.00 7.00
COMMON LABORERS 8.00 8.00 9.00 9.00
OPERATORS 3.00 3.00 4.00 2.00
BACKHOE (0.8cu.m.) 1.00 1.00 1.00 1.00
ROAD ROLLER 1.00 1.00 1.00 -
GRADER 1.00 1.00 1.00 -
EQUIPMENT UTILIZATION
SCHEDULE TRANSIT MIXER - - 1.00 1.00
ONE-BAGGER MIXER - 1.00 1.00 1.00
BAR CUTTER 1.00 1.00 1.00 1.00
MINOR TOOLS ENOUGH ENOUGH ENOUGH ENOUGH
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
EGLIN E. SIA MARK SAMMY L. DISCAYA FLORANTE U. ZURBITO RIZALINA V. VERDIDA ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION OIC - ASST. DISTRICT ENGINEER DISTRICT ENGINEER
IGLEN SIA CONSTRUCTION
B.5
A.1.1(8)
(72)
902(1)a1 506(1)
(23) (20)
CONTRACT ID: 19FJ0013
PROJECT TITLE: Local Program, Local Roads and Bridges - Local Roads - Local Infrastructure Program, 102(1)
104(2)a B.9
Construction of Concrete Road - Concreting of Junction Cabangcalan-Luna Road, Placer, Masbate AB.9B C D 105(1)a E 200(1) F 311(1)b G H
LOCATION: Brgy. Cabangcalan, Placer, Masbate 0 0 2 24 4 7 7 (20) 27 27 (23) 50 50 (20) 70 7272
(2) (2) (3) (2)
CONTRACTOR: IGLEN SIA CONSTRUCTION
CONTRACT AMOUNT: P 13, 961, 930.31
START DATE: July 2, 2019 101(4)a1 500(1)a3
EXPIRY DATE: September 11, 2019 (23) (20)
CONTRACT DURATION: 72 C.D. B.7(2)
B.8(1)
PERT / CPM NETWORK AND S-CURVE (72)
PLANNED PERIODIC
ACCOMPLISHMENT COMMULATIVE
ACTUAL PERIODIC
ACCOMPLISHMENT COMMULATIVE
SLIPPAGE
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
EGLIN E. SIA MARK SAMMY L. DISCAYA FLORANTE U. ZURBITO RIZALINA V. VERDIDA ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION OIC - ASST. DISTRICT ENGINEER DISTRICT ENGINEER
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
B.5
Masbate II A.1.1(8)
DISTRICT ENGINEERING OFFICE (72)
REGIONAL OFFICE V
Dimasalang, Masbate 902(1)a1 506(1)
(23) (20)
CONTRACT ID: 19FJ0013
PROJECT TITLE: Local Program, Local Roads and Bridges - Local Roads - Local Infrastructure Program, 102(1)
104(2)a B.9
Construction of Concrete Road - Concreting of Junction Cabangcalan-Luna Road, Placer, Masbate AB.9B C D 105(1)a E 200(1) F 311(1)b G H
LOCATION: Brgy. Cabangcalan, Placer, Masbate 0 0 2 24 4 7 7 (20) 27 27 (23) 50 50 (20) 70 7272
(2) (2) (3) (2)
CONTRACTOR: IGLEN SIA CONSTRUCTION
CONTRACT AMOUNT: P 13, 961, 930.31
START DATE: July 2, 2019 101(4)a1 500(1)a3
EXPIRY DATE: September 11, 2019 (23) (20)
CONTRACT DURATION: 72 C.D. B.7(2)
B.8(1)
PERT / CPM NETWORK AND S-CURVE (72)
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT % JULY 2019 AUGUST 2019 SEPT. 2019
WT. 2-15 16-31 1-15 16-31 1-11
PART II FACILITIES FOR THE ENGINEER
B.5 Project Billborad/Signboard 2.40 month 11,235.00 26,964.00 0.193
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 each 4,914.00 9,828.00 0.070
B.7(2) Occupational Safety & Health Program 1.00 l.s. 147,420.00 147,420.00 1.056
B.8(1) Traffic Management 2.40 month 16,852.50 40,446.00 0.290
B.9 Mobilization / Demobilization 1.00 l.s. 512,103.81 512,103.81 3.668
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees (Small a, 150-300mmØ) 25.00 each 1,265.16 31,629.00 0.227
101(4)a1 Removal of Actual Structures / Obstruction (610mmØ RCPC) 24.00 l.m. 2,512.90 60,309.60 0.432
102(1) Unsuitable Excavation 2,187.20 cu.m. 432.28 945,482.82 6.772
104(2)a Embankment from Borrow (Common Soil) 2,070.33 cu.m. 755.21 1,563,533.92 11.199
105(1)a Subgrade Preparation (Common Material) 8,000.00 sq.m. 105.16 841,280.00 6.026
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 2,450.10 cu.m. 882.79 2,162,923.78 15.492
PART E SURFACE COURSE
311(1)b1 PCCP (Unreinforced, 200mm, 14 days) 5,000.00 sq.m. 1,424.11 7,120,550.00 51.000
PART G DRAINAGES AND SLOPE PROTECTION STRUCTURES
506(1) Stone Masonry 45.20 cu.m. 4,294.42 194,107.78 1.390
500(1)a3 Pipe Culverts, 910mmØ 40.00 l.m. 7,633.79 305,351.60 2.187
TOTAL 13,961,930.31 100.000
LEGEND: CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
S-CURVE
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
EDISON A. ANDRADE MARK SAMMY L. DISCAYA FLORANTE U. ZURBITO RIZALINA V. VERDIDA ROMEO D. DOLOIRAS
PROJEC INSPECTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION OIC - ASST. DISTRICT ENGINEER DISTRICT ENGINEER
IGLEN SIA CONSTRUCTION
B.5
A.1.1(8)
(72)
902(1)a1 506(1)
(23) (20)
CONTRACT ID: 19FJ0013
PROJECT TITLE: Local Program, Local Roads and Bridges - Local Roads - Local Infrastructure Program, 102(1)
104(2)a B.9
Construction of Concrete Road - Concreting of Junction Cabangcalan-Luna Road, Placer, Masbate AB.9B C D 105(1)a E 200(1) F 311(1)b G H
LOCATION: Brgy. Cabangcalan, Placer, Masbate 0 0 2 24 4 7 7 (20) 27 27 (23) 50 50 (20) 70 7272
(2) (2) (3) (2)
CONTRACTOR: IGLEN SIA CONSTRUCTION
CONTRACT AMOUNT: P 13, 961, 930.31
START DATE: July 2, 2019 101(4)a1 500(1)a3
EXPIRY DATE: September 11, 2019 (23) (20)
CONTRACT DURATION: 72 C.D. B.7(2)
B.8(1)
PERT / CPM NETWORK AND S-CURVE (72)
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT % JULY 2019 AUGUST 2019 SEPT. 2019
WT. 2-15 16-31 1-15 16-31 1-11
PART A FACILITIES FOR THE ENGINEER
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 2.40 month 11,235.00 26,964.00 0.193
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 each 4,914.00 9,828.00 0.070
B.7(2) Occupational Safety & Health Program 1.00 l.s. 147,420.00 147,420.00 1.056
B.8(1) Traffic Management 2.40 month 16,852.50 40,446.00 0.290
B.9 Mobilization / Demobilization 1.00 l.s. 512,103.81 512,103.81 3.668
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees (Small a, 150-300mmØ) 25.00 each 1,265.16 31,629.00 0.227
101(4)a1 Removal of Actual Structures / Obstruction (610mmØ RCPC) 24.00 l.m. 2,512.90 60,309.60 0.432
102(1) Unsuitable Excavation 2,187.20 cu.m. 432.28 945,482.82 6.772
104(2)a Embankment from Borrow (Common Soil) 2,070.33 cu.m. 755.21 1,563,533.92 11.199
105(1)a Subgrade Preparation (Common Material) 8,000.00 sq.m. 105.16 841,280.00 6.026
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 2,450.10 cu.m. 882.79 2,162,923.78 15.492
PART E SURFACE COURSE
311(1)b1 PCCP (Unreinforced, 200mm, 14 days) 5,000.00 sq.m. 1,424.11 7,120,550.00 51.000
PART G DRAINAGES AND SLOPE PROTECTION STRUCTURES
506(1) Stone Masonry 45.20 cu.m. 4,294.42 194,107.78 1.390
500(1)a3 Pipe Culverts, 910mmØ 40.00 l.m. 7,633.79 305,351.60 2.187
TOTAL 13,961,930.31 100.000
LEGEND: CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
S-CURVE
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
EGLIN E. SIA MARK SAMMY L. DISCAYA FLORANTE U. ZURBITO RIZALINA V. VERDIDA ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION OIC - ASST. DISTRICT ENGINEER DISTRICT ENGINEER
A.1.1(8)
(93)
902(1)a1 506(1)
(29) (30)
CONTRACT ID: 18FJ0089
PROJECT TITLE: Concreting of Tunga - Libertad FMR, Brgy. Tunga and
104(2)a B.9
Brgy. Libertad, Esperanza, Masbate AB.9B C D 105(1)a E 200(1) F 311(1)b G H
LOCATION: Esperanza, Masbate 0 2 4 7 (26) 33 33 (28) 61 61 (30) 91 93
(2) (2) (3) (2)
CONTRACTOR: SQUARE N CONSTRUCTION & SUPPLY 102(2)
CONTRACT AMOUNT: P 16, 069, 082.61
START DATE: August 16, 2018 101(4)a1 500(1)a3
EXPIRY DATE: November 16, 2018 (29) B.5 (30)
CONTRACT DURATION: 93 C.D. B.7(1)
B.8(1)
(93)
PERT / CPM NETWORK AND S-CURVE
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT % AUGUST 2018 SEPTEMBER 2018 OCTOBER 2018 NOVEMBER 2018
WT. 16-31 1-15 16-30 1-15 16-31 1-16
PART A FACILITIES FOR THE ENGINEER
A.1.1(8) Provision of Field Office for the Engineer (Rental Basis) 3.10 month 11,796.75 36,569.93 0.228 0.039 0.037 0.037 0.037 0.039 0.039
PART B OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 2.00 each 6,352.50 12,705.00 0.079 0.014 0.013 0.013 0.013 0.014 0.014
B.7(1) Occupational Safety & Health Program 3.10 month 41,569.50 128,865.45 0.802 0.138 0.129 0.129 0.129 0.138 0.138
B.8(1) Traffic Management 3.10 month 31,458.00 97,519.80 0.607 0.104 0.098 0.098 0.098 0.104 0.104
B.9 Mobilization / Demobilization 1.00 l.s. 56,928.57 56,928.57 0.354 0.177 0.177
PART C EARTHWORKS
100(3)a1 Individual Removal of Trees (Small a, 150-300mmØ) 40.00 each 1,202.15 48,086.00 0.299 ### 0.155
101(4)a1 Removal of Actual Structures / Obstruction (610mmØ RCPC) 12.00 l.m. 1,542.07 18,504.84 0.115 0.048 0.059
102(2) Surplus Common Excavation 7,157.49 cu.m. 189.27 1,354,698.13 8.430 8.430
104(2)a Embankment from Borrow (Common Soil) 2,064.74 cu.m. 599.52 1,237,852.92 7.703 7.703
105(1)a Subgrade Preparation (Common Material) 8,680.00 sq.m. 36.83 319,684.40 1.989 0.689 1.148 0.153
PART D SUBBASE AND BASE COURSE
200(1) Aggregate Subbase Course 2,706.37 cu.m. 1,003.70 2,716,383.57 16.904 7.848 9.056
PART E SURFACE COURSE
311(1)b PCCP (Unreinforced, 200mm, 14 days) 5425.00 sq.m. 1,804.67 9,790,334.75 60.927 32.494 28.433
PART G DRAINAGES AND SLOPE PROTECTION STRUCTURES
506(1) Stone Masonry 15.49 cu.m. 5,319.86 82,404.63 0.513 0.274 0.239
500(1)a3 Pipe Culverts, 910mmØ 18.00 l.m. 9,363.59 168,544.62 1.050 0.560 0.490
TOTAL 16,069,082.61 100.000
LEGEND: CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
S-CURVE
FOR THE MONTH OF AUGUST 2018 SEPTEMBER 2018 OCTOBER 2018 NOVEMBER 2018
16-31 1-15 16-30 1-15 16-31 1-16
PLANNED 17.47 1.638 8.278 9.332 33.623 29.634
MONTHLY
ACTUAL
PLANNED 17.465 19.103 27.382 36.714 70.337 99.971
CUMMULATIVE
ACTUAL
SLIPPAGE
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT ENGINEER
DECEMBER JANUARY FEBRUARY
FOR THE MONTH OF
AA A B C D E
PLANNED
MONTHLY
ACTUAL
PLANNED 0.000 5.000 35.000 45.000 65.000 79.000
CUMMULATIVE
ACTUAL
SLIPPAGE
95.000 100.000
jan 1-15 jan 16-31 feb 1-15 feb 16-28 mar 1-15 mar 16-31 apr 1-15 apr 16-30 may 1-15 may 16-31
10.476 0 0 11.189 9.537 9.008 3.516 6.635 5.236 4.271
49.139 49.139 49.139 60.328 69.865 78.873 82.389 89.024 94.260 98.531
100.000
A.1.1(8)
(93)
902(1)a1
(29)
1
CONTRACT ID: 18FJ0089 0
PROJECT TITLE: Concreting of Tunga - Libertad FMR, Brgy. Tunga and 4 B
B.9 ( .
Brgy. Libertad, Esperanza, Masbate A B 2 105(1)a E 200(1) F H9
LOCATION: Esperanza, Masbate 0 2) (26) 33 33 (28) 61 61 (
(2)(2) a 23
CONTRACTOR: SQUARE N CONSTRUCTION & SUPPLY 102(2) )
CONTRACT AMOUNT: P 16, 069, 082.61
START DATE: August 16, 2018 101(4)a1
EXPIRY DATE: November 16, 2018 (29) B.5
CONTRACT DURATION: 93 C.D. B.7(1)
B.8(1)
(93)
PERT / CPM NETWORK AND S-CURVE
ITEM NO. DESCRIPTION QTY. UNIT UNIT COST AMOUNT % Jan-24 Feb-24 Mar-24
WT. 29-31 1-15 16-29 1-15 16-18
PART II OTHER GENERAL REQUIREMENTS
B.5 Project Billboard / Signboard 1.00 Each 6,037.91 6,037.91 0.006
B.7(2) Occupational Safety & Health Program 1.00 L.S 63,423.13 63,423.13 0.067
B.9 Mobilization / Demobilization 1.00 L.S 12,763.80 12,763.80 0.014
PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS
PART A EARTHWORKS
801(1) Removal of Structures and Obstruction 1.00 L.S 56,605.97 56,605.97 0.060
PART B PLAIN AND REINFORCED CONCRETE WORKS
900(1)c1 Structural Concrete (Class A, 28 days) 0.78 cu.m. 9,314.88 7,265.61 0.008
902(1)a Reinforcing Steel (Deformed), Grade 40 395.82 cu.m. 117.77 46,615.72 0.049
903(2) Formworks & Falseworks 18.08 sq.m. 1,017.90 18,403.63 0.019
PART C FINISHING WORKS
1003(1)a1 Ceiling (Fiber Cement Board 4.5 mm thk on Meatl Frame) 9.00 sq.m. 1,331.94 11,987.46 0.013
1003(2)h Wall 1.00 l.s. 32,768.01 32,768.01 0.035
1010(2)b Wooden Panel Door 1.80 sq.m. 10,512.94 18,923.29 0.020
1018(1) Glazed Tiles & Trims 28.80 sq.m. 2,468.36 71,088.77 0.075
1018(2) Unglazed Tiles (Floor) 20.01 sq.m. 1,469.23 29,399.29 0.031
1027(1) Cement Plaster Finish 10.39 sq.m. 344.42 3,578.52 0.004
1032(1)a Painting Works (Masonry/Concrete) 194.96 sq.m. 397.64 77,523.75 0.082
1032(1)b Painting Works (Wood) 26.40 sq.m. 516.64 13,639.30 0.014
PART H MISCELLANEOUS STRUCTURES
628(11) Structural Concrete Injection and Crack Repair 1.00 l.s. 473,952.34 473,952.34 0.502
TOTAL 943,976.50 1.000
LEGEND: CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
S-CURVE
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT ENGINEER
CONTRACT ID: 24FJ0064
PROJECT TITLE: Convergence and Special Support Program - Rainwater Collectors System (RWCS)
LOCATION: Bugtong Elementary School, Bugtong, Pio V. Corpus, Masbate
CONTRACTOR: JRMG Construction and Supply
CONTRACT AMOUNT: P 406,131.39
START DATE:
EXPIRY DATE:
CONTRACT DURATION: 73 C.D
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT
4th QUARTER
14 CD
0.0149305130046708 0.0149305130046708
0.012798
0.0270760282774498
4th QUARTER
14 CD
6.97%
68.61%
28,321.43
278,662.37
APPROVED BY:
ROMEO D. DOLOIRAS
DISTRICT ENGINEER
ROMEO D. DOLOIRAS
DISTRICT ENGINEER
JANUARY FEBRUARY
FOR THE MONTH OF
AA A B
PLANNED
MONTHLY
ACTUAL
PLANNED 0.00% 6.73% 49.10% 61.64% 68.61%
CUMMULATIVE
ACTUAL
SLIPPAGE
dec
FOR THE MONTH OF
A B D
PLANNED
MONTHLY
ACTUAL
PLANNED 0.000 5 27.386
CUMMULATIVE
ACTUAL
SLIPPAGE
dec 1-15 dec 16-31 jan 1-15 feb 1-15 feb 16-28 mar 1-15 mar 16-31 apr 1-15 apr 16-30 may 1-15
13.045 11.202 10.476 0 11.189 9.537 9.008 3.516 6.635 5.236
#REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF! #REF!
#REF! 100.000
CONTRACT ID: 24FJ0044
PREPARED BY: CHECKED AND SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
A.1.1(8)
B.7(1) 13 56
B.8(1)
Provision of Field Office for the
Engineer (Rental Basis), Occupational
Safety and Health Program, Traffic
Management
0 56
0 56
0 3 3 9 9 15 15 22 22 30 30 39 39 53 53 56
0 3 3 9 9 15 15 22 22 30 30 39 39 53 53 56
-6
LEGEND:
CRITICAL ACTIVITIES
PARALLEL ACTIVITIES
PREPARED BY: CHECKED AND SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
PREPARED BY: REVIEWED BY: SUBMITTED BY: RECOMMENDING APPROVAL: APPROVED BY:
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT ENGINEER
NEIL L. NUÑEZ HILARIO A. MANLANGIT FLORANTE U. ZURBITO MARIANO M. ESPARES, JR. ROMEO D. DOLOIRAS
CONTRACTOR PROJECT ENGINEER CHIEF, CONSTRUCTION SECTION ASST. DISTRICT ENGINEER DISTRICT ENGINEER
4th QUARTER
14 CD
0.0004
0.00094471156725009
0.00130806217003859
0.004031
0.40981703932284
4th QUARTER
14 CD
41.92%
100.00%
4,027,091.16
9,606,682.15
APPROVED BY:
ROMEO D. DOLOIRAS
DISTRICT ENGINEER
ROMEO D. DOLOIRAS
DISTRICT ENGINEER