Foreword

Inspections are an integral part of the various safety measures


undertaken by the Railways to make train-mode transport safe,
comfortable, efficient and punctual. Inspections in general means
visits to various work centres to carefully examine the working of
the system; find out the defects and to see that rules and
instructions are implemented according to their spirit. It is both
educative and corrective in nature.
The Civil Engineering assets comprise important part in Railway
system and its upkeep is very important from safety and comfort point
of view. This handbook containing compendium of instructions
related to inspection of civil engineering assets would be of great
help to all the inspecting officials. An attempt has been made in
formulating certain frame work which will be of help in facilitating
focussed and in-depth inspections of civil engineering asset.
The information presented in this book is in no way intended to
supersede or negate any existing rules, regulations, or instructions
contained in various codes and manual. Further, it is not intended to
conflict with any currently effective operating and maintenance
instructions and/or specifications. It also cannot be taken as
exhaustive. It should, however, always be kept in mind that
inspections are not merely fault finding. It is one of the most
effective tools that can be intelligently used to run the system
smoothly and safely.
It is hoped that all Engg officials will make use of present book
during their inspections in improving quality of inspections and
thereby bringing overall improvement in productivity and
performance enhancement of Civil Engg. assets in particular and Rly
system in general.

(Vishwesh Chaubey)
Director/IRICEN
iii
iv
CONTENTS

S.N. Title Page


1 Inspection schedule of Engineering Officials
A. Sr.DEN/DEN 1
B. ADENS 4
C. SSE/SE/JE (P.Way) 9
D. SSE (Works) 14
E. Bridge Organization 18
F. Track Machine Organization 20
2 List of Functionaries Authorise to issue Competency
Certificate for various track activities 23
3 Check List for different Registers for Track Maintenance 41
4 Check list for Inspection of Open Line Organization
A. Track 65
B. SSE (P.Way) Office/Store 82
C. USFD testing 83
D. AT Welding 91
E. Level Crossing 107
F. Tamping Machine 116
G. Ballast Cleaning Machine 131
H. Check List of Concrete Sleeper Plant 150
I. Bridges & Tunnels 157
J. Passenger Amenities 169
K. Colony And Other Buildings 187

v
S.N. Title Page
L. Land matters 192
M. Steel Structures in Work Shops, Running Sheds &
P/F Covers 197
N. Steel Water Tank, Staging and Flood Light Towers 198
O. Water Supply Installation 200
P. Rain Water Harvesting System 203
5 Check List for New Construction Site
A. Worksite 204
B. Work in/near Electrified Area 206
C. Precautions within Station Premises 207
D. Track Ballast 207
E. Formwork in Concrete Work 210
F. Box Pushing Work 210

vi
CHAPTER - 1
INSPECTION SCHEDULES OF ENGINEERING OFFICIALSG

A. Inspection Schedules of Sr. DENs /DENs

S. Type of Schedule of Reference


N. Inspection Inspection
1. Push Trolley Once in four month.
Inspection Unimportant branch line
having less than 2 GMT
traffic – Once in 6 month

2. Foot Plate/ Brake Once in three month to


Van/Rear Window cover his entire section
either by footplate, rear- RB No.
window, TRC or OMS. 2013/CE-11/
3. Points & Crossings At least one Point & Cross- CS/1 dated
ing on passenger running 20.06.2013
line as often as possible
4. Level Crossing Minimum one Level
Crossing per PWI every
three month
5. LWR/SEJs During routine motor
trolley/push trolley or
foot inspection
6 Hot Weather As and when required
Patrolling

1
S. Type of Schedule of Reference
N. Inspection Inspection
7. Curves Minimum one curve in
each ADEN’s section every
four month
8 Inspection of As much as possible
ongoing works of during Foot Plate/Trolley
construction and inspections to check quality
other organization and safety
e.g. RVNL etc RB No.
2013/CE-
9. Land boundary During trolley inspection at II/CS/1 dated
verification vulnerable locations 20.06. 2013
10. Track renewal/ As much as possible during
Deep Screening site Trolley inspection
11. AT welding site As much as possible during
Trolley inspection
12. Private sidings When referred
13. Review of Routine checking during
inspection by trolley inspection
subordinate
14. Bridge:
• Important Bridge • Once in a year
• On reference by • On reference
ADEN
• Bridge with • Once in a year Para 1104
Overall Rating of IRBM
number (ORN)
1,2,3

2
S. Type of Schedule of Reference
N. Inspection Inspection
15. Tunnel on on reference Para 1104
reference of IRBM
from ADEN
16. Inspection of Track
machines working
in the section
• CSM, BCM, FRM, • Once a two month when
P&C Tamper, DTS working in section
• T-28, PQRS • At least once in a month
• UT, UNO, DUO, • As per need
BRM RB No. 2013/
CE- II/CS/1
17. Night/surprise Minimum once in three dated
Inspection month. More intensive 20.06.2013
during monsoon
18. Monsoon Patrolling Minimum once in two
month to evaluate
adequacy of safety
19. Gang Inspection Minimum one gang per .
SSE every three month
20. Railway Affecting Peruse the inspection
Works/ Tanks report of revenue /PWD
and forward, with name Para 726 of
of Tank (so marked) for IRPWM
inspection by ADEN to
report upon.
21. TRC/OMS run Accompany each TRC run RB No. 2013/CE-
and alternate OMS run II/CS/1 dated
20.06.2013
3
S. Type of Schedule of Reference
N. Inspection Inspection
2 2 Inspection of Once a year IRPWM Para
waterworks 554 (d)

B. Inspection Schedule of ADEN

S. Type of Schedule of Reference


N. Inspection Inspection
1. Push Trolley Entire section Main Line
Inspection – Once in 2 month Para 107 (1) of
Unimportant branch Lines IRPWM
having GMT < 2 (C.S. No. 132)
– once in 3 month
2. Fast train Entire sub-division either Para 107 (2) of
inspection by engine / rear window IRPWM
of a fast train or by TRC/ (C.S. No. 132)
OMS - Once a month
3. Points & All Points & Crossings on
Crossings passenger lines once a year Para 107(5) of
& 10% of Points & IRPWM
Crossings on other lines
4. Level Crossing All manned Level crossings Para 107(3) of
- Once in six month IRPWM (C.S. No.
132)
5. LWR Once in six month Para 8.1.5(ii) of
(Preferably in hottest and LWR Manual
coldest month)
6. Curves One curve each SSE Para 107(4) of
jurisdiction every quarter IRPWM

4
S. Type of Schedule of Reference
N. Inspection Inspection
7. Bridge Once in a year after Para 102(a) of
monsoon IRBM
8 Inspection of Side Once in a year before
drains, Catch water on set of rains Para 223(C) of
drains and Water IRPWM
ways of bridges & CS no. 132
culvert
9 Inspection of Once in a year before Para 1011 of
Cutting onset of rain IRBM C.S. NO.28
10. Tunnel Once in a year before Para 1004 of
Monsoon IRBM
11 Inspection of Track
machines working
in the section
• CSM, BCM, FRM, • Once a month when C.S. No.14 of
P&C Tamper, DTS working in section IRTMM
• T-28, PQRS, TRT • At least once in fortnight Para 5.3.3
& RGM
• UT, UNO, DUO, • At least once in a period
BRM of working in their section
12. Night foot plate Once in a month between Para 107 of
Inspection 0.0 – 4.00 hrs. IRPWM
13. AT Welding AT welding each site as Para 107 (11) of
much as possible but at IRPWM
least once in a month C S NO. 132.

5
S. Type of Schedule of Reference
N. Inspection Inspection
14. Test check of USFD USFD checking few hours Para 4.3 of USFD
Inspection each month (min. two manual 2012
hours) during regular
Trolley Inspection.
15. Monsoon At night once in a month Para 107 (6) of
Patrolling either by train, push IRPWM
trolley, Motor trolley. (C.S. No. 132)
16. Private Sidings Min. once in a year S. NO.1.4
Inspection
Manual Rly.Bd.
17. Gang Inspection Min. one Gang each SSE Para 107 (1) of
every quarter IRPWM
(C.S. No. 132)
18. RAW/RAT Min. once in a year before Para 726 of
inspection monsoon IRPWM
19. Inspection of Sand Min. once in a year -
Humps
20. Inspection of Steel Once in 12 month Para 273(b)(7) of
Channel Sleepers alternately with SSE IRPWM
(P way) (C.S.No. 128)
21. TRC/OMS Run Every Run Para 111 of
IRPWM

6
S. Type of Schedule of Reference
N. Inspection Inspection
22. Inspection of
Steel Structures
• Structure such as work- • One fifth every year
shops, running sheds, on a programmed
platform covers and basis
foot over bridges
• Cast iron, wrought • As required
iron or pressed
steel plate water
tanks and
staging’s whether of
steel section or rails
• Structures with roof • 10-20% test check
trusses inspection of struc-
Para 228(a)
ture under each
of IRWM
group
• Other structures in • 10-20% test check
which timber, rail or inspection of
steel work is used to structure under
support any part of the each group
structure
• Tie rods of arched roof • 10-20% test check
excluding jack inspection of
structure under
each group
• Wrought iron or mild • 10-20% test check
steel tanks or sleeper inspection of
cribs at temporary structure under
watering kilometerage. each group

7
S. Type of Schedule of Reference
N. Inspection Inspection

23. Inspection of staff As many buildings Para 224 (d)


quarters & service (particularly those of IRWM
buildings required heavy repairs)
24. Inspection of water Once in 3 month Para 554(c)
supply installations (i) of IRWM
25. Inspection of Land Once a year Para 813 of
boundary and IRWM
Encroachment
26. Inspection of colony Once in 2 month Para 225(b)
by care committee (iii) of IRWM
28. Inspection of colony by Once in 2 month Para 225(a)
Services Improvement of IRWM
Group (SIG)
29. Inspection and checking Minimum once a year Para 115 of
of stores and office of IRPWM
SSE
30. Small Track Machines Once in 6 month each Para 115(b)
PWI of IRPWM
31. Inspection of Canal and Joint inspection with Para 1103 of
Irrigation crossing state government IRBM
officers wherever
necessary
32 Inspection of washable Once in 6 month Railway Board
apron Lr.No.2010
CE-II/TK/11
dt.8.11.2010
8
S. Type of Schedule of Reference
N. Inspection Inspection
33 Joint Inspection for Annually
identifying trees which
are likely to endanger
Para 715 (c)
safety of track along
of IRWM
with Junior scale
officers of S&T and
Electrical Department.
34 Inspection of station As prescribe and Para 302 of
and Colony by nominated by GM IRWM
sanitation committee.

C. Inspection Schedule of SSE/SE /JE (P.Way)


(Over all in-charge/Sectional)
S. Type of Schedule of Reference
N. Inspection Inspection
1 Foot Inspection Over all in charge
– As much as possible
on pro-rata basis so as
to cover entire section
at least once a year
Not Over all in charge C.S. No. 132
– Once in a six month of IRPWM
in a systematic
manner (Every month
on pro rata basis so
as to cover entire
length of running
track)

9
S. Type of Schedule of Reference
N. Inspection Inspection
2 Inspection of Over all in-charge Para 124 of
Gangs / Trolley – Entire section by Push/ IRPWM (C.S.
Inspection Motor Trolley – Once in a No. 132)
month Para 139 of
Not Overall in charge IRPWM
- Entire section by Push (CS No.132)
trolley – Once in a
fortnight
3 Loco / Break van / Para 123 &
SSE/JE –
Rear window 139 (6) of C.S.
Once in a month 132, IRPWM
4 Night Foot plate Over all in charge – Night Para 124 & 139
Inspection Foot plate once in a of IRPWM
month between 00 to C.S. No. 132
4.00 hrs
5 Night Inspection Not over all in charge – Para 139 (8) of
Once in a month IRPWM CS
no.132
6 Monsoon Over all in-charge – One
Patrolling inspection every month by
train and inspection by
trolley – As per the schedule
laid down by the
administration Para 126 of
Not over all in charge – One IRPWM
inspection every fortnight by
train and inspection by
trolley - As per the schedule
laid down by the
administration
10
S. Type of Schedule of Reference
N. Inspection Inspection
7 Points & Crossings Passenger & running line
– Once in three month by
rotation with JE / P. way.
Other lines & yards lines –
Para 126 of
Once in a six month by
IRPWM
rotation with JE / P. way.

8 Level Crossing Once in a month by


rotation with JE / P. way

9 LWR Once in fort night during Para 8.1.5 of


two coldest and two LWR Manual
hottest month otherwise and Para 144
once in two month by of IRPWM
rotation with JE

10 Curves Once in six month by Para 124 &


rotation with JE 139 of IRPWM
(CS No. 132)
11 Bridge Over all in charge - Once Para 1101 of
in a year in prescribed IRBM
month before monsoon

12 Tunnel Once in a year after Para 1001 of


monsoon IRBM
13 Inspection of Side Over all in charge - Once
drains, Catch in a year in Prior to
monsoon Para 223 of
water drains and
IRPWM
Water ways of Not Over all in charge - (CS no. 132)
bridges & culvert Once in a year in the month
of April prior to monsoon
11
S. Type of Schedule of Reference
N. Inspection Inspection
14 Cutting SSE/JE - Once in a year Para 1011 of
immediately after IRBM
Monsoon (C.S.No.28)

15 Inspection of pre Over all in charge –


tamping, during Once at the time of taming.
tamping and post C.S. No.14 of
Not Over all in charge – IRTMM
tamping Once at the time of pre
operations during Para 5.3.3
tamping, during tamping
working of track and post tamping.
machines

16 Inspection of AT Over all in charge – As


Welding site much as possible but at Para 127 (3)
least once in a month and 139 (9) of
Not Over all in charge –At IRPWM
least two inspections in a (CS No. 132)
month
17 Private Sidings SSE/JE - Once in three Manual of
month Inspection
Schedule for
Engg. official
18 Inspection of Steel Over all in charge -Once in Para 273(b)(7)
Channel Sleepers a year by rotation with of IRPWM
ADEN (C.S. No. 128)

19 Accompany TRC/ SSE – Each run Para 139 (7)


OMS Run JE - Alternate run of IRPWM

12
S. Type of Schedule of Reference
N. Inspection Inspection
20 Inspection of Land Over all in charge - Para 813 of
boundary and Once a year IRWM
Encroachment

21 Small Track SSE in charge - Once in 3 Para 1.5 of


Machines month IRSTM (CS No.2)

22 Ongoing work of SSE/JE - As much as Para 127 (4)


construction and possible during foot plate and 139 (10)
other organization and trolley inspection of IRPWM
e.g. RVNL etc. (CS No.132)

23 Inspection of Once in 3 month on Railway Board


Washable Apron rotation basis by SSE/P. Lr.No.2010/CE-
Way (overall in charge) & II/TK/11
JE/P. Way (not in overall dt.8.11.2010
in charge)

24 Joint Inspection of Once in 3 month with


Section Engineer (S&T) if
Points & Crossings
not done by sectional J.E.
Interlocked points
on passenger run-
ning lines

25 Joint Inspection of Once in 6 month with


Points & Crossings Section Engineer (S&T) if
Interlocked points not done sectional J.E.
on other than
passenger running
lines.

13
S. Type of Schedule of Reference
N. Inspection Inspection
26 Inspection of Once in three month Para 814 (d) of
Encroachment IRWM

27 Inspection of Land Once a year Para 813(c) of


boundary IRWM
verification at
between stations
and unimportant
stations
28 Survey of Every year Para 720 of
Surviving trees IRWM

D. Inspection Schedules of SSE/Works

S. Type of Schedule of Reference


N. Inspection Inspection
1 Inspection of Steel
Structures
• Structure such • Once a year during the
as workshops, prescribed month.
running sheds, Para 228 (a)
platform covers of IRWM
and foot over
bridges
• Cast iron, • Once a year on a
wrought iron or Programmer basis.

14
S. Type of Schedule of Reference
N. Inspection Inspection
pressed steel
plate water
tanks and
staging’s
whether of steel
section or rails
• Structures with • Once a year during the
roof trusses prescribed month.
• Other structures in • Once a year during the
which timber, rail prescribed month
or steel work is
used to support Para 228 (a)
any part of the of IRWM
structure
• Tie rods of arched • Once a year during
roof excluding jack the prescribed month
• Wrought iron or • Once a year during
mild steel tanks the prescribed
or sleeper cribs at month
temporary
watering
kilometerage
2 Inspection of All the buildings, water
Buildings supply installations,
sewerage installations Para 224 (e)
and drainage of IRWM
arrangements once a
year.

15
S. Type of Schedule of Reference
N. Inspection Inspection
3 Inspection of all Frequently
water supply Para 552 (a)
installations & Pipe of IRWM
lines

4 Inspection of Land Once a year


boundary Para 813 (c)
verification at of IRWM
important stations
and staff colonies

5 Inspection of Once in three month Para 814 (d) of


Encroachment IRWM
6 Inspection of colony Once in 2 month Para 225 (b)
by care committee (iii) of IRWM
7 Inspection of colony As prescribed Para 225 (e)
by Services of IRWM
Improvement
Group (SIG)

8 Testing of yield of Once a year in Para 119 (c )


tube well and other coordination with of IRWM
source of water Electrical staff at the
time when the subsoil
water is at the lowest.

9 Petty repair/ Frequently 225 (a & b (i))


Complaint book of IRWM
10 Joint Inspection of Once a year 554 c (i) of
Pumping machinery IRWM
along with staff of
16
S. Type of Schedule of Reference
N. Inspection Inspection
Mechanical/
Electrical
Department

11 Survey of Surviving Every year Para 813 (c)


trees of IRWM
12 Storage-tanks for Frequently Para 552 (b) of
drinking water and IRWM
for flushing
purposes over
offices, bungalows
and quarters
13 Inspection of leaky Preferably be done Annexure 2.7,
roofs. during rainy season Para 5 of
IRWM

14 Inspection of Once a year prior to Para 117 and


bridges minor , monsoon 1101 of IRBM
major and
important including
ROB/RUB/FOB
(except track and
approaches)
(as per practice of
railways)

15 Detail inspection of Once in five years Para 1101 (a)


steel girder less - 20% per year. iv of IRBM
than 12.2 m clear
span ( as per
practice of railway)
17
S. Type of Schedule of Reference
N. Inspection Inspection
16 Inspection of tunnel Once a year during the Para 1001 of
(structural part prescribe month after IRBM
only) the monsoon season

E. Inspection Schedules of Bridge Organization


Inspection Schedules of Dy. CE (Bridge)
S. Type of Schedule of Reference
N. Inspection Inspection
1 Steel work of Called for his inspection Para 1106 (2a)
Bridges after scrutiny of register of IRBM
by DEN(Br) /AEN(Br)
2 Steel work of As directed by CBE Para 1106 (2b)
Bridges of IRBM

Inspection Schedules of Assistant (Bridge)


Engineer/Divisional Bridge Engineer
S. Type of Schedule of Reference
N. Inspection Inspection
1 Bridges All overstressed girders Para 105 (2) of
where camber loss is IRBM
noted and such bridges
which have been
referred to him by BRI

18
S. Type of Schedule of Reference
N. Inspection Inspection

2 Bridges Called for his inspection Para 105 (2) of


based on scrutiny of the IRBM
Bridge Inspector’s
registers.

3 Bridges 10% test check of the Para 105 (2) of


Bridges inspected by IRBM
Bridge Inspectors every
year.

4 Bridges All such steel structures Para 105 (2) of


as ordered by the Chief IRBM
Engineer at specified
intervals.

Inspection Schedules of Bridge Inspector


S. Type of Schedule of Reference
N. Inspection Inspection
1 All welded, RCC, Within one year of Para 107(1a)
PSC and composite Installation. of IRBM
girders and their
bearings.
2 Girders kept under Once a year or at intervals Para 107(1b)
observation specified by the CBE of IRBM
3 Floor system of Once a year Para 107(1c)
early steel girders of IRBM

19
S. Type of Schedule of Reference
N. Inspection Inspection
4 Superstructure Once in five years on Para 107 (1d)
including bearings planned basis. of IRBM
of all steel girders
of span 12.2m and
above, RCC,PSC and
composite girder
bridges.
5 Other nominated Once in five years. Para 107 (1e)
steel structures, of IRBM
being maintained
by Bridge Inspector

F. Inspection Schedules of Track Machine Organization


Inspection Schedules of Dy.CE and Senior Engineer
In-charge of Track Machines

S. Type of Schedule of Reference


N. Inspection Inspection
1 Inspection of Frequently especially Para 1.1 of
Machines where a group of IRTMM
machines such as
tamping, ballast cleaning
machines are deployed.

20
Inspection Schedules of Assistant Engineer
(Track machine)
S. Type of Schedule of Reference
N. Inspection Inspection
1 Inspection of
Machines
• CSM • Monthly
• Unimat • Monthly
• BCM • Fortnightly
• BRM • Once in two month
Para 5.3.2 (ii)
• SBCM • Monthly of IRTMM
• DTS • Once in two month
• UNO • Monthly
• DUO • Monthly
• T-28 • Monthly
• PQRS • Monthly
• TRT • Weekly

21
Inspection Schedules of SSE/Track Machine
S. Type of Schedule of Reference
N. Inspection Inspection
1 Inspection of
Machines
• CSM • Fortnightly
• Unimat • Fortnightly
• BCM • Weekly
• BRM • Monthly
Para 5.3.2(ii)
• SBCM • Fortnightly of IRTMM
• DTS • Monthly
• UNO • Fortnightly
• DUO • Fortnightly
• T-28 • Fortnightly
• PQRS • Fortnightly
• TRT • Daily

Every Officer should ensure inspections as per 'Inspection


Schedules'.

Quality of inspection is as important as an inspection.

  

22
CHAPTER - 2
LIST OF FUNCTIONARIES AUTHORISE TO ISSUE COMPETENCY
CERTIFICATE FOR VARIOUS TRACK ACTIVITIES.
S. Authorise level Functionaries Authority &
N. Nature of Activity /Work of authorise to issue Reference
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

1 Lifting/Lowering of track in LWR territory PWM Competency ANN VI Item


(Beyond that is done in normal certificate 1(C) ii LWR
maintenance of track) should be Manual 1996
issued by CTE duly up dated
in CS NO. 14

2 Deep Screening in LWR territory PWM Competency ANN VI Item


certificate 1(C) ii LWR
should be Manual 1996
issued by CTE duly up dated
in CS NO. 14

23
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

3 To carry out Maintenance work under PWM Competency Para 9.1.3(i),


their personal Supervision in LWR/CWR. certificate 9.2.2 and
Permitted only following work Issued by 9.2.3 of LWR
1. Maintenance operation - Lifting / Zonal or Manual1996
Lowering of track Divisional
2. Rails, sleepers and fastenings Training
(a) Casual renewal if sleepers and centre to
fastening over long stretches work on
(b) Renewal of defective rails LWR/CWR
3. Minor realignment of curves (valid for 3
4. Temporary repairs to rail fracture years) (Work
prescribed in
ANN VI only)

24
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

4 To carry out Maintenance work under Key man Zonal / LWR manual
their personal supervision in LWR/CWR. Divisional 1996 Para
Permitted only following works Training 9.2.2 and
1. (a) Ensuring that all creep anchors centre. Para 9.2.3
butt against sleepers during daily (Valid for 3 and ANN VI
rounds. years from the
(b) Renewal of fastenings not date of issue)
requiring lifting.
2. Emergency repairs to Rail fracture
3. Inspection and Checking of SEJ, oiling
and greasing and re-tightening /
renewal of fittings once a fortnight.
(Posting of Key men after getting
valid competency certificate by
Zonal/ Divisional training centre
which will be valid for three years
from the date of issue.)

25
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

5 a. Hot weather patrolling as per a .Hot Weather SSE/P. way Para 1008 of
IRPWM and LWR manual Patrolmen (Experienced IRPWM and
and trust ANN VI (para
b. Cold weather patrolling b.Cold Weather worthy men 5 & 6) of LWR
Patrolmen from the Manual 1996.
Permanent
c. Protection of track and secure safety c. Patrolman/ Gang to work
of trains in case of buckling, rail Trackman/ as patrolmen/
fractures, or any abnormal Gang Mate Watchmen.
behaviour of track Also be verified
for vision test &
shall not
employed as
Patrolmen
unless passed
requisite
medical test.)

26
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

6 Authorise level of supervision as per LWR PWI Subject to Chapter XV of


Manual (JE/SSE- various initial IRPWM and
(1) Mechanised Maintenance P. Way) /refresher/ ANN VI of
including Lifting, aligning, Promotional LWR Manual
packing etc course at ZRTI
in case of emergencies at
temperatures higher than those
permitted. Welding of rail joint at
site.
(2) Replenishment of ballast & checking
ballast section before onset of
summer.
(3) Major realignment of curves under
special instructions from AEN
(4) Organising hot weather patrolling
during summer months.

27
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

(5) Inspection in summer months and PWI Subject to Chapter XV of


checking on the working of hot (JE/SSE- various initial IRPWM and
weather patrols P. Way) /refresher/ ANN VI of
(6) All operations regarding distressing Promotional LWR Manual
(7) Permanent repairs to Rail fracture course at ZRTI
(8) Buckling
(a) Emergency repairs
(b) Permanent repairs
(9) Action in case of damage to track
following Derailments, breaches etc.
(10) Inspection & Checking of SEJ

7 Permitted to use trolley/Lorry /dolly Gang mate/ Min. JA grade As per


Section officer from IRPWM Para
Mates engineering 1103 & 1104
department. and G & SR
(Valid for one Chap XV SR
year) 15.18.3

28
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

8 Responsibility of keeping length of Gang mate Inspector of General Rule


line safe for passage of trains and P. Way or 15.14
signal supplied are to be kept in Works
proper order and ready for use.

9 Correct knowledge of hand signal Gang man Inspector of General Rule


and detonating signals and other P. Way or 15.12
tools or implements as may be Works
prescribed by special instructions.

10 Use of private trolley Permitted ONLY Non Rly Official Only by CE, G& SR Ch. XV
in siding (By name) (use of CSO & DRM Para SR Para
private trolley) 15.18.(13)
11 Certificate of competency to permit Motor Minimum JA G&SR Chapter
use of Motor trolley trolley driver Grade officer SR 15.18.3 and
of Eng. dept CE, IRPWM 1103
CTE, CBE, DRM and 1104

29
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

12 Competency certificate to Gateman Gateman Competency Para 912 of


certificate IRPWM SR
issued by PWI & 16.01.1
Countersigned
by ADEN or by
Divl Training
Centre (only
those passed A3
medical
examination)
13 Certificate of competency to permit Head trolley Minimum JA As per G&SR
usage of trolley/MT/Lorries. man Grade officer of Chapter XV
engineering SR
department. 15.18.1nd
(Permit shall be IRPWM
valid for one 1103 and
1104
30
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

year from the


date of issue
and Renewal
every year.)

14 Certificate of competency to permit PWI (SSE/ Minimum JA As per G&SR


usage of trolley/MT/Lorries. SE/JE) P.Way Grade officer, Chapter XV SR
DRM, CBE, 15.18.1 and
CTE. IRPWM 1103
(Permit shall and 1104
be valid for one
year from
the date of
issue and
Renewal every
year)

31
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

15 Supervision of work site of hand held JE/P.Way Nominated IRSTM para


off track tampers by ADEN 8.1.3.1 (iii)

16 Operation of On Track Machine Track Machine Issued by Dy.CE/ Para 1.4.1 &
Operator TM of the zonal 4.2.1 and 4.3
Railway of IRTMM
* (Valid for 3
years and shall
be kept in
Personal custody
of the operator)
17 SSE/SE/JE (P.Way) supervising Departmental Issued by Para 4.1.2.3
departmental AT welding. AT Welding & annex . I of
TPP/Lucknow Manual for
(after successful completion of training Supervisor or TWC/ Fusion
course) Vijayawada welding of
Rails by the
Alumino –
Thermic
Process
32
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

18 Welder for departmental AT welding Departmental Issued by Para 4.1.2.3 &


(Provisional Certificate) AT Welder TPP/Lucknow Annex I of
(After satisfactory completion of or TWC/ Manual for
TW1 course at TPP/Lucknow or TWC/ Vijayawada Fusion welding
Vijayawada with validity up to for of Rails by the
executing 100 joint or 6 months Alumino –
whichever is earlier) Thermic
Process

19 Regular Competency Certificate for Departmental Issued by Para 4.1.2.3 &


departmental welding. AT Welder TPP/Lucknow Annex I of
(after satisfactory completion of or TWC/ Manual for
TW2 course with validity up to 2 Vijayawada Fusion welding
years and after two year of Rails by the
reassessment valid for 5 year.) Alumino –
Thermic
Process

33
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

20 Provisional Competency certificate Contractor DG(M&C), As per IRST-


for welding supervisor and welder of AT welding RDSO 19/2012 Para
firm. supervisor/ (valid for 2 16.2 and 16.6
(Issued separately for welding of 52kg/ Welder years)
60kg with standard gap, with wide gap,
or welding of HH/110 UTS rails.)

21 Regular Competency certificate for Contractor DG (M&C), As per IRST-


welding supervisor and welder of firm. AT welding RDSO 19/2012 Para
(After 2 years from issue of Provisional supervisor/ 16.2 and 16.6
Competency certificate for welding Welder
supervisor and welder of firm shall be
reassessed by RDSO and DG(M&C)
RDSO extended validity for 5 years
(This certificate issued separately for
welding of 52kg/60kg with standard gap
, with wide gap , or welding of HH/110
UTS rails.)
34
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

22 Supervision of FB welding Departmental Zonal Railway Para 13.1 and


(Min diploma in mech/elect engg or FB welding CTE / CE(con) 13.2 of
BSc duly passing test as per manual supervisor (without Manual for
provision) examination if Flash butt
quality of welding of
weld is ok) rails revised
January 2012.

23 Welder for FB welding Departmental Zonal Railway Para 13.1 and


(Min class X or equivalent duly FB welders CTE / CE(con) 13.2 of
passing test as per manual (without Manual for
provision) examination if Flash butt
quality of welding of
weld is ok) rails revised
January 2012.

35
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

24 USFD operator of departmental USFD Department DG (M&C), Para 3 manual


machines (Initial certification) USFD RDSO for Ultrasonic
(Duly trained by RDSO in the technique of Operator Rail Testing of
USFD testing. Initially valid for 3 years) rails & welds.
25 USFD operator of departmental USFD Department DG (M&C), Para 3 manual
machines (extended validity after initial USFD RDSO for Ultrasonic
certification). Operator Rail Testing of
(Extended validity for 5 years after rails & welds.
satisfactory completion of refresher
course.)
26 USFD operator of contracted USFD USFD DG (M&C), Para 3.1 and
machines (Provisional certificate) Testing by RDSO 3.3 of
(issued in three categories which Rail contractor Procedure
Testing, Weld Testing and Rail and Weld operator order issued
testing both. Provisional certificate issued by RDSO
by RDSO valid for 6 months.) conveyed by

36
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

RailwayBoard
L.No.Track/21/
2004/0902/7
Vol –II Dt.24/
10/2014

27 USFD operator of contracted USFD USFD DG(M&C), Para 3.1 and


machines (Regular Certificate) Testing by RDSO 3.3 of
(Issued in three categories which Rail contractor Procedure
Testing, Weld Testing and Rail and Weld operator order issued
testing both. by RDSO
Regular competency certificate after conveyed by
verifying experience of operator in USFD Board
testing 100 no’s weld joints or 100 km L.No.Track/
track (200 Km rails) RDSO issue 21/2004/
competency having validity of 3 years.) 0902/7 Vol –II
Dt.24/10/
2014
37
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

28 Quality Control of Contract USFD Quality DG (M&C), Para 3.1 and


(Contractor supervisor having minimum control USFD RDSO 3.3 of
academic qualification of BSc or supervisor Procedure
equivalent with physics as one of the by order issued
subject or Diploma/Degree in contractor by RDSO
Engineering from any National/ conveyed by
International University. He shall Board
possess requisite qualification in NDT- L.No.Track/21
Testing as per Para 7 of specification.) / 2004 / 0902
/ 7 Vol –
II Dt.24 / 10 /
2014
29 Period of hot weather patrolling Period of Chief Para 9.1.2 (i)
(PWI/PWM shall be vigilant & shall also Hot weather engineer & ANN X A
introduced patrolling when temperature Patrolling LWR Manual
rises above td + 200C or as per ANN X A
of LWR Manual)
38
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

30 Cold Weather Patrolling (Period and Period of Chief Para 9.1.2 (ii)
section) CWP engineer & ANN X B
LWR Manual

Track Divl Training Small track


31 Operation & routine maitenance of
small track machine maintenar Centre/ machine
Divisional small manual Para
track machine 1.3.2 duly
maintenance updated in
centre CS no.4

32 Skilled qualified welders, fitters Welder, M&C Para 20 of


approved individually by M&C fitter for directorate Indian
director, RDSO, Bridge work RDSO Railways
(Approval & testing of welder shall be shop standard code
trained in accordance with IS 817 of practise for
subject to qualifying test specified in IS metal arc
7310 (part -1)
39
S. Authorise level Functionaries Authority &
Nature of Activity /Work of authorise to issue Reference
N.
Supervision/ competency / from Manual/
Designation permission for Circular/
work. G&SR

welding in
Structural steel
bridge code.

33 Initial course at Centralised training Training for Centralised Para 1303


school of zonal railways along with Bridge Khalasi training and 1304 of
practical training in field /Artisans / institute of Bridge
Bridge Mistry/ zonal railways Manual 1998
Bridge
Inspectors

  

40
CHAPTER - 3
ENGINEERING DEPARTMENT REGISTERS
(PHYSICAL/TMS)

1. Points & Crossing Register-


Physical: This register is maintained by Senior Section Engineer / Section
Engineer (Permanent Way) [SSE/SE (P.Way)] of the section and it is kept in
his office. Detailed inspections of points & crossings and compliance are
recorded in this register.
TMS: Same register can be accessed through TMS.

Physical Register

S. Item Check Reference


N.

1 Whether chart for inspection is Yes/No Para 236(5) of


prepared in register? IRPWM

2 Whether compliance of each point Yes/No -


is recorded?

3 Whether yard diagram showing Yes/No -


Point No. and details prepared?

4 Whether proper entry has been Yes/No Ann 2/6 & 2/6
done in each column of point and (A) of IRPWM
crossing register?

41
TMS
1 Check Inspection Planning Report. Go to Report >
Inspection > 3. Inspection Planning. Choose PWI and
year, press GO. The asset number color indicates the
position of inspection.
Inspection planned Inspection planned
and done in in the month but
same month. inspection done in Yes/No
later month.

Inspection planned Inspection planned


in the month and and not done so
month is not over. far
Note down the points and crossings to
be inspected during sample month.
2 Check whether planned inspections done by the
official or not. Go to Report > Inspection > 4. Inspection
Register > select ‘feature type’, ‘from date’, ‘to date’
and click on ‘Click here to see Inspections of individual Yes/No
assets’ from the list choose same P&C no. and check
details of inspection done during the month or not.

3 Whether compliance of inspection note against Yes/No


each point is recorded?

2. Curve Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept
in his office. Versines, Super Elevation and Gauge in the curve are recorded
in the register along with compliance chart of inspections carried out by
Junior Engineer/Senior Section Engineer (Permanent Way) [JE/SSE (P.Way)]
and Assistant Divisional Engineer/Divisional Engineer (ADEN/DEN).
42
Physical Register
S. Item Check Reference
N.

1 Whether summary of inspections is Yes/No Annexure 4 / 5


mentioned in the register? of IRPWM

2 Whether inspection is being done Yes/No Para 420(2)


in each quarter? of IRPWM

3 Whether proper entry has Yes/No


been done in each column? Annexure 4 / 5
of IRPWM
4 Whether compliance of each Yes/No
point is recorded?

TMS
1 Check Inspection Planning Report. Go to Report >
Inspection > 3. Inspection Planning. Choose PWI and
year, press GO. The asset number color indicates the
position of inspection.
Inspection planned Inspection planned
and done in in the month but
same month. inspection done in Yes/No
later month.

Inspection planned Inspection planned


in the month and and not done so
month is not over. far
Note down the points and crossings to be
inspected during sample month.

43
2 Check whether planned inspections done by the
official or not. Go to Report > Inspection > 4. Inspection
Register > select ‘feature type’, ‘from date’, ‘to date’
Yes/No
and click on ‘Click here to see Inspections of individual
assets’ from the list choose same P&C no. and check
details of inspection done during the month or not.

3 Whether compliance of inspection note against each Yes/No


point is recorded?

3. Long Welded Rail (LWR) - Continuous Welded Rail (CWR)


Register
This register is maintained by SSE/SE (P.Way) of the section and it is
kept in his office. Details of inspections are recorded in the register.
It includes a detailed drawing of Switch Expansion Joint (SEJ) assembly,
Line diagram of LWR mentioning position of SEJs and other special
features viz. Level Crossings, Glued joints, Bridges, Curves, Gradients
etc. of each LWR/CWR
Physical Register

S. Item Check Reference


N.
1 Whether summary of inspections is Yes/No Para 8.2 and
mentioned in the register? Annexure-XI,
XII, XIII A,
and XIII B of
LWR manual
2 Whether inspections are up to Yes/No -
date?

3 Whether line diagram of LWR Yes/No -


is prepared?
44
S. Item Check Reference
N.
4 Whether action taken / compliance Yes/No Annexure- XIII
is recorded with date? A and XIII B of
LWR manual
TMS
1 Check Inspection Planning Report. Go to Report >
Inspection > 3. Inspection Planning. Choose PWI and
year, press GO. The asset number color indicates the
position of inspection.
Inspection planned Inspection planned
and done in in the month but
Yes/No
same month. inspection done in
later month.

Inspection planned Inspection planned


in the month and and not done so
month is not over. far
Note down the points and crossings to be
inspected during sample month.
2 Check whether planned inspections done by the
official or not. Go to Report > Inspection > 4. Inspection
Register > select ‘feature type’, ‘from date’, ‘to date’ Yes/No
and click on ‘Click here to see Inspections of individual
assets’ from the list choose same LWR no. and check
details of inspection done during the month or not.

3 Whether compliance of inspection note against


Yes/No
each point is recorded?

45
4. Level Crossing Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. It contains permanent features of a level crossing.

Physical Register

S. Item Check Reference


N.

1 Whether register is up dated? Yes/No Para 915 with


Ann 9/4 of
IRPWM

2 Whether length of check rail Yes/No Item 3 of Ann


is mentioned? 9/4 Para 904 of
IRPWM

3 Whether details of track Yes/No Item 16 of Ann


structure mentioned? 9/4 of IRPWM

4 Whether a detail of Train Vehicle Yes/No Para 919 &


Units (TVU) along with date is Item 15 of Ann
mentioned? 9/4 of IRPWM
TMS
1 Check Inspection Planning Report. Go to Report >
Inspection > 3. Inspection Planning. Choose PWI and
year, press GO. The asset number color indicates the
position of inspection.
Yes/No
Inspection planned Inspection planned
and done in in the month but
same month. inspection done in
later month.

46
Inspection planned Inspection planned
in the month and and not done so
month is not over. far
Note down the points and crossings to be
inspected during sample month.
2 Check whether planned inspections done by the
official or not. Go to Report > Inspection > 4. Inspection
Register > select ‘feature type’, ‘from date’, ‘to date’ Yes/No
and click on ‘Click here to see Inspections of individual
assets’ from the list choose same LC no. and check
details of inspection done during the month or not.

3 Whether compliance of inspection note against


Yes/No
each point is recorded?

5. Track Recording Car Register


This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. It contains results of Track Recording Car (TRC) / Track Recording
Cum Research Car (TRRC) running in the section. One page is given for
each kilometer of track.
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No Para 122, 210 of
IRPWM
2 Whether one page is allotted Yes/No Para 122, 210 of
to each kilometer IRPWM
3 Whether register is checked Yes/No Para 122, 210 of
by Engineering Officers? IRPWM

47
TMS
1 Whether latest TRC report is uploaded on TMS. Go to Yes/No
‘Reports(M-Z)>TRC>TRC Report> select all Parameters
and check the date of latest run from drop down
menu
2 Check on locations needing attention based on TRC Yes/No
from ‘Reports (A-L)>Locations Needing Attention>
select indirect>TRC

6. Section Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. It contains all important information including a brief history of
the section. A few pages for major unusual occurrences are also included.
Physical Register

S. Item Check Reference


N.

1 Whether register is up dated? Yes/No Para 210 of


IRPWM

2 Whether brief history of the Yes/No Para 210 of


section is mentioned? IRPWM

3 Whether all unusual Yes/No Para 210 of


occurrences are recorded IRPWM
with date?

4 Whether register is checked Yes/No Para 210 of


by Engineering Officers? IRPWM

48
TMS
1 Check for latest entry by going to ‘Reports(M-Z)>Misc Yes/No
Registers

7. Encroachment Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. In the register, one page is allotted to each encroachment, so
that about 15 years record is available at a glance regarding efforts made
in the removal of the encroachments.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No
Para 814 (e)
Ann 8/2 of
2 Whether a separate page is allotted Yes/No
IRPWM
for each encroachment?

3 Whether action taken / follow up Yes/No


action is recorded?
Para 814(e)
4 Whether any encroachment once Yes/No
mentioned is deleted?

TMS
1 Check on entries on encroachment from ‘Reports Yes/No
(A-L) > Land Management

49
8. Land Boundary Verification Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. One page is allotted to record availability and location of boundary
stones in each kilometer. About 10 years record is available at a glance
about attentiveness exercised in maintenance and fixation of the land
boundary stones.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No

2 Whether a separate page is allotted Yes/No ANNEXURE


for each encroachment? 8.1(a)

3 Whether land boundary diagram is Yes/No (Para 813


prepared? (d) of IRWM

4 Whether missing boundary stones Yes/No


recorded?

5 Whether missing stones are Yes/No


replaced?

TMS
1 Check on land offset file in excel and verify sample Yes/No
boundary pillars at site from ‘Reports(A-L)>Land
Management>Land Offset File (Excel file)
2 Whether land boundary diagram is prepared? Yes/No
3 Whether missing boundary stones recorded? Yes/No
4 Whether missing stones are replaced? Yes/No
50
9. Creep Register
This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. A separate page is allotted for each kilometer of track to record
creep in fish plated/SWR Track.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No

2 Whether a separate page is allotted Yes/No Ann 2/7


for each kilometer? Para 242
of IRPWM
3 Whether proper entries are made Yes/No
in each column?

4 Whether excessive creep is Yes/No


adjusted and recorded with date?

TMS
1 Check from ‘Inspection Register’> choose LWR Yes/No
on type of asset
2 Whether excessive creep is adjusted and Yes/No
recorded with date?

10. Gap Survey Register


This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. Record of Gap survey done in Short Welded Rail (SWR) track is
maintained in the register.

51
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No Ann 5/2 Para
510 of IRPWM
2 Whether gap survey is done in the Yes/No Ann 5/2 Para
month of February regularly? 510 of IRPWM

3 Whether gaps requiring gap Yes/No Ann 5/2 Para


adjustments are adjusted? 510 of IRPWM
4 Whether gap survey is done in Yes/No Ann 5/2 Para
rising trend of temperature? 510 of IRPWM

TMS
1 Check from ‘Reports(M-Z)> Misc Register> Gap Survey Yes/No
2 Whether gap survey is done in the month of February Yes/No
regularly?
3 Whether gaps requiring gap adjustments are Yes/No
adjusted?
4 Whether gap survey is done in rising trend of Yes/No
temperature?

11. Sand Hump Register


Maintained by SSE/SE (P.Way) of the section and kept in his office, details
of various Parameters of sand humps are recorded in this register.

52
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No -
2 Whether adequate loose sand is Yes/No -
available in sand hump?
3 Whether depth of sand above Yes/No -
rail level is mentioned?
4 Whether any deficiency noted Yes/No -
is complied?

TMS

1 Check from ‘Inspection Register’> Select Yes/No


feature type – Sand Hump
2 Whether adequate loose sand is available Yes/No
in sand hump?
3 Whether depth of sand above rail Yes/No
level is mentioned?
4 Whether any deficiency noted is complied? Yes/No

12. Casual Renewal Register


This register is maintained by SSE/SE (P.Way) of the section and it is kept in
his office. Record of piece-meal renewals is maintained allotting a separate
page for each kilometer of track.

53
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No
Para 205, 209,
2 Whether reason for replacement Yes/No 210(xi) of
is mentioned? IRPWM
3 Whether complete detail of Yes/No
whole section is recorded?

TMS
1 Check from ‘Report(A-L)’>Asset Register Yes/No
2 Check from wire book whether all blocks taken
for rail renewal has been entered in TMS? Yes/No

13. Corroded Rail Register: This register is maintained by SSE/SE


(P.Way) of the section and it is kept in his office. One page is allotted
for each kilometer of track or each running line in yard to check extent
of corrosion in rail flange and web.
Physical Register
S. Item Check Reference
N.
1 Whether register is up dated? Yes/No

2 Whether a separate page is Yes/No


Ann 2/20,
allotted for each kilometer?
Para 250(2)
3 Whether corroded rails are being Yes/No of IRPWM
replaced regularly?
4 Whether action taken is recorded Yes/No
and checked by officers?
54
TMS --- This register is not available in TMS
14. Permanent Way Diagram
Record is kept in the office of SSE/SE (P.Way). A bar chart containing
complete details of the section of SSE In-charge is prepared by the
division/Sub division and a copy of the same is made available to each
SSE/P.Way, who keeps it duly updated.
Physical Register

S. Item Check Reference


N.
1 Whether Permanent Way Yes/No Ann 2/4, Para
diagram is up dated? 211 of IRPWM
TMS
1 Check from ‘Report(M-Z) Track Diagram Yes/No

15. Welding Register


This register is maintained by SSE/SE (P.Way) of the section and it is
kept in his office. All Alumino Thermit Welding (ATW) done in the section
is recorded in this register.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No
Ann 5 of
2 Whether proper entries have Yes/No
AT welding
been done in each column?
manual
3 Whether register is scrutinized Yes/No
by ADEN regularly?
55
TMS
1 Check from ‘Report(A-L)’>Asset Register>AT Weld Yes/No

16. Ultrasonic Flaw Detection (USFD) Testing Register:


This register is maintained by SSE/SE (P.Way) of the section and it is
kept in his office. Results of USFD testing and action taken there upon
is recorded in this register.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No Para 5.1.3 and
Ann V,VI,VII &
VIII of USFD
Manual
2 Whether USFD testing in the Yes/No Para 6.6.1.1
section is being done regularly of USFD Manual
as per frequency ?
3 Whether this register is Yes/No -
scrutinized by higher officers?
4 Whether action taken is Yes/No -
recorded with date?

TMS
1 Check from ‘Report(M-Z)>USFD>USFD due/Overdue Yes/No
2 Check monthly progress Yes/No
3 Check defect list Yes/No

56
17. Rail / Weld Fracture Register:
This register is maintained by SSE/SE (P.Way) of the section and it is
kept in his office. It contains records of Rail/Weld Fractures in his
section. A statement showing details of Rail/Weld fracture occurred
during the current and preceding years are also attached to have a
clear assessment of fracture prone areas and to have special watch
over those kilometers

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No Ann V,VI & VII of
USFD manual
2 Whether date of last USFD Yes/No and Para
testing against each case is 210(X) of
recorded? IRPWM
3 Whether month-wise statement Yes/No
showing detail of rail/weld
fractures is recorded?
4 Whether USFD classification Yes/No
is recorded?

TMS
1 Check from ‘Report(A-L)>Fracture>Fracture Yes/No
Analysis
2 Check whether all fracture reports have remarks Yes/No
of USFD PWI
3 Check whether all reports have photos Yes/No

57
18. Glued Joints Register
Register is maintained by the sectional JE/P. Way and it is kept in the
office of SSE/SE (P.Way), in which details of glued insulated joints and
annual record of its maintenance and performance is kept. A separate
page is used for each Glued Joint.

Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No -
2 Whether a separate page is Yes/No -
allotted for each glued joint?
3 Whether annual record of Yes/No -
performance is mentioned?
4 Whether track structure Yes/No -
mentioned along with ballast
cushion?

TMS
1 Check from ‘Report(A-L)’>Asset Register> select Yes/No
feature type – Glued Joint

19. Tie Tamping Machine (TTM) Register:


This register is maintained by SSE/SE (P.Way) of the section and it
is kept in his office. Tamping record along with record of track
Parameters i.e. cross level and alignment before and after tamping is
maintained in the register.

58
Physical Register
S. Item Check Reference
N.
1 Whether register is up dated? Yes/No -
2 Whether track Parameters are Yes/No Para 3.1.2 (i)
recorded before tamping of IRTMM
3 Whether track Parameters are Yes/No Para 3.1.4 (iv)
recorded after tamping? of IRTMM
4 Whether quality of work is Yes/No -
assessed and mentioned?

TMS
1 Check from ‘Report(M-Z)>Track Machine Yes/No

20. PCDO Register: PCDO register is maintained as per the latest


instructions of division/Hd.Qr. from time to time.
Physical Register
S. Item Check Reference
N.
1 Whether register is up dated? Yes/No -
2 Whether assistance required is Yes/No -
highlighted?
3 Whether vacancy position is Yes/No -
highlighted?

TMS - This register is available from Sr.DEN (Cordination)


and above logins.

59
21. Inspection Notes of Higher Officials :
This register is maintained by SSE/SE (P.Way) of the section and it
is kept in his office. Inspection notes of higher officials and their
compliance is recorded in this register.
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No -
2 Whether action taken is Yes/No -
recorded against each item?
3 Whether timely action is taken? Yes/No -
4 Whether items pertaining to Yes/No -
higher officials brought to their
notice?

TMS
1 Check from ‘Miscellaneous’>Inspection Notes Yes/No
2 Whether action taken is recorded against each
item? Yes/No
3 Whether timely action is taken? Yes/No
4 Whether items pertaining to higher officials Yes/No
brought to their notice?

22. Rainfall Register:


Maintained by SSE/SE (P.Way) of the section, kept in his office,
extent of rainfall is recorded in this register.

60
Physical Register

S. Item Check Reference


N.
1 Whether register is up dated? Yes/No Para 210(c-i)
of IRPWM
2 Whether time and date of rain Yes/No -
fall is properly mentioned?
TMS
1 Check from ‘Report (M-Z)>Miscellaneous Yes/No
Register>5. Rainfall Register
2 Whether date wise rainfall for all measuring Yes/No
stations is entered for previous month?
23. Points & Crossing Joint Inspection Register of SSE/P.Way and SSE/
Signal and Telecommunication (S&T):
This register is maintained jointly by SSE/SE (P.Way) and SSE/SE(S&T) of
the section and it is kept in SS office/Power Cabin. A proper record of joint
inspections carried out along with compliances is maintained in this register.
Physical Register
S. Item Check Reference
N.
1 Whether summary of inspection Yes/No -
is recorded in register?
2 Whether compliance of each Yes/No -
shortcoming noticed is recorded?
3 Whether inspection is being Yes/No -
done in each quarter?
4 Whether proper entry has been Yes/No -
done in each column?
61
TMS
1 Check from Report (A-L) > Inspection > 4.
Inspection Register > Choose Point & Crossing Yes/No
(Joint) in drop down menu for type of register. Fill
all the relevant information.
2 Whether inspection is being done in each Yes/No
quarter?
3 Whether proper entry has been done in each
Yes/No
column?
4 Whether compliance of each shortcoming
Yes/No
noticed is recorded?

24. Material Under Trial Register:


This register is maintained by SSE/SE (P.Way) of the section and it
is kept in his office. Complete and proper record of material which is
under trial (if any) in the section is maintained in this register.

Physical Register

S. Item Check Reference


N.
1 Whether any material is under Yes/No Para 212(iii)
trial in the section? of IRPWM
2 Whether proper entries are Yes/No
made in corresponding columns?
3 Whether register is brought Yes/No
up-to-date?

62
TMS
1 Check from ‘Register (M-Z)>Material Under Trial Yes/No
2 Whether any material is under trial in the Yes/No
section?
3 Whether proper entries are made in Yes/No
corresponding columns?
4 Whether register is brought up-to-date? Yes/No

25. Annual Temperature Record Register:


This register is maintained by SSE/SE (P. Way) of the section and it
is kept in his office.

Physical Register
S. Item Check Reference
N.
1 Whether register is up dated? Yes/No Para 505 (iii)
of IRPWM
2 Whether proper entries are Yes/No
made in corresponding columns?

TMS
1 Check from ‘Register (M-Z)>Miscellaneous Yes/No
Register> 7. Temperature Register
2 Whether register is up dated? Yes/No
3 Whether proper entries are made in Yes/No
corresponding columns?

63
26. Assurance Register

Physical Register
S. Item Check Reference
N.
1 Whether assurance of having Yes/No Para 826 of
read all rules & guidelines has IRPWM
been recorded?

TMS
1 Check from ‘Register (M-Z)>Miscellaneous Yes/No
Register> 10. Circular Viewed

  

64
CHAPTER - 4
CIVIL ENGINEERING INSPECTIONS

A PERMANENT WAY (TRACK)


1. Inspection of Track

S. Item to be inspected Remarks Reference


N.
1. Whether condition of Rail is good?
a) Vertical wear of rail is within
13/8 mm (60/52 kg)
b) Lateral wear of rail is within
i) 6/8 mm (A&B / C,D,E routes on Yes/No
straight track)
ii) 8/10 mm (A&B / C,D,E routes
on curved track)
2. Whether condition of Sleepers Yes/No IRPWM
specially under rail seat is good Para 302
and their spacing is correct? (60/65 (iii) & (iv)
cm c/c for 1660/1540 sleeper
density)
3. Whether all track fittings are Yes/No
complete and tightened?
4. Whether ballast available is Yes/No IRLWRM
sufficient and properly boxed? para 4.2

65
S. Item to be inspected Remarks Reference
N.
5. Whether oiling and greasing of Yes/No IRPWM
fishplate joints is being done as per Para 241(3)
annual schedule? (once in 12 month)
6. Whether there is any blowing/ Yes/No
pumping joint?
7. Whether knowledge of staff regarding Yes/No
safety of track is up to the mark?
8. Whether proper protection is resorted Yes/No IRPWM Para
to at track work site as per prescribed 806,807,808
norms?
9. Whether P.Way material is properly Yes/No
stacked and is away from running
track and marked wherever required?
10. Is the Machine tamping overdue Yes/No
(in Mechanised maintained track)?
11. Whether “Location needing Yes/No
Inspection” are being regulated by
field official?
12. Whether all field officials are entering Yes/No
their irregularities in Track
Management System (TMS)?
13. Whether resources/work planning Yes/No
has been done with respect to
“Location needing attention” as per
TMS?

66
2. Gang Inspection

S. Item to be inspected Remarks Reference


N.
1. Whether gang is working under proper Yes/No IRPWM Para
track protection? 806, 807,
808

2. Whether all the Trackmen are in Yes/No


uniform?
3. Whether Gang charts, Mates diary, Yes/No IRPWM Para
attendance sheet are available with 232(1)
gang?
4. Whether all equipments i.e. Gang
tools, first aid box, Safety equipments
are available and in working
condition? (In good condition /Not in
good condition)
IRPWM
4.1 Powrah (Spade) Yes/No Para
232(2)(c)
4.2 Crowbar Yes/No
4.3 Pan mortar Yes/No
4.4 Pick Beater Yes/No
4.5 Pick Axe Yes/No
4.6 Shovel Yes/No
4.7 Ballast Rake Yes/No

67
S. Item to be inspected Remarks Reference
N.
4.8 Bar Straightening Yes/No
4.9 Bar Claw Yes/No
4.10 Tommy Bar Yes/No
4.11 Wire Claw Yes/No
4.12 Punches Yes/No IRPWM
Para
4.13 Wire Basket Yes/No 232(2)(c)
4.14 Spanners Yes/No
4.15 Hammer Yes/No
4.16 Rail drilling Ratchet Yes/No
4.17 Track Bond Drill/ Drill Twist Yes/No
4.18 Chisel Yes/No
4.19 Rail hole chamfering kit Yes/No
4.20 Tools for Lubrication of ERCs Yes/No
4.21 ERC Extractor / Applicator Yes/No
4.22 Rail Tongues Yes/No
4.23 Rail Shunt-Cable (Jumper) Yes/No
4.24 Cutting Blowpipe Yes/No
4.25 De-stressing Roller Yes/No
4.26 Rail Roller Yes/No

68
S. Item to be inspected Remarks Reference
N.

4.27 Rammer Yes/No


4.28 Ballast Profile Template Yes/No
4.29 Hump Cord Yes/No
IRPWM
4.30 Wooden Mallet Yes/No
Para
4.31 Hand Signal Flag Yes/No 232(2)(c)

4.32 Staff suitable for exhibition of red


lamp or red flag Yes/No
4.33 Detonators Yes/No
4.34 Whistle thunderer Yes/No
4.35 Battery operated LED based Torch
Light-cum Hand-Signal Lamp Yes/No
4.36 Safety Helmet Yes/No
4.37 Safety Jacket Yes/No
4.38 Safety Gloves Yes/No
4.39 Shoes Yes/No
4.40 First aid box Yes/No
4.41 Safety goggle Yes/No
5. Whether previous day work is as Yes/No IRPWM
per data entered in Gang chart/ Para 232(1)
diary? Is it as per expected quality?

69
S. Item to be inspected Remarks Reference
N.
6. Knowledge of Mate and Gang Yes/No IRPWM
regarding safety and quantity of Para 232 (3)
work is adequate?
7. Whether PME of Mate, Keyman and Yes/No IRMM Vol I
Trackman is being done regularly as Para 514(B)
per norms? (On attaining the age
of 45 years and thereafter at the
termination of every period of
five years)
8. Whether compliance of various Yes/No
points noted during last inspection
have been made?
9. Whether Gang Progress/work is Yes/No
being entered in TMS?

3. Checklists for Curve

S. Item to be inspected Remarks Reference


N.
1. Whether curve board is properly Yes/No IRPWM
provided at both ends of curve with Para 409(1)
adequate details of Degree, Radius,
Super Elevation (SE) etc.?
2. Whether marking of cant & stations Yes/No IRPWM
no. and versines is indicated on rail Para
and is legible? (10 m apart on inside 409(3)
of web of inner/outer rail)
70
S. Item to be inspected Remarks Reference
N.
3. Shoulder width on outer rail on LWR Yes/No LWR Manual
track. Para 4.2
(350/500 mm shoulder ballast on
straight and inside of curve/ outside
of curve)
4. Whether rail posts are available at Yes/No IRPWM Para
Transition Tangent Point (TTP) and 409(2)
Common Tangent Point (CTP)?
5. Whether extra clearance for curves
have been provided?
1.On platforms - IRPWM
Yes/No
Inner side of curve – 27330/R + 5L/4 – Para 417 &
51 mm Appendix of
Outside of curve – 29600/R – 25 mm SOD
2. Adjacent Track–27330/R+29600
R+2L/4 mm Where R is radius of curve Yes/No
in meter and L is Lean
6. Whether compliance of various Yes/No IRPWM
points noted during last inspection Para 122(l)
have been made?
7. Whether the inspection of curve has Yes/No
been done as per schedule by ADEN
SSE(P.Way)/JE(P.Way)? IRPWM
(one curve every quarter in each SSE/ Para 107(4),
JE (P.Way) 124 (4)
jurisdiction for ADEN/ once in 6
months by rotation for SSE/JE(P.Way) )

71
S. Item to be inspected Remarks Reference
N.

8. Whether Curve Inspections are Yes/No


being entered by SSE/P.Way in TMS
9. Does the curve require local Yes/No
complete realignment? (20% or
more stations are having versines
variations beyond limits as per
speed band)
IRPWM
<140 - ≥ 110 kmph :- 10 mm (15mm
Para 421(2)
for 110kmph) or 20% of average
versines whichever is more ;
<110 - ≥ 50 kmph :- 20 mm or 20% of
avg. versines whichever is more ;
< 50 kmph :- 40 mm or 20% of avg.
versines whichever is more;
10. Permissible Gauge on curve - Yes/No IRPWM
radius ≥ 440 m :- -6 to +15 mm Para
radius < 440 m :- upto +20 mm 224(2)(e)(v)

4. Points & Crossings

S. Item to be inspected Remarks Reference


N.
1. Whether entries are recorded in Yes/No
Points & Crossing's register by SSE/JE
IRPWM Para
as per their inspection schedule?
124(3)
(once in 3 months on running lines
and once in 6 months on non-running
lines by rotation)

72
S. Item to be inspected Remarks Reference
N.
2. Whether condition of stock rail and Yes/No
tongue rail of switch is damaged or
worn out?
a. Tongue rail is chipped/crack within Yes/No
200 mm length in 1000 mm from ATS
b. Vertical wear of Tongue rail is Yes/No
within 8/5 mm at 13 mm head width
and level point (60/52 kg) IRPWM
c. Lateral wear of tongue rail at Q Yes/No Para 237(2)
point and Level point is within 8/6 & 302
mm(60/52 kg)
d. Vertical wear of Stock rail is within Yes/No
13/8 mm (60/52 kg)
e. Lateral wear of Stock rail is within Yes/No
i. 6/8 mm (A&B / C,D,E routes on
straight track)
ii. 8/10 mm (A&B / C,D,E routes on
curved track)
3. Whether tongue rails are out of Yes/No
square?
4. Whether tongue rail houses properly Yes/No
against stock rail?
5. Whether throw of switch is within Yes/No SOD Ch.2
tolerance limit? (Straight switch- Item 16
95mm, Curved switch-115mm, Thick
web switch-160mm)

73
S. Item to be inspected Remarks Reference
N.
6. Whether correct gauge and cross Yes/No IRPWM Para
level is maintained at toe of switch 237(1)(g)
in both the settings i.e., Normal and
Reverse? (nominal gauge + 6 mm for
T/out having SEA> 0020’00” & nominal
gauge for T/out having SEA ≤
0 020’00”)
7. Whether all tongue rail fittings are Yes/No
intact and effective?
8. Whether correct gauge and cross Yes/No IRPWM Para
level is maintained in lead portion? 237(8)

9. Wear at Actual Nose of Crossing Yes/No IRPWM Para


(ANC) is within the Permissible 237(3)
limits? (Rajdhani/Shatabdi route-
Built Up Xing: 6mm, CMS Xing:8mm;
Other routes all xings:- 10mm).
10. Whether proper clearance between Yes/No SOD Ch.2
vee and wing rail at nose of crossing Item 14 &
is maintained properly? (44-48 mm 15
in B/Up xings)
11. Whether correct clearance of check Yes/No SOD Ch.2
rail opposite the crossing is Item 12 &
maintained? ( 41-45 mm for Fan 13
shaped T/out; 44-48 mm for other T/
outs)
12. Whether correct gauge and cross Yes/No IRPWM Para
level is maintained at nose of 237(8)
crossing?
74
S. Item to be inspected Remarks Reference
N.
13. Whether proper packing is given in Yes/No IRPWM Para
switch and crossing portion? 237(1)
14. Whether length of turnout is standard Yes/No RDSO Drg.
or not? (28613 mm for 1 in 8.5 & No.-4865,
39975 mm for 1 in 12 Fan shaped T/ 4218&
out) 4732
15. Whether compliance of various Yes/No
points noted during last inspection
have been made?
16. Is Machine tamping overdue? Yes/No

17. Whether inspections are entered Yes/No


regularly in TMS as per laid down
schedule?

5. Insulated Joints (Conventional), Glued Joints and Rail Joints

S. Item to be inspected Remarks Reference


N.
1. Whether condition of rails, sleepers Yes/No IRPWM Para
and packing of Insulated Joints/Glued 280 & 281
Joints is satisfactory?
2. Whether there is metal flow on the Yes/No
Insulated/Glued Joint rail ends?
3. Whether rails at joint are battered/ Yes/No
hogged?

75
S. Item to be inspected Remarks Reference
N.
4. Whether drainage is good on the Yes/No
Insulated/Glued Joints?
5. Whether inspections are entered Yes/No
regularly in TMS?

6. Deep Screening
S. Item to be inspected Remarks Reference
N.
1. Whether work is being done under Yes/No C.S. 128 of
competent supervisor? (JE/P.Way or PWS IRPWM
now a days, redesignated subject to
competency certificate issued by CTE)
2. Whether stipulated speed Yes/No IRPWM Para
restrictions are imposed at work site? 238(2)(f)
3. Whether level pegs are provided for Yes/No IRPWM Para
initial/final rail level restoration? (At 238(2)
every 30 M)
4. Whether screened muck is thrown Yes/No IRPWM Para
away from running track? 238(2)(e)
5. Whether proper wooden blocks and Yes/No IRPWM Para
other packing are used for passing the 238(2)(e)
trains?
6. Whether cess is cross-sloped and Yes/No IRPWM Para
repaired? 238(2)(e)
7. Whether Deep screening is being Yes/No
entered in TMS?
76
7. Lifting of Track.
S. Item to be inspected Remarks Reference
N.
1. Whether SE/P.Way is present at the Yes/No C.S. 128 of
site of lifting of track? IRPWM
2. Whether proper speed restrictions Yes/No IRPWM Para
are imposed at site? 233(3)
3. Whether track protection is done at Yes/No IRPWM Para
site? 806,807,808
4. Whether level pegs are provided for Yes/No IRPWM Para
finalising the required level? (At every 233 & 234
30M)
5. Whether lifting is being done from Yes/No IRPWM Para
down-hill end? 233(4)
6. Lifting of track should not more than Yes/No IRPWM Para
75mm at a time. Whether these 233(3)
instruction followed?
7. Whether work done is being entered
in TMS?
8. Drainage in Station Yards/Block Sections
S. Item to be inspected Remarks Reference
N.
1. Whether all drains were cleaned Yes/No IRPWM
before monsoon and its silt was Para 239 &
taken away from track? 240

77
S. Item to be inspected Remarks Reference
N.
2. Whether cleaning of shoulder ballast, Yes/No IRPWM Para
and removal of vegetation/weeds has 239 & 240
been ensured before monsoon?
3. Whether all side drains, catch water Yes/No IRPWM Para
drains are intact and desilted before 239 & 240
monsoon?
4. Whether work done has been Yes/No
entered in TMS?

9. Ballast Depot
S. Item to be inspected Remarks Reference
N.
1. Whether adequate leveled spacious Yes/No IRPWM Para
ground is available at specific ballast 266(2)
depot?
2. Whether all testing equipments are Yes/No
available and in working order at
depot laboratory?
3. Whether all records including Yes/No
registers, challans are updated and
intact?
4. Whether all qualitative and Yes/No IRS-GE-1
quantitative measures are being 2004
followed?
5. Whether adequate space is available Yes/No
between the stacks?
78
S. Item to be inspected Remarks Reference
N.
6. Whether unloading facilities are Yes/No
adequate?

10. Long Welded Rails (LWR)

S. Item to be inspected Remarks Reference


N.
1. Whether all inspections are done by Yes/No C.S. 15, LWR
SSE/JE as per laid down stipulations Manual
and properly recorded in LWR
register? (Fortnightly in 2 hottest & 2
coldest months individually by SSE/JE ;
once in 2 months by rotation by SSE/JE
in other months)
2. Whether gaps of SEJ are within Yes/No Para 5.6
permissible limits? (should be within LWR Manual
10 mm from specified value as per
Annexure V of LWR Manual)
3. Whether conditions of SEJ i.e. tongue Yes/No
rail, stock rail, sleepers & fittings are
good?
4. Whether speed restriction imposed Yes/No Annexure III
as per condition of track? LWR Manual
5. Whether destressing is done at
stipulated periods, date and Yes/No LWR Manual
temperature are recorded on LWR Para 8.2.2
board?

79
S. Item to be inspected Remarks Reference
N.
6. Whether staff is aware about rules? Yes/No LWR Manual
Para 8.1.3,
7. Whether Hot/Cold Weather Patrolling Yes/No Annexure X-
is being practiced at prescribed A & X-B of
temperatures? LWR Manual
td + 25 for HWP on LWR with PSC
sleeper & density 1540 or more
td + 20 for LWR in other cases for HWP
td - 30 for Cold weather patrolling
8. Whether Hot Weather Patrolmen is Yes/No Annexure
equipped with all stipulated tools X-A, LWR
mentioned in LWR Manual? Manual
9. Whether the condition of sleepers is O.K? Yes/No
10. Whether all fittings are available and Yes/No
tight?
11. Whether reference posts are Yes/No Para 5.9 of
available? LWR Manual

12. Whether temperature record is being Yes/No Para 5.2,


maintained on daily basis in SSE/ LWR
P.Way office? Manual
13. Whether LWR needs destressing? Yes/No Para 6.4.1,
LWR Manual

14. Whether all inspections, work done Yes/No


and changes are being entered in TMS?
15. Whether cold/Hot weather patrolling Yes/No Para 1.17
introduced? LWR Manual
80
11. Complete Track Renewal (CTR) Work
S. Item to be inspected Remarks Reference
N.
1. Whether work is being done as per Yes/No IRPWM Para
approved plan, estimate, tender 309 A
conditions, and location section?
2. Whether Railway Supervisor is Yes/No IRPWM Para
available at site of work? 826
3. Whether SR is imposed at the Yes/No IRPWM Para
worksite? 308
4. Whether track is adequately Yes/No IRPWM Para
protected? 806,807,808
5. Whether all material is kept ready
before commencement of traffic block? Yes/No

6. Whether inventory of released Yes/No


material is being ensured?
7. Whether all track-parameters within Yes/No IRPWM Para
permissible limits work at the end of 316(2)
the day?
8. Whether there is any infringement of Yes/No
new/released material with running
track?
9. Whether quality of laying is as per Yes/No
stipulated rules?
10. Whether a thermit welding done in Yes/No Para 8.10 of
situ is joggle fish platted with two USFD
clamps till tested as good by USFD? Manual
81
S. Item to be inspected Remarks Reference
N.
11. Whether all work is being entered in Yes/No
TMS?

B. SSE (P.Way) Office/Store


S. Item to be inspected Remarks Reference
N.
1. Whether all entries made in TMS? Yes/No
2. Whether all codes, manuals, Yes/No IRPWM Para
circulars, inspections notes are 119
available?
3. Whether Store and Office is neatly Yes/No
maintained?
4. Whether all Consumable and Yes/No
Perishable (C&P), Tools and Plants
(T&P) are recorded in ledgers?
5. Whether disposal of scrap, including Yes/No
proper weighment is being ensured?
6. Whether submission of Material At Yes/No
Site (MAS), revenue returns, test
check of stores being complied by
SSE?
7. Whether Periodical Medical Yes/No IRPWM Para
Examination (PME) of all Safety 133(1)
category staff/Supervisors are
ensured by SSE?

82
S. Item to be inspected Remarks Reference
N.
8. Whether all service records, leave Yes/No
staff are neatly maintained?
9. Whether all C&P and T&P available Yes/No
as per scale?
10. Whether proper water supply, Yes/No
electric supply and toilet facilities
are available?

C. Check list for USFD testing


(Issued by RDSO. Vide Letter no. CT/Welding/Policy dt.28.10.14)
Date of Inspection: …………..
SECTION........................DIVISION........................KM/
TP........................LINE.......................
Machine used for testing: Single Rail Tester / Double Rail Tester
Machine make and number:
Track Structure on test location:
Whether Stretch is having D-Marked Rails: Yes / No

S. Item of Works Observation/


N. Values Recorded
A. USFD Team
1. Operator (s)
(a) Name
(b) Competency Certificate Details
(c) Competency Certificate valid Yes / No

83
S. Item of Works Observation/
N. Values Recorded
2. Adequate staff for handling /
lifting of machines Yes / No
B. USFD Machines & Condition
1. Machine used is RDSO approved Yes / No
2. Availability of requisite tools & plants
i Sensitivity block Yes / No
ii IIW block for calibration Yes / No
iii Standard Rail test piece Yes / No
3. Visual Condition of electronic unit Proper / Not proper
4. Visual condition of Trolley Proper / Not proper
5. Condition of Probes & shoes
a Right Hand Side
i 0 degree Proper / Not proper
ii 70 degree (F) Proper / Not proper
iii 70 degree (B) Proper / Not proper
b Left Hand Side
i 0 degree Proper / Not proper
ii 70 degree (F) Proper / Not proper
iii 70 degree (B) Proper / Not proper

84
S. Item of Works Observation/
N. Values Recorded
c For Flange testing
i 70 degree 2 MHz Proper / Not proper
ii 70 degree 2 MHz (Side looking probe) Proper / Not proper
iii 45 degree 2 MHz Proper / Not proper
d Alignment probes & Lifting System
with respect to centre line Central / eccentric
6. Check on Characteristics of Machine
a Date of Check
b Whether due or not (Monthly check) Due / Not Due
7. Condition of Battery Charged/Not Charged
8. Condition of Audio Alarm Sounding /
Not Sounding
9. All Controls of electronic unit i.e.
depth range, gain, reject etc.
properly functioning Yes / No
10. Whether watering arrangement for
Probes is functional Yes / No
11. Availability of spares
i 0 0, 4 MHz Double crystal Probes : 8No. Yes / No
ii 00, 2 MHz Double crystal Probes : 8 No. Yes / No
Iii 700 (F&B) probes, 2 MHz Single
crystal : 8 No. Yes / No

85
S. Item of Works Observation/
N. Values Recorded
iv 450, 2 MHz Single crystal Probes : 2 No. Yes / No
v 700, 2 MHz Single crystal Probes : Yes / No
4 No.
vi 700, 2 MHz Single Crystal Probes Yes / No
(SLP) : 2 No
vii 00, 2/2.5 MHz Single crystal Yes / No
Probes : 2 No.
viii Connecting Cable (Flaw detector Yes / No
with junction box.) : 6 No
ix BNC Connector : 6 No. Yes / No
x IIW Block (as per IS : 1408) :2 Yes / No
xi 60x50x50 mm steel block (as per steel Yes / No
grade 45 C8 to IS : 1875-1992) : 1 No.
xii Battery Charger : 1 No. Yes / No
xiii Fuse : 12 No. Yes / No
xiv Step gauge : 1 No. Yes / No
C Check on sensitivity settings and calibration
1. Calibration Check
a Calibration for 300/200 mm longitudinal Proper /
wave using 00, Double crystal Probe Not Proper
b 165 mm Direct shear wave Proper /
calibration for 700, 2 MHz Single Not Proper
crystal Probe
86
S. Item of Works Observation/
N. Values Recorded
2. Sensitivity setting of equipment
and probes with help of standard Proper / Not Proper
rail piece
a Whether gain is locked after setting Yes / No
3. Check on function & sensitivity
of probes
a Normal Probe
(Back wall echo adjusted to full Proper / Not Proper
screen height)
b Angle probe 700 (Centre forward &
backward) (Amplitude of 12 mm dia. Proper / Not Proper
hole to be set to 3 div. i.e. 60% of
full screen height)
c Gauge face & Non gauge face
corner probe 700 (Forward &
Backward) Proper / Not Proper
(Signal amplitude from 5 mm FBH
to be set 60% of full height)
d 45 0 probe Proper / Not Proper
4. Whether adjustment in sensitivity
setting was done for variation in Proper / Not Proper
rail temperature
5. Whether gain has been increased Yes / No
by 10 db. for D Marked rails

87
S. Item of Works Observation/
N. Values Recorded
6. Check on equipment characteristic
a Linearity of time base of flaw Proper / Not Proper
detector
b Linearity of Amplification of flaw
detector Proper / Not Proper
c Penetrative Power Proper / Not Proper
d Resolving Power Proper / Not Proper
e Probe index Proper / Not Proper
f Burn angle Proper / Not Proper
7. Whether scheduled maintenance Yes / No
of USFD machine was done
D. Check on Work
1. Whether equipment is in proper Yes / No
working order duly calibrated
a Battery is fully charged Yes / No
b All controls of electronic unit Yes / No
properly functioning
c Calibration & sensitivity setting Yes / No
done
d Whether the gap between probing
face and probe shoe is proper Yes / No
(0.2 mm)

88
S. Item of Works Observation/
N. Values Recorded
e Whether alignment of probes is Yes / No
proper
f Adequate supply of water for
coupling for all the probes is Yes / No
ensured
2. Check on previous day’s work
(i) Date of testing
(ii) Location of testing (From Km to Km)
(iii) Rail testing
a Whether all IMR defects confirmed Yes / No
b If No, number of additional defects
1. Over Reported
2. Under Reported
(c) Whether preventive action taken Yes / No
on all defects
(d) Whether all OBS defects confirmed Yes / No
(e) If No, number of additional defects
1. Over Reported
2. Under Reported
(f) Whether preventive action taken Yes / No
on all defects

89
S. Item of Works Observation/
N. Values Recorded
(iv) Weld testing
(a) Type of Welds
(b) Whether all defects confirmed
(c) If No, number of additional defects
1. Over Reported
2. Under Reported
(d) Whether preventive action taken Yes / No
on all defects
(v) Whether the A-scans of all defects Yes / No
preserved in machine
3. Check on day's work
(a) Type of Testing Rail / weld
(b) The A-Scans of all defects being
preserved Yes / No
(c) The defects details are properly Yes / No
logged in machine
(d) Defects are properly entered in Yes / No
Register
E. Schedule of USFD testing and adherence
1. Date of last USFD Testing of
Inspected Stretch
(a) Rail testing

90
S. Item of Works Observation/
N. Values Recorded
(b) Weld testing
2. Stipulated frequency of section
(a) Rail testing
(b) Weld testing
3. Whether testing is done as per Yes / No
Schedule
4. Proper up keep of defects register Yes / No
has been done

D. Check list for Inspection of AT Welding


(Issued by RDSO. Vide Letter No. CT/Welding/Policy dt.28.10.14)
Date of Inspection:
SECTION........................DIVISION........................KM/
TP........................LINE.......................
Brief of Welding Technique
(Rail Section/UTS/Heating Technique/Mould/Tapping)

S. Item of Works Observation/


N. Values Recorded
A. Storage of Welding Material at Store
1. AT Welding Portion
(a) Secured Building Yes / No
(b) Ventilation Good / Poor
(c) Dampness Yes / No

91
S. Item of Works Observation/
N. Values Recorded
(d) Properly Packed Yes / No
2. Igniters
(a) Storage different from portion Yes / No
(b) Stored in locked steel cupboard Yes / No
3. Prefabricated Moulds
(a) Dampness Yes / No
(b) Properly Packed / Neatly stacked Yes / No
B. Preparatory Arrangements at Site
1. Availability of complete T & P and
consumables at site
(A) Preheating Equipment
A-1 Air-Petrol Heating
1. Pressure Tank with Pressure Yes / No
gauges : 1 No.
2. Vaporizers ( Burner ) complete : 1 No. Yes / No
3. Nozzle Pricker : 2 Nos. Yes / No
4. Nozzle Keys : 1 No. Yes / No
5. Vaporizer stand : 1 No. Yes / No
6. Goose neck attachment to Yes / No
vaporizers : 2 No.
A - 2 Compressed Air - Petrol Pre-Heating

92
S. Item of Works Observation/
N. Values Recorded
1. Compressor system with Pressure Yes / No
gauge : 1 No.
2. Torch ( Burner ) complete :2No. Yes / No
3. Torch ( Burner ) Keys : 1 No. Yes / No
4. Torch ( Burner ) Stand : 2 No. Yes / No
5. Goose neck attachment to Yes / No
vaporizers : 2 No.
A - 3 Oxy - LPG Pre-Heating
1. Oxy - LPG Torch ( Burner ) : 1 No. Yes / No
2. Oxygen Cylinder with Pressure Yes / No
gauge : 1 No.
3. LPG Cylinder with Pressure Yes / No
gauge : 1 No.
4. Torch ( Burner ) Stand : 1 No. Yes / No
5. Connecting Hose Pipe : 2 No. Yes / No
B. Sufficient quantity of fuel
(Petrol / LPG-Oxygen as required Yes / No
from authorized sources )
(Indicate Source) →
C. Crucible and accessories :
1. Crucible Complete : 1 No.
(a) Crucible shell Yes / No

93
S. Item of Works Observation/
N. Values Recorded
(b) Crucible Lining (Availability of
Magnesite powder & sodium
silicate )
2. Crucible cap : 1 No. Yes / No
3. Crucible forks : 1 No. Yes / No
4. Crucible stands : 1 No. Yes / No
5. Crucible rings : 1 No.
D. Mould fixing arrangement
1. Mould Pressure ( Clamp ) : 1 set Yes / No
2. Mould Shoes : 2 Pairs Yes / No
E. Weld Trimmer with power pack: 1 No.
( From Approved source ) Yes / No
Indicate Source →
F. Rail profile weld grinder: 1 No.
( From Approved source ) Yes / No
Indicate Source →
G. Measuring Tools :
1. Straight Edge 1m long : 1 No. Yes / No
2. Straight Edge 10 cm long : 1 No. Yes / No
3. Gap gauge & Height Gauge : 1 No. Yes / No
4. Filler gauge : 1 No. Yes / No

94
S. Item of Works Observation/
N. Values Recorded
5. Pyrometer / Thermal chalk for Pyrometer /
measurement of Rail Temperature Thermal Chalk
: 1 No.
6. Stop watch : 1 No. Yes / No
H. Other tools / Equipments
1. Cleaning rod round : 1 No. Yes / No
2. Tapping rod : 1 No. Yes / No
3. Aluminum / steel rod for thermal
plugging : 1 No, Yes / No
4. Leather washers for pump : 2 No. Yes / No
5. Tool for punch marking : 1 set Yes / No
6. Mirror 150 X 100mm with Yes / No
handle : 1 No.
7. Wooden wedges for rail Yes / No
alignment : 12 No.
I. Tool box Containing following :
1. Hot Sets (Chisels): 2 No. Yes / No
( For Emergency use only )
2. Rail file 350 X 40-6 mm: 2 No. Yes / No
( For Emergency use only )
3. Funnel tin for pouring petrol : 1 No. Yes / No
4. Adjustable spanner : 1 No. Yes / No

95
S. Item of Works Observation/
N. Values Recorded
5. Hammer 1 kg : 1 No. Yes / No
6. Sledge hammer double panel 5 kg : 2 No. Yes / No
7. Steel wire brush : 1 No. Yes / No
8. Blue goggles : 2 pairs Yes / No
9. Paint brush 50 mm : 1 No. Yes / No
10. Slag container (bowl) : 1 No. Yes / No
11. Asbestos gloves : 2 pairs Yes / No
12. Hose clips : 4 No. Yes / No
13. Pliers : 1 No. Yes / No
J. Insulation hood for control cooling Yes / No
(for HH rail, 110 UTS rail welding ) Required /
Not Required
2. Welding Technique used is proper Yes / No
as per extant provisions
(Compressed Air/Oxy-LPG Heating,
3 piece mould & Auto Tapping
Thimble for 52 kg 90 UTS rails and
above)
(Indicate Technique being used) →
2.1 Technique is approved for the firm Yes / No
3. Welding Portion & consumable
(a) Portion as per Rail section /UTS to Yes / No
be welded & of proper technique

96
S. Item of Works Observation/
N. Values Recorded
1. Supplier / Firm
2. Batch No.
3. Portion No.
4. IC No.
5. Date of Manufacture
6. Results of Reaction test, if the Required / Not
portion is 2 years old Required
Nature of Reaction Normal / Boiling
7. Condition of Packing
(b) Three piece Mould
1. Condition of Mould Damp / Dry Cracked
/ Intact
2. Condition of vents in mould Blocked / Clear
(c) Proper quality looting sand,
ignition etc. are properly inspected Yes / No
(d) Other consumables Indicate Material &
Condition
4. Welding Team
(a) Whether full contingent of welding
team is available at site
(i) Welder : 1 No. Yes / No
(ii) Skilled Artisan : 2 No. Yes / No
97
S. Item of Works Observation/
N. Values Recorded
(iii) Helper Khalasi / Khalasi : 5 No. Yes / No
(iv) Track Man: As required for site Yes / No
protection.
Name of Welder
Details of competency certificate
(b) (certificate no. & validity )
Whether competency is for Yes / No
technique to be used & is valid
Name of supervisor
Details of competency certificate
(c) (certificate no. & validity )
Whether competency is for Yes / No
technique to be used & is valid
(d) Welding of Rails being welded
5. Details of Rails being welded
(a) Section / UTS
(b) Old or new
(c) In case old Rails,
1. Anticipated balance service life
2. Rail is free from corrosion or Yes / No
excess wear.
3. Result of USFD testing.
98
S. Item of Works Observation/
N. Values Recorded
4. General Condition of rails
6. General Condition of Rail ends
1. Condition of Rail Ends Hogged / Battered
Straight
2. Battering / Hogging in mm
3. End Bends of the rails in mm Vertical :
( Vertical : +0.5mm/ -0.0 mm Lateral :
Lateral : 0.5 mm )
4. End cuts are truly vertical Yes / No
5. Ends are cleaned by K-oil & wire
brush Yes / No
6. Fish bolt holes have been
eliminated Yes/No
If no. distance of fish bolt holes
from rail end being welded
C. Execution of Welds
1. Traffic Block Time
2. Gap between rail in mm
(25mm + 1for normal welds
50 + 1 and 75 + 1 for wide gap welds)
3. Alignment of rail with 1m straight
edge

99
S. Item of Works Observation/
N. Values Recorded
a Lateral
(+0.5mm)
b Vertical
(The joint shall be kept higher by :
3 to 4 mm for 72UTS and 2 to
2.4 mm for higher UTS)
4. Whether proper clear working
space of 250 mm is available and Yes / No
fastening of 5 adjacent sleepers
removed
5. Proper Fixing of Prefabricated
Mould
(a) Mould aligned Centrally Yes / No
(b) The gap between mould and rail Yes / No
packed firmly with luting sand
6. Proper Fixing of Mould shoes : Yes / No
perfectly vertical, not skew
7. Pressure in Preheating
arrangement
(a) Air Petrol : Compressor tank
Pressure (7+0.7 Kg/cm2)
(b) Compressed Air Petrol : Air Pressure
(0.2 to 0.3 Kg/cm2)
(c) Oxy - LPG Pre heating :

100
S. Item of Works Observation/
N. Values Recorded
(i) Pressure for Oxygen Cylinder
(7 to 8 Kg/cm2)
Pressure for LPG Cylinder
(2 to 2.5 Kg/cm2)
8. Whether pre heating torch is Yes / No
properly placed
9. Proper fixing of crucible
9(a) Whether the crucible has been
repaired properly with no loose Yes / No
sand particles
10. Specific check on AT welding Dry / Wet
portion before pouring in crucible
11. Preheating time (in minutes)
(a) Air Petrol Heating (10 to 12 minutes)
(b) Compressed air petrol (4 to 4.5
minutes)
(c) Oxy - LPG preheating (2 to 2.5
minutes)
12. Reaction of AT welding portion on Normal / Boiling
ignition violent
13. Tapping time in seconds
(Manual Tapping: (20+3) sec,
Auto Tapping L As per approval)
(a) Tapping done at time
101
S. Item of Works Observation/
N. Values Recorded
14. Mould waiting time
(4-6 minutes for 25 mm weld
12 minutes for 75 mm welds)
(a) Mould Removed at time
15. Trimming of weld done by weld Yes / No
trimmer with alignment wedges
in position
a . Wedges was removed fastening Yes / No
re-fixed and sleeper spacing
corrected
b. Wedges removed at time
16. All the removed fastening
re-fixed and sleeper spacing Yes / No
corrected
17. Provision of wooden block
below the weld for support Yes / No
before passing first train
18. Removal of Risers & Runners
(a) Whether weld has completely Yes / No
cooled
(b) Removed by knocking towards Yes / No
the rail
19. First train was passed after 30
min of pouring weld metal and Yes / No
completion of weld trimming

102
S. Item of Works Observation/
N. Values Recorded
(a) First Train passed at time
(b) First train passed with speed
restriction of
20. Grinding of Weld
Whether Grinding done with Profile Grinder /
profile grinder or manually Manual
Grinding was done after how
much time
Grinding of location as required Yes / No
D. Inspection of Weld
1. Visual Inspection Satisfactory /
Not satisfactory
2. Tolerances of finished weld
(a) Vertical (with 1m straight edge)
(Variation not more than +1mm/
-0.0 mm)
(b) Lateral (with 1m straight edge)
(Variation not more than +0.5mm)
(c) Finished of top surface at the
end of 10cm straight edge
(+0.4 mm /-0.0mm)
(d) Finished on sides of rail head at
the centre of 10cm straight
edge (+0.3mm)
103
S. Item of Works Observation/
N. Values Recorded
3. Numbering of Weld
(a) Serial number of Weld
(b) Marking on weld done on NGF Yes / No
side as per provisions
4. Whether USFD testing of weld was Yes / No
done
(a) If yes, result of USFD testing
Action Plan for Re-welding in case
the weld found defective
(b) If no, necessary precautions taken
at site
(Protection of weld by joggled
fish plates)
5. Whether painting of thermit weld Yes / No
done or not
6. Whether the details of weld was Yes / No
properly entered in weld Register
E. Miscellaneous Items
1. Whether sample test joint are due
to be made for testing. (One out of
100 joints to be tested for Load
deflection, Hardness & porosity
tests)
(a) If, yes Indicate details viz. Joint
No. etc.
104
S. Item of Works Observation/
N. Values Recorded
(b) Action Taken for testing of sample
joints
2. In case of contractual welding
2.1 Contract Details
(a) Name of firm
(b) CA No.
(c) Validity of contract
2.2 Total number of welds done so far
2.3 Details of USFD Testing
(a) Total no. of weld found defective in
USFD Testing
(b) Total no. of welds failed in service
during guarantee period
(c) Total Percentage of defective Welds
(d) The % of defective weld is within
the permissible range
2.4 Load Deflection Test, Hardness &
Porosity test
(a) Total No. of samples Required to
be tested @ 1 sample per 100 welds
(b) No. of test weld tested in Load
deflection, hardness & porosity test

105
S. Item of Works Observation/
N. Values Recorded
(c) Test Weld Samples results Yes / No
satisfactory
(d) Action taken in case of
unsatisfactory results
3. Proper Maintenance of Weld Yes / No
Register

106
E. Level Crossing.
1. Manned Level Crossing.

S. Item to be inspected Remarks Reference


N.
1. Is the number of the Level Crossing (LC) Yes/No
mentioned at the LC Gate?
2 Is class of the gate mentioned on the Yes/No
gate?
3 Whether Traffic/Engineering is written Yes/No IRPWM PARA
on the gate? 909
4 Whether no. of G.K. sanctioned is Yes/No
written on the gate?
5 Whether lifting barrier is provided or Yes/No IRPWM
not? Annexure 9/1

6 Whether the focusing of gate lamps is Yes/No IRPWM


all right, when observed from an Annexure
adequate distance from the middle of 9/1
the road?
7 Whether sufficient quantity of Yes/No IRPWM Para
kerosene oil, wicks and match boxes 910
are available at the gate?
8 Whether the gateman is on duty as per Yes/No
duty roster or not?
9 Whether height gauge is provided at Yes/No IRPWM Para
the level crossing (in electrified 910(4)
sections)?

107
S. Item to be inspected Remarks Reference
N.
10 Whether the knowledge of gate man Yes/No IRPWM Para
is up to the mark? 914

11 Whether in the electrified section, the Yes/No


clearance between the height gauge
and the road surface is as per
stipulation? (4.67 meter)
12 Whether the condition of gate and its Yes/No IRPWM
locking arrangements are all right? Annexure 9/1
13 Whether cross levels/gauge are in Yes/No
order?
14 Whether adequate ballast cushion is Yes/No
available at the gate?
15 Whether interlocking as per Train Yes/No
Vehicle Units (TVU) criteria arecarried
out or not? (Spl., A and B1 class)
16 Are the whistle boards corroded? Yes/No
17 Whether the condition of the Yes/No
drainage is all right at the gate?
18 Whether the station working rule Yes/No
book is available in Hindi?
19 Whether a ramp has been provided at
Yes/No
both ends of the road?
20 Whether the gate man has undergone Yes/No IRMM Vol I
medical checkup? (At the termination Para 514(A)
of every period of four years,
108
S. Item to be inspected Remarks Reference
N.
calculated from the date of
appointment, until they attain the age
of 45 years, and then every two years
until the age of 55 years and then there
after annually, until the conclusion of
their service.)
2 1 Whether safety banners and other Yes/No IRPWM
related items have been displayed at Annexure
the gate? 9/1
2 2 Has the gate man undergone the Yes/No CS No. 113 of
refresher course as per IRPWM
periodicity?(Every 5 years)
2 3 Is the condition of the approach road Yes/No IRPWM
good? Annexure 9/1
2 4 Does the gate man have extra chains Yes/No IRPWM
in case of failure of the gate barrier for 910.(1)(e)
immediate and prompt action?
2 5 Whether gate working Rules are Yes/No IRPWM
available at Gate? Annexure9/1
2 6 Whether gate working rules are as per Yes/No
provision of Station working rules?
2 7 Are Safety equipments such as hand Yes/No
signal lamp, hand signal detonators,
pad locks and safety chains available
at LC gate as per equipment list
provided on the gate?

109
S. Item to be inspected Remarks Reference
N.
28 Is the gate man fully acquainted with Yes/No
the use of the equipments?
29 Whether overhauling of the gate has Yes/No IRPWM Para
been done and is not overdue? (Once 914(1)(b)
in 2 years on PSC sleepers. Every year
for other than PSC sleepers)
30 Whether night inspections are being Yes/No IRPWM Para
carried out regularly? 914(1) (d)
31 Whether the TVU data is updated as Yes/No IRPWM
per three years schedule? Para 919
32 Whether the speed breakers are Yes/No IRPWM
provided on both sides of the road? (20 Annexure
m from gate post) 9/1
33 Is the revolving unit of the lifting Yes/No
barrier in working order?
34 Is the communication to the gate Yes/No IRPWM
proper by means of telephone? Annexure 9/1
35 Whether Station Master is responding Yes/No
to rings from the gate?
36 Whether private number are being Yes/No
recorded correctly at gate?
37 Has a hand pump for drinking water Yes/No
provided at the site?
38 Whether fencing has been provided
Yes/No IRPWM
along the track, at the level crossing Annexure 9/1
gate? (15 Meters)
110
S. Item to be inspected Remarks Reference
N.
39 Has the cleaning of the check rails being Yes/No
done properly at the gate?
40 Whether Check rail clearance is in Yes/No SOD Ch. I
order? (Clearance 51–57mm Clear item 5 & 6
depth-38mm )
41 Are the road signs on the approaches Yes/No IRPWM
properly maintained? Annexure 9/1
42 Whether the protection diagram has Yes/No
been exhibited at gate?
43 Whether detonators are available at Yes/No G&SR CS. No
LC Gate in adequate numbers with 30
valid date? (Validity 5 years and
extended up to 8 years).
44 Whether competency certificate of the Yes/No
gate man is current and valid?
(Once in 3 years)
45 Whether condition of check rail, check Yes/No
rail blocks proper or not?
46 Whether adequate ballast cushion is Yes/No
available below sleeper or not?
47 Whether proper bend/flair in check Yes/No
rails end portion has been provided?
48 Whether extra shoulder ballast has Yes/No
been provided in the approaches of
level crossing track to arrest the extra
111
S. Item to be inspected Remarks Reference
N.
stress in rails during extreme hot
weather?
49 Whether painting and fitting of rails Yes/No
and check rails has been done? (Along
with over hauling)
50 Whether adequate longitudinal slope Yes/No IRPWM
has been given in the approach road of Annexure 9/1
level crossing?
51 Whether adequate width has been Yes/No IRPWM
provided on the road in the Annexure 9/1
approaches, as well as on the track
portion i.e. as per class of road?
52 Are the W/L boards provided at Yes/No IRPWM
adequate distance? (600 m) 916/1
53 Is the gate lodge as per standard of the Yes/No
type plan?
54 Whether the wall clock in working Yes/No
condition?
55 Have the Safety posters been Yes/No
displayed?
56 Whether the train time tables have Yes/No
been displayed at the gate lodge?
Yes/No
57 Whether the inspection book of level Yes/No
crossings is available at the gate?

112
S. Item to be inspected Remarks Reference
N.
58 Whether the complaint book is Yes/No
available at the gate?
59 Whether level crossing registers are Yes/No IRPWM
available at the gate? Para 915
60 Whether the gate booms/gate leaves Yes/No
are properly functioning?
61 Whether the gate man is aware of the Yes/No
safety rules in case of emergency?

2. UNMANNED LEVEL CROSSINGS

S. Item to be inspected Remarks Reference


N.
1 Is the number of LC mentioned at LC Yes/No
Gate?
2 Is the type of gate mentioned on the Yes/No
gate?
3 Whether the road surface is well Yes/No
maintained between gate posts and
approaches as regards level &
gradient? IRPWM
(The uneven or broken surface of Annexure 9/1
road should be leveled as early as
possible. And patch work should be
done immediately, so that the road
surface can be made leveled and
113
S. Item to be inspected Remarks Reference
N.
smooth. Hexagonal concrete blocks may
be provided, which are durable against
wear and tear in gauge conversion and
new construction. It has been proved
more useful and durable for maintaining
the road surface. Secondly it gives better
appearance to the road surface and
having high resisting power during
monsoon season. It should be provided
in between the two gates. Outside the
gate road surface can be maintained by
black top road. Hence it is easy to
maintain and easy to prepare a smooth
road surface quickly. Road surface is
made smooth in such a way that vehicles
are not struck to the track)
4 Are the road signs on the approaches Yes/No
properly maintained?
(Generally indicators and warning
boards get faded with time when
ordinary paint is used. Hence as for as
IRPWM
possible luminous paints / luminous
Annexure
strips should be used. As far as
9/1
luminous strip and luminous paint are
concerned, for speed breakers sign
boards, whistle boards and stop boards
etc. the luminous strip are more
effective rather than luminous paint as
it is just a like a pre-cast concrete which
cannot be deteriorated immediately.)
114
S. Item to be inspected Remarks Reference
N.
5 Whether check rail clearance is in Yes/No SOD Ch. I
order? (Clearance 51-57 mm Clear item 5 & 6
depth 38 mm )
6 Whether track gauge and Cross-Level Yes/No
are in order?
7 Whether W/L board provided on both Yes/No IRPWM Para
sides of the gate at a proper location, 916(1)
at a distance of 600 m from level
crossings on either side of the road?
8 Whether the condition of the approach Yes/No IRPWM
track of level crossings is in good Annexure 9/1
condition?
9 Whether visibility requirement for Yes/No IRPWM Para
road users of 600 m along the track from 917
5 m from nearest track center.
10 Whether road users are taking Yes/No
precautions of stopping on the whistle
of the train?
11 Whether stop board is provided on the Yes/No IRPWM
both ends of the road approaching in 916(2)
case of unmanned gate? (5 m from
center line of nearest track)
12 Whether speed breakers are provided Yes/No CS No. 128 of
on both sides of the road? 20 m from IRPWM
gate post

115
S. Item to be inspected Remarks Reference
N.

13 Whether warning boards have been Yes/No IRPWM


provided at the proper location? Annexure 9/1

14 Is the census being carried out Yes/No IRPWM Para


regularly after three years? 919

F. Inspection for Tamping Site


(3X/CSM/Duomatic/UNIMAT)
S. Item to be inspected Obser- Reference
N. vation
1 a) Machine Type
(CSM/Duomatic/Unimat)
b) Machine No. & Make
c) Base station/Division Railway
Board
d) Manufacturer
Letter
e) Year of manufacturing No.98/
Track-III/Tk/
f) Last major Maintenance schedule POH/ 27-Pt
(POH/IOH) undertaken IOH dated 20-
g) Next POH/IOH due on POH____ 05-2003
IOH___

h) Month/year of last POH/IOH


i) Depot of last POH/IOH

116
S. Item to be inspected Remarks Reference
N.
j) Rated output of the machine
(No. of Sleepers/Hour)
k) Name of SSE/TM/In-charge
l) Name/designation of the operator
2 Is there any tamping tool(s) missing Yes/No Para 3.1.3
or worn-out? (V)
(Wear to be < 20% of cross sectional (IRTMM)
area)
3 Is the Condition of tamping tools Yes/No Para 3.1.3
satisfactory and fitting tight? (V) (IRTMM)

4 Is the condition and adjustment of Yes/No Checklist iss-


track lifting rollers satisfactory? ued by RDSO
5 Is the condition of lifting hooks Yes/No/ Checklist iss-
(UNIMAT) satisfactory? NA ued by RDSO
6 Availability of Camping coach Yes/No

7 Is the condition of the Camping Yes/No Para 3.1.1(i)


Coach satisfactory? (IRTMM)
8 Are all safety equipment as per list Yes/No Checklist
annexed available? issued by
RDSO

9 Has it been ensured that stabling Yes/No Para 7.2 (i)


siding for machine’s coaches is having IRTMM
adequate water supply, power supply
& resting facility?

117
S. Item to be inspected Remarks Reference
N.
1 0 Pre-tamping Inspection
i) Location of inspection
KM.
Line
Blocksection
Route
Division
ii) Availability of
a) Clean Cushion (minimum 150 mm) Yes/No Para 3.1.1(iv)
(IRTMM)
b) Adequate ballast for min. 20 mm Yes/No
lift in shoulder / crib
iii) Month & Year of Last Deep
Screening
iv) Is the condition of track drainage Para 3.1.2
satisfactory, pumping locations (vi)
attended & rounded ballast replaced Yes/No
(IRTMM)
with clean angular ballast?
v) Is the condition of cess satisfactory Yes/No Para 3.1.2(v)
and low cess made-up? (IRTMM)
vi) Is the speacing of sleeper’s Yes/No Para 3.1.2(iv)
uniform? (IRTMM)
vii) Are fittings in good Condition and Yes/No Para 3.1.2
tightened? (vi)
(IRTMM)

118
S. Item to be inspected Remarks Reference
N.
viii) Has all missing/broken fittings Yes/No Para 3.1.2
been replaced? (vii) (IRTMM)

ix) Is the condition of sleepers Yes/No Para 3.1.2


satisfactory? (ix) (IRTMM)
x) Has all damaged/broken sleepers Yes/No Para 3.1.2
been replaced? (viii) (IRTMM)
xi) Are all the sleepers square? Yes/No Para 3.1.2
(ix)(IRTMM)
xii) Has attention to hogged/battered Yes/No/ Para 3.1.2
joints been given? NA (iv) (IRTMM)
xiii) Was Pre-tamping survey done as Yes/No Para 3.1.2 (i)
per guidelines (IRTMM/Anne. 5.3) for (IRTMM)
design mode working?
xiv) Is the solutions for Realignment Yes/No/ Para 3.1.2(i)
of curves with interpolation of slews NA (IRTMM)
for feeding (with correction values, as
applicable) available? (as per
Annexure 5.3of IRTMM)
xv) Are the beginning and end of Yes/No/ Para 3.1.2(ii)
circular and transitions of curves NA (IRTMM)
marked on sleepers?
xvi) Is the plotting of existing profile
after pre-survey done and working Yes/No Para 3.1.2 (i)
sheet for slew & lift values and (IRTMM)
interpolation for feeding (with
correction values, as applicable)
prepared? (as per Annex. 5.3 of IRTMM)
119
S. Item to be inspected Remarks Reference
N.
xvii) Are the reference markings Yes/No Para 3.1.2 (i)
along the track available? (IRTMM)
xviii) Has slew values, lift values and Yes/No Para 3.1.2 (ii)
SE values written on sleepers? (IRTMM)
xix) Is ballast heaped in tamping Yes/No Para 3.1.2
zone? (iii) (IRTMM)
xx) Are the level crossing road Yes/No/ Para 3.1.2
surface opened for tamping? NA (IRTMM)
xxi) Are the check rails on level Yes/No/ Para 3.2.1
crossings removed for tamping? NA (xi) (IRTMM)
xxii) Are the guard rails on bridge Yes/No/ Para 3.2.1
approaches removed? NA (xi) (IRTMM)
xxiii) Is the Removal/marking of Yes/No Para
obstructions such as rail lubricators, 3.2.2(xii)
signal rods, cable pipes, glued joints (IRTMM)
etc. done?
xxiv) Are the marking of OHE bonds/ Para
Yes/No/
removal done? (in electrified 3.2.2(xiv)
NA
sections) (IRTMM)

xxv) Are the joggled fishplates, Yes/No Para 3.2.2


wooden blocks etc. removed? (xiii) (IRTMM)
xxvi) Is the sufficient lighting at work Yes/No/ Para 3.1.2
site arranged for working during NA (vii)
night? (IRTMM)
xxvii) Has the availability of OHE and

120
S. Item to be inspected Remarks Reference
N.
S&T staff been ensured, as required? Yes/No/ Para 3.2.2 (v)
NA of IRTMM
xxviii) Has adjustment of gaps in Yes/No/ Para 3.1.2 (x)
joints / creep adjustment been NA of IRTMM
done?
xxix) UNIMAT working
a) Turnout No.
b) Station
c) Angle of crossing
d) LH/RH
e) When was it last Tamped?
(Month/ Year )
f) Is the layout including spacing of Yes/No Para 3.2.1 (i)
sleepers as per relevant drawings? (IRTMM)
g) Is the battered or worn Crossing Yes/No Para 3.2.1 (ii)
attended? (Reconditioning/ (IRTMM)
Replacement)
h) Are the S&T gears likely to infringe Yes/No Para 3.2.2 (v)
during tamping cleared? (IRTMM)
LWR
i) Destressing temperature of LWR
ii) Last destressing date

121
S. Item to be inspected Remarks Reference
N.
iii) Is the temporary de-stressing Yes/No Para 3.1.2(x)
done at higher/lower temperature? Temp (IRTMM)
td= °C
iv) Likelihood of temperature Yes/No Para 6.2.1 (i)
exceeding t d+20°C (a) (LWR
Manual)

9 Section of work
i) Division
ii) ADEN
iii) SSE Section
1 0 Section of work / Traffic block
i) Block section and lines blocked
ii) Timing and total Duration (minutes)
iii) Travel time to work spot (minutes)
iv) Actual working time (minutes)
v) Travel time to clear block (minutes)
vi) Total ineffective time (minutes) Railway
(Max ineffective time = 0.45 Hrs.) Board
(27 minutes) Letter
No.98/
Track-III/Tk/
27-Pt dated
20-05-2003

122
S. Item to be inspected Remarks Reference
N.
11 Operations During Tamping
i) Has the protection of the site of Para 4.2.2
Yes/No
work and adjoining track done as per (IRTMM)
G&SR?
ii) Working alignment .
(Straight/curve)
iii) Degree & Length of curve Degree=
Length=
in meter
iv) Is there any Points & Crossings Yes/No
present in planned stretch for
tamping?
v) Are there points and crossing Yes/No
being tamped in same block?
vi) Is the Lining being done in Design Yes/No
mode?
vii) Lining Working Method adopted 3 Point
4 Point
viii) Is the Levelling being done in Yes/No
Precision mode?
ix) Has the Setting of tamping depth Yes/No Para 3.1.3 (i)
been done as per track structure? (IRTMM)
The gap between top edge of the
tamping blade and the bottom edge
of the sleeper in closed position of
the tamping tool should be adjusted
123
S. Item to be inspected Remarks Reference
N.
depending upon the type of rail and
sleepers.
(For Metal sleeper: 22-25 mm, for
Flat bottom sleeper : 10-12 mm)
x) Is the Squeezing pressure of Yes/No Para 3.1.3
tamping unit correctly set? (iii) (IRTMM)
a) PSC sleepers (110-120 kg/cm2),
b) ST, Wooden sleepers (100-110 kg/
cm2),
c) CST-9 sleepers (90-100 kg/cm2)
xi) Minimum Slew Value (mm) mm
xii) Maximum Slew Value (mm) ( Not mm Para 3.1.3
more than 50 mm) (viii) (IRTMM)
xiii) Maximum lift value (mm) ( Not mm Para 3.1.3
more than 50 mm) (viii) (IRTMM)
xiv) Has it been ensured that a Yes/No Para 3.1.1
minimum 15-20 mm general lift is (i) (IRTMM)
given at high point?
xv) Is no. of insertion commensurate Yes/No Para 3.1.3
with lift? (iii) (d)
(up to 30mm lift – single insertion, (IRTMM)
30mm to 50mm – two insertions for
PSC sleeper track)

124
S. Item to be inspected Remarks Reference
N.
xvi) Is the squeezing time set Yes/No Para 3.2.3
correctly? (0.4 to 0.6 sec) (iv) (IRTMM)
xvii) Are the feeding of correction Yes/No/ Annexure
values on transitions of curves (Vm/ NA 2.1
F) being done? (In 4 point system of (IRTMM)
lining only)
xviii) Is the feeding of SE values done Yes/No/ Track Machine
as per feeding location? NA Documentation
xix) Is the correction for new SE, (K) Yes/No/ Track Machine
being done? NA Documentation
xx) Is the feeding of ‘X’ correction for Yes/No/ Track Machine
vertical curve being done? NA Documentation

xxi) Is the ramping of 1 in 1000


given before closing the day's work Para 3.1.3
Yes/No
and obligatory points being done? (vi) (IRTMM)
(The next day's work shall begin from
the point of commencement of
previous day's ramp)
xxii) Are the parameters of tamped Yes/No Para 3.1.3
track checked after tamping? (ix) (IRTMM)
xxiii) UNIMAT working
a) Length of approaches covered Para 3.2
------m
along with turnout (m) IRTMM
b) Direction of tamping
(Switch → Crossing) Yes/No

125
S. Item to be inspected Remarks Reference
N.
c) Is the Sequence of tamping is first Para 3.2.2
on main line then on turnout side? Yes/No (i)
(ML → LL) (IRTMM)
d) Is the turnout side rail supported Yes/No/ Para 3.2.2
after lifting on mainline; till it is NA (i)
tamped (IRTMM)

e) Has the Squeezing pressure been


set correctly?
Yes/No Para 3.2.2
(i) ST/wooden sleepers : 110-115 kg/
(iii)(IRTMM)
cm2
(ii) PSC sleepers: 135-140 kg/cm2
f) Has it been ensured that a Yes/No Para 3.2.1
minimum of 10 mm general lift is (iii) (IRTMM)
given at high points in the turnout?
g) Has the turn in curve been tamped Yes/No/ Para 3.2
along with turnout? NA (IRTMM)

12 Post Tamping Operations


i) Location of inspection :-
KM:-
Line:-
Block section:-
Route:-
Division:-

126
S. Item to be inspected Remarks Reference
N.
ii) Has all loose fittings been Yes/No Para3.1.4 (i)
tightensd? IRTMM

iii) Has all broken fittings been Yes/No Para3.1.4 (ii)


replaced? IRTMM

iv) Has the ballast been dressed Yes/No


neatly? Para3.1.4
v) Has the ballast between the (iii) IRTMM
sleepers and on shoulders been Yes/No
consolidated?
vi) Has all track parameters been Para 3.1.4
Yes/No
recorded with the help of recorders (iv) IRTMM
provided in the tamping machine?
vii) Whether Value of Track Parameter
recorded satisfies IRTMM provisions?
Alignment Para 3.1.4
a) Not more than 10 peaks exceeding Yes/No
(iv) IRTMM
+/- 4 mm.
b) Any peak not more than +/- 6 mm.
Cross level Not more than 10 peaks Para 3.1.4
Yes/No
exceeding +/- 6 mm. (iv) IRTMM

Unevenness Para 3.1.4


a) Not more than 10 peaks exceeding Yes/No
(iv) IRTMM
6 mm.
b) Any peak not more than 10 mm.
viii) Has all check rails/guard rails Para 3.1.4
Yes/No
been re-fixed? (vi) IRTMM
127
S. Item to be inspected Remarks Reference
N.
ix) UNIMAT working – Has all S&T/ Yes/No Para 3.2.3
Electrical connections been (IRTMM)
restored?
1 3 Has it been ensured that adequate Yes/No Para 263
ballast is trained out for complete (IRPWM
ballast profile as per IRPWM and
profiling done?
1 4 Is the actual Output of the machine Yes/No Railway
matches with rated Progress of the Board Letter
Machine? No.98/Track-
Duomatic - III/Tk/27-Pt
dated 20-05-
CSM - 1.2 Km/effective block hour 2003
T EX - 1.6 Km/effective block hour
UNIMAT - 75/90 min for each turnout
1 5 Any other specific Observation (not
covered above):

128
Safety Equipment

S. Description Quantity
N.
1 Detonators in a tin case 1 Box
2 H.S. flag red 2 Nos.
3 H.S. flag green 1 Nos.

4 H.S. Tri colour lamps (LED) 2 Nos.


5 Chain & Padlock 1 Set
6 Clamp with Padlock 2 Nos.

7 10 t jack ( CSM / UNIMAT ) 1 No.


8 20 t jack ( Tamping Express ) 1 No.
9 Crow bars 4 Nos.

10 Wooden blocks off sizes 8 Nos.


11 Gauge cum level 1 No.
12 Rail thermometer (dial type) 1 No.

13 Banner flag 2 Nos.


14 Portable Control Phone 1 No.
15 Walky Talky 2 Nos.

16 First Aid Box 1 No.


17 Skids 2 Nos.

129
S. Description Quantity
N.
18 Working time table of section where machine
1 Copy
working
19 G&SR book with upto date amendment slips 1 Copy

20 4 Cell Flasher Light / LED Torch, 6 Watt 1 No.


21 LED Petromax / Led Lamps 1 No.
22 Safety Helmets Machine
Staff
23 Protective Clothing, Safety Shoes and Safety Machine
Gloves Staff
24 Track Machine Manual (with updated C.S) 1 No.
25 Accident Manual (with updated C.S) 1 No.
26 Fire Extinguisher 1 No.

27 Hooter (Manual / Remote) 2 Nos.


28 Hydraulic Hand Pump 1 No.
29 Emergency pneumatic/Hydraulic hose of
sizes suiting to different machines(complete 1 No.
with end fittings)

130
G. Inspection for Ballast Screening Site (BCM Working)

S. Narration Observa- Reference


N. tions
1 a) Machine Type (BCM)
b) Machine No.
c) Base station/Division
d) Manufacturer
e) Year of manufacturing
f) Last major Maintenance schedule
POH/IOH RB’s
(POH/IOH)
Leeter No:
g) Month/Year of last IOH/POH 98/track/
III/TK/27-
h) Rated output of the machine (m/ Pt.
Hour) dated.20/
i) Name of SSE/TM/In-charge 05/2003.-
j) Name/designation of the operator
2 Availability of Camping coach? Yes/No
3 Is condition of the Camping Coach
Yes/No
satisfactory?
4 Has it been ensured that stabling
siding for machine’s coaches is having Yes/No Para 7.2 (i)
adequate water supply, power supply (IRTMM)
& resting facilities?
5 Has it been ensured that OHE Block is Yes/No Para 7.2 (vi)
taken or OHE is disconnected for (IRTMM)
maintenance of BCM in stabling
siding?
131
S. Narration Observa- Reference
N. tions
6 Has it been ensured that the gas cutting Yes/No Para 3.3.2
equipments is available on the machine? (xi) (IRTMM)
7 Are all safety equipment as per list Yes/No Checklist iss-
annexed available? ued by RDSO
Preliminary Works
8 Location of inspection
9 Availability of cushion (Total cushion Yes/No
shall not be less than 250 mm)
IRPWM Para
Clean cushion =
mm 238 (5)-
1 0 i) Month & Year of Last Deep Screening
ii) GMT passed after last deepscreening
1 1 Has all preliminary works including Yes/No Para 3.3.2
survey for marking of the longitudinal (i) & (ii)
levels for lifting and proper cross fall (IRTMM)
to avoid formation of water traps etc.
been ensured?
1 2 Has the final longitudinal levels as per Yes/No Para 3.3.2
redesigned profile been worked out & (iii)
marked on the pegs/OHE mast (IRTMM)
alongside the track?
1 3 Has it been ensured that adequate Yes/No
ballast is available on track for requisite
cushion and to avoid ballast deficiency
immediately after screening?
1 4 Has it been ensured that adequate
ballast is available on cess/depot for

132
S. Narration Observa- Reference
N. tions
supplementing the ballast for Yes/No Para 3.3.1
complete profile as per IRPWM? (iv) (IRTMM)
1 5 Are Sleeper fittings in good Condition Yes/No Para 3.3.2
and tightened? (x) (IRTMM)
16 Has all missing/broken fittings and Yes/No Para 3.3.2
Damaged/broken sleepers been (x) (IRTMM)
replaced?
17 Has it been ensured that entire ballast Yes/No Para 3.3.2
beyond the reach of cutter chain is (iv) (IRTMM)
transferred in its cutting width?
18 Has it been ensured that a trench of Yes/No
300mm depth & 1 meter width is
prepared lowering of cutter bar in
advance? Para 3.3.2
(xiii)
In case of screening of turnout, Yes/No (IRTMM)
whether requisite trench for
installation of extension pieces on right
side is prepared?
19 Has it been ensured that proper Yes/No Para 5.3.5
lighting arrangement are made for (viii)
night working on machine and/or OHE (IRTMM)
Mast?
20 Has it been ensured that there is no Yes/No Para 3.3.2
obstruction (including LWR pegs, creep (v) & (vii)
post, signal rodding/cables etc.) in the (IRTMM)
width of 4100mm to avoid
infringement to cutter chain?
133
S. Narration Observa- Reference
N. tions
21 Has it been ensured that L-Xing should Yes/No Para 3.3.2
be opened in advance so as to enable (ix)
machine to work? (IRTMM)

22 Has it been ensured that in OHE Yes/No Para 3.3.2


section distance of mast foundation (vi)
from track centre is accurately (IRTMM)
measured and checked for free
movement of cutting chain?
23 Has it been ensured that approaches Yes/No Para 3.3.2
to bridges which cannot be screened (viii)
by the machine screened manually in (IRTMM)
advance of the machine working?
24 Has it been ensured that all the Yes/No Para 3.3.2
obstruction i.e., rail pegs, broken PRCs, (v)
foundation etc. are removed in advance? (IRTMM)
25 Has it been ensured that Tamping
machine & DGS is available while Yes/No
doing deep screening by BCM?
26 LWR
i) Destressing temperature of LWR
ii) Last distressing date
iii Is the temporary de-stressing done Yes/No Para 3.1.2(x)
at higher/lower temperature?Temp td= °C (IRTMM)
iv) Likelihood of temperature Yes/No Para 6.2.1 (i)
exceeding td + 20°C (a) (LWR
Manual)
134
S. Item to be inspected Remarks Reference
N.
During Working of BCM
27 Location of work
i) Division
ii) ADEN
iii) SSE Section
28 Traffic block
i) Block section and lines blocked
ii) Timing and total Duration (minutes)
iii) Travel time to work spot (minutes)
iv) Actual working time (minutes)
v) Travel time to clear block (minutes)
vi) Total ineffective time (minutes) Rly. Bd.
Letter
(Max ineffective time = 60 minutes) No.98/
Track-iii/Tk/
27-pt dated
20-05-2003

29 i) Has it been ensured that proper Yes/No


protection of worksite done with
banner flag & detonators during block
to follow the lookout caution on Para 4.6.1
adjacent line? (IRTMM)
ii) Whether speed restriction on Yes/No
adjacent track has been imposed
while block working?
135
S. Item to be inspected Remarks Reference
N.
3 0 Has it been ensured that hooter in
Para 4.6.8 (i)
working condition is available at the Yes/No
(IRTMM)
BCM site and everybody is sensitized
to ensure safety?
3 1 Has it been ensured that a person on
either side of BCM/SBCM is nominated Yes/No Para 3.3.3 (ii)
and available to watch for any (IRTMM)
obstruction & stop machine
immediately?
3 2 Has all staff working with machine Yes/No Para 3.3.3
provided with helmets and masks? (vi) (IRTMM)

3 3 Has it been ensured that cutter chain is not Para 3.3.1


cutting/disturbing the formation and Yes/No
(i) (IRTMM)
necessary lifting of track done as required?
(If total cushion, less than 250 mm)
3 4 Are the S&T gears likely to infringe Yes/No Para 3.3.2(v)
cleared in case of Turnouts? (IRTMM)

3 5 Is the availability of S&T / Electrical Yes/No Para 3.3.2 (v)


Staff ensured? (If required) NA Para 7.2 (vi)
(IRTMM)
3 6 Is the Ramping of 1 in 1000 given Yes/No Para 3.1.3(vi)
before closing the day's work and (IRTMM)
obligatory points being done?
3 7 Has it been ensured that vertical and Yes/No Para 3.1.4(ii)
lateral clearances of OHE, signal post (IRTMM)
& any other structure is checked and
adjusted before clearing BCM block?

136
S. Item to be inspected Remarks Reference
N.
38 Has it been ensured that a round of
Yes/No Para 3.3.4(v)
tamping with DTS is carried out (IRTMM)
immediately after deepscreening to
resume trafficat aspeed of 40 Kmph?
Post BCM Working
39 Has all loose fittings been tightened? Yes/No Para 3.1.4 (i)
(IRTMM)
40 Has all broken fittings been replaced? Para 3.1.4
(ii) (IRTMM)
41 Has all check rails/guard rails been re-
fixed?
42 Has it been ensured that adequate
Para 3.3.4
ballast is trained out for complete Yes/No
(iii) (IRTMM)
ballast profile as per IRPWM and
profiling done?
43 BCM working – Has all S&T/OHE Yes/No Para 3.2.3
connections restored? (IRTMM)
44 Is the actual Output of the machine Yes/No Railway Board
matches with rated Progress of the Letter No.98/
Machine? Track-iii/Tk/27-
Pt dated 20-
(BCM - 0.2 Km/effective hour of working)
05-2003
45 Has it been ensured that watchman is
posted after the block or round the clock Yes/No Para 3.3.4
at the location while cutter bar & chain (iv) (IRTMM)
are left at site?
46 Any other specific observation (not
covered above):
137
Safety Equipment
S. Description Quantity
N.
1 Box
1 Detonators in a tin case
2 Nos.
2 H.S. flag red
1 Nos.
3 H.S. flag green
2 Nos.
4 H.S. Tri colour lamps (LED)
1 Set
5 Chain & Padlock
2 Nos.
6 Clamp with Padlock
1 No.
7 10 T jack
4 Nos.
8 Crow bars
8 Nos.
9 Wooden blocks off sizes
1 No.
10 Gauge cum level
1 No.
11 Rail thermometer (dial type)
2 Nos.
12 Banner flag
1 No.
13 Portable Control Phone
2 Nos.
14 Walky Talky
1 No.
15 First Aid Box
2 Nos.
16 Skids
138
S. Description Quantity
N.

17 Working time table of section where


1 Copy
machine working
1 Copy
18 G&SR book with upto date
amendment slips
1 No.
19 4 Cell Flasher Light / LED Torch, 6 Watt
1 No.
20 LED Petromax / Led Lamps
Machine Staff
21 Safety Helmets
Machine Staff
22 Protective Clothing, Safety Shoes and
Safety Gloves

23 Track Machine Manual (with updated C.S) 1 No.

24 Accident Manual (with updated C.S) 1 No.

25 Fire Extinguisher 1 No.

26 Hooter (Manual / Remote) 2 Nos.

27 Hydraulic Hand Pump 1 No.

28 Emergency pneumatic/Hydraulic hose 1 No.


of sizes suiting to different machines
(complete with end fittings)

139
Checklist for Machine Operator for Safe Operation of Track Machine

S. Item Check Reference


N.
A. Personal
1 Is valid Track Machine competency Para 4.3.2
Yes/No
certificate issued by Dy.CE/Machine (IRTMM)
available with operator?
2 4 Are all safety equipment as Yes/No Para 4.3.1
indicated in IRTMM available? (IRTMM)
3 Is Operator Carrying Extra pair of Yes/No Para 4.3
spactacles, if wearing? NA (IRTMM)

4. Are all safety equipment as indicated Para 4.4.1


in IRTMM available? Yes/No
(IRTMM)
5 Is Operator conversant with the Yes/No GR
system of working and having route 3.78
learning of the section?
6 Is the machine staff self-declared that Yes/No
liquor / intoxication not taken by him
prior to reporting ON Duty? -
7 Is the machine equipped with Para 4.4.2
prescribed head & tail light, LV board, Yes/No
(IRTMM)
marker light and flasher light?
8 Is the machine equipped with Para 4.4.3
prescribed equipment in working Yes/No
(IRTMM)
condition as per IRTMM?

140
S. Item to be inspected Remarks Reference
N.
B. Yard
1 Is Track Machine stabled clear of Yes/No Para 4.6.5
fouling mark, sand traps and not (IRTMM)
obstructing adjacent line(s)?
2 Are necessary precaution taken Yes/No Para 4.5.1(i)
against rolling down such as pinning (IRTMM)
down hand brakes, chaining and
provision of skids and temporary
buffers?
3 Are concerned points set against the Yes/No Para 4.6.6
line on which track machine(s) is (IRTMM)
stabled and such points are secured
with clamps or cotter bolts and
padlocks?
4 Is brake feel test conducted before Yes/No GR 4.31
proceeding from siding?
5 Is the shunting order issued by on duty Yes/No Para 4.5.1
SM to move the machine in running line (ii)(IRTMM)
to/from the siding/stabling line?
6 Is shunting staff with proper shunting Yes/No GR 5.13
order available during shunting?
7 Is track machine having proper Yes/No Para 4.5.1
authority to proceed? (iii)(IRTMM)
8 Is special caution order issued by SM Yes/No Para 4.5.1
duly signed by JE/SE (P.Way) and (IRTMM)
Operator?

141
S. Item to be inspected Remarks Reference
N.
9 Is authority issued to work all Yes/No GR0 4.65
machines working in convoy as per
Subsidiary Rule of Railway?
10 Is facing point locked by clamp for Yes/No Para 4.6.6
movement of machines? (IRTMM)
C. Block Section Working.
1 Is proper line block taken for working Yes/No Para 4.5.1
the Track Machine indicating number (IRTMM)
of machines to work duly endorsed by
SM with special instruction to proceed,
work and return via right or wrong
direction?
2 Is the adjacent line also blocked (and Yes/No Para 4.6.2
permitted by control and SM) in case of (IRTMM)
some BRM, T-28 etc. likely to foul
adjacent line(s).
3 Is SE (P.Way) available on machine for Yes/No Para 4.2.2
working in block section? (IRTMM)
4 Are all restriction followed as detail Yes/No GR 4.09
given in caution order?
5 Is continuous whistling being done Yes/No Para 4.6.4
approaching to L-Xing? (IRTMM)
6 Is safe distance of 120m between the Yes/No Para 4.6.4
machines moving in convoy (IRTMM)
maintained?

142
S. Item to be inspected Remarks Reference
N.
7 Is the machine moving cautiously at Yes/No GR 9.07(5)
very low speed which shall under no
circumstances exceed 10 kmph in foggy
weather / poor visibility/dust storm
etc.?
8 Is minimum 120 meter distance kept Yes/No Para 4.6.4
machine to machine while travelling & (IRTMM)
50 meter while working?
9. Is protection of work site in block Yes/No Para 4.6.1
section and also for adjoining track(s), & 4.6.2
in case of infringement, carried out by (IRTMM)
SE/JE (P.Way)?
10 Is temporary whistle board is provided Yes/No Para 4.6.8
by SE/JE/P.Way on adjoining track at (ii)(IRTMM)
Track Machine work site?
11 Are hooter available with the track Yes/No Para 4.6.8
machine deployed at site? (i)(IRTMM)

12 Are all trains passing adjoining track Yes/No Para 4.6.8


issued a caution order to "OBSERVE (iii)(IRTMM)
HAND SIGNAL, WHISTLE FREELY AND
STOP IF REQUIRED"
13 Is PTW issued by OHE supervisor for Yes/No Para 3.6.2
working of machine in electrified area? (IRTMM)
14 Are all physical locking of working unit Yes/No As per
of machines checked after availing RDSO’s
block? inspection
checklist
143
S. Item to be inspected Remarks Reference
N.
1 5 Has it been ensured that the Yes/No Para 4.6.8
clearances (vertical and lateral) for (iv)
OHE, Signal Post and any other (IRTMM)
structure are checked and there is no
infringement to SOD before clearing the
block?
1 6 Is the track certified fit and cleared for Yes/No Para 4.5.2
normal train operations subject to (IRTMM)
observation of speed restrictions?
1 7 Did JE/SE (P.Way) travel on last machine Yes/No Para 4.5.2
in work & proceed mode & first & Para
machine in work & return mode? 4.5.3
(IRTMM)
1 8 Sanction of CRS for working of the track Yes/No Para 3.1.1
machine (ii) (IRTMM)
NOTE:-
1 Please refer to GR 4.65, and subsidiary rules thereunder for
working of Track Maintenance Machines
2 Any other safety rule not covered above, shall also be followed
by the machine operator in letter and spirit.

144
Maintenance Instructions & Guidelines for
Different On-Track Machines.
Report is also available at: http://www.rdso.indianrailways.gov.in/
view_section.jsp?lang=0&id=0,2,465,610,1073

S. Name of Document Issue Report


N. Machine Date No.
1 Ballast Inspection Check List Nov.2004 TM-73
Cleaning Maintenance Jan.2005 TM-77
Machine Schedule
(BCM-RM-80)
Trouble-Shooting Jan.2002 TM-42
Manual
2 Ballast Inspection Check List Feb.2006 TM-96
Regulating Maintenance Jun.2005 TM-87
Machine Schedule
(BRM-
Kershaw) Trouble-Shooting Jul.2004 TM-70
Manual (English)
Trouble-Shooting Jul.2004 TM-70
Manual(Hindi)

3 Ballast Inspection Check List Feb.2011 TM-156


Regulating Maintenance
Machine (PBR- Schedule Dec.2010 TM-153
400R)
4 Continuous Inspection Check List Oct-14 TM-74 Rev.-1
Tamping
Machine (CSM Maintenance Jul.2004 TM-69
09-32) Schedule (English)
Maintenance Jul.2004 TM-69
Schedule (Hindi)

145
S. Name of Document Issue Report
N. Machine Date No.
Trouble-Shooting Mar.2004 TM-62
Manual
List of Critical Spare Jul.2012 CSP
Parts(Rev.01)
5 Dynamic Inspection Check List Oct.2005 TM-92
Track Maintenance Aug.2005 TM-90
Stabilizer(DGS- Schedule
Plasser-62N)
Trouble-Shooting Sept.2010 TM-148
Manual
List of Critical Spare Aug.2004 CSP
Parts
6 Shoulder Inspection Check List Sept.2005 TM-91
Ballast Maintenance
Cleaning Feb.2005 TM-79
Schedule
Machine(FRM-
80) Critical Spare Part Dec. 2014 CSP
list of Shoulder
Ballast Cleaning
Machine (FRM-80)
7 Shoulder Inspection Check List Dec.2009 TM-136
Ballast Maintenance Nov.2008 TM-125
Cleaning Schedule
Machine
(FRM-85F)
8 Multipurpose Inspection Check List Dec.2006 TM-105
Track Tamping Maintenance Jun.2006 TM-100
Machine Schedule
(UNIMAT
Compact-M) List of Critical Spare Parts Aug.2004 CSP
146
S. Name of Document Issue Report
N. Machine Date No.
9 Plasser Quick Inspection Check List Mar.2015 TM-108 Rev.-1
Relaying Maintenance Mar.2015 TM-101
System Schedule Revision-1
(PQRS)
Trouble-Shooting Feb.2009 TM-128
Manual
List of Critical Spare Aug.2004 CSP
Parts
1 0 Point And Inspection Check List Sept.2006 TM-103
Crossing Maintenance Aug.2006 TM-102
Changing Schedule
Machine
(AMECA T-28) Trouble-Shooting Mar.2007 TM-110
Manual
List of Critical Spare Aug.2004 CSP
Parts
1 1 Tamping Inspection Check List Dec. 2014 TM-106 Rev.-1
Express Maintenance May.2005 TM-85
(09-3X) Schedule
List of Critical Spare Jul.2012 CSP
Parts (Rev.01)
1 2 Track Inspection Check List Jul.2011 TM-160
Relaying Maintenance Jul.2011 TM-159
Equipment Schedule
(TLE-SIMPLEX)
Trouble-Shooting Feb.2009 TM-128
Manual
1 3 Track Inspection Check List Feb.2007 TM-107
Relaying Maintenance Oct.2006 TM-104
Train (TRT) Schedule
147
S. Name of Document Issue Report
N. Machine Date No.
Critical Spares Parts Dec. 2014 CSP
list of Track Relaying
Train
1 4 Point & Inspection Check List Sept.2004 TM-71
Crossing Maintenance Jun.2013 TM-175
Tamping Schedule
Machine Mar.2006
Trouble-Shooting TM-99
(UNIMAT)
Manual
List of Critical Spare Aug.2004 CSP
Parts
1 5 Unomatic Tie Inspection Check List Dec.2004 TM-76
Tamping Maintenance May.2005 TM-83
Machine Schedule
Trouble-Shooting Jul.2005 TM-88
Manual
1 6 Utility Track Inspection Check List Jun.2009 TM-132
Vehicle Maintenance Jun.2008 TM-121
(Phooltas Schedule
Make)
Critical Spares Parts Jul.2014 CSP
1 7 Worksite Inspection Check List Aug.2010 TM-144
Tamping Maintenance Jun.2010 TM-141
Machine Schedule
(METEX Make)
1 8 Worksite Inspection Check List Mar.2009 TM-129
Tamping Maintenance Mar.2009 TM-130
Machine Schedule
(8049
148
S. Name of Document Issue Report
N. Machine Date No.
Onwards) Trouble-Shooting Feb.2008 TM-117
Manual
List of Critical Spare 2013-14 CSP
Parts
1 9 UNIMAT-4S Maintenance May-12 TM-168
Schedule
Inspection Check List Dec. 2014 TM-169Rev.1
Critical Spares Part Apr-15 CSP
list of Unimat-4S
2 0 Rail Grinding Maintenance Jan. 2014 TM-180
Machine Schedule
2 1 Ballast Maintenance Feb. 2014 TM -178
Cleaning Schedule
Machine List of Critical Spare Nov.2013 CSP
(BCM-RM-80- Parts
92U)
Inspection Check List Mar- 2015 TM-186
2 2 Worksite Inspection Check List Mar-15 TM-183
Tamping Maintenance Mar-15 TM-187
MachineVPR- Schedule
02M
(Kalugaputmash
Make)
2 3 Inspection INSPECTION OF Aug-15 TM-184
Check List UNIMAT-SPLIT HEAD
MFI

149
H. Check list for Inspection of Concrete Sleeper Plant:

Ref: IRS-T-39 August 2011, IRS-T-45- 1996 and Schedule of Technical


Requirement (STR) issued by Rly. Bd. Vide letter no. 2010/Track-II/22/
11/4 (STR) dtd 27-5-2011

S. Item Remark
N.
A About Plant
1 Whether plant is approved for production? Yes/No
2 Whether plant is approved for production of 1 in 8.5 Yes/No
T/out sleepers?
3 Whether plant is approved for production of 1 in 12 Yes/No
T/out sleepers?
4 Whether plant is approved for production of any Yes/No
other type of sleepers?
B Quality Assurance Plan & ISO Certification
5 Whether QAP is approved by RDSO? Yes/No
6 Whether Plant is having ISO: 9001-2008? Yes/No
C About Organisation
7 Whether plant is having at least one Graduate Civil Yes/No
Engineer?
8 Whether plant is having at least one Diploma Civil Yes/No
Engineer for each shift per casting shed?
9 Whether plant is having one Mechanical/Electrical Yes/No
diploma Engineer for maintenance of equipments?

150
S. Item Remark
N.
D Layout Requirement
1 0 Whether Cement godown capacity is as per STR? Yes/No
(Minimum covered area 576 Sqm.)
1 1 Whether HTS storage capacity is as per STR? Yes/No

(Minimum covered area 100 Sqm.)


1 2 Whether Insert godown capacity is as per STR? Yes/No
(Minimum covered area 100 Sqm)
1 3 Whether Steam curing chambers numbers and Yes/No
capacity are as per STR?
1 4 Whether Submerged water curing tank numbers and Yes/No
capacity are as per STR?
1 5 Whether Stacking area for finished sleepers is as per Yes/No
STR?
1 6 Is Area of Laboratory is as per STR? (General- 40 Sqm. Yes/No
& sleeper testing-30 Sqm.)
1 7 Whether Lab is climate controlled? Yes/No

1 8 For inspection of turnout sleeper set- Whether Yes/No


minimum two platforms of 70 x 6m with gantry
arrangements for handling of inspection of two sets
at a time is available?
1 9 Minimum requirements of Plant and Machinery as Yes/No

151
S. Item Remark
N.
per STR for production line are available or not? Yes/No

2 0 Whether Laboratory equipments are available as Yes/No


per STR?
E Raw Material Details :
E1 Cement
2 1 Whether current cement source is approved by Yes/No
RDSO?
Name of Supplier:___________________.
2 2 Whether stacking of cement is as per IS code? Yes/No

2 3 Whether placards are displaying week number, Yes/No


name of manufacturer?
24 Whether cement is being used on “first in first out” Yes/No
basis?
2 5 Whether manufacture’s test certificate is available? Yes/No

E2 HTS Wire
2 6 Whether HTS wire is procured from BIS approved Yes/No
source?
2 7 Whether HTS wire is inspected by railway’s Yes/No
inspecting Authority?
2 8 Whether HTS wire coils are wrapped in Jute/plastic Yes/No
cloths?

152
S. Item Remark
N.
2 9 Whether Manufacture’s tag & seal of Inspecting Yes/No
Authority available on coils?
3 0 Whether HTS wire coils are stacked in covered Yes/No
godown?
E3 Aggregates (CA1 & CA2)
3 1 Whether source is approved by RDSO? Yes/No

E4 Inserts
3 2 Whether Inserts are being procured from RDSO Yes/No
approved source?
3 3 Whether Inserts are inspected by RITES with lead seal Yes/No
on every bag?
3 4 Whether dimensional checking of each & every Yes/No
inserts is done before use in Plant?
3 5 Whether Inserts are stacked in covered godown / Yes/No
heat no wise& supplier wise?
E5 PVC Dowel
3 6 Whether PVC Dowels are procured from RDSO Yes/No
approved source?
3 7 Whether PVC Dowels are inspected by RDSO? Yes/No
F Production Shed
3 8 Whether regular cleaning of mould’s by cup wired Yes/No

153
S. Item Remark
N.
brush is being done before use? Yes/No
3 9 Filling of black putty for sealing the gap between end Yes/No
plates & mould is being done properly or not?
4 0 Whether Greasing for inserts pockets in moulds is Yes/No
done?
4 1 Whether labours are doing hand pulling of HTS wire Yes/No
for removal of sag before tensioning?
4 2 Is Calibration of tensioning m/c as per schedule being Yes/No
done?
4 3 Whether Tensioning m/c is equipped with auto cut- Yes/No
off?
4 4 Whether tensioning supervisor is measuring the Yes/No
elongation of HTS wire of each & every bench and
entering it in register regularly?
4 5 Whether Calibration of bottom vibrators as per
Yes/No
schedule is done?
4 6 Whether Calibration of automatic batching plant as Yes/No
per schedule is done?
4 7 Whether Pouring of cement in mixture is through Yes/No
screw conveyor?
48 Whether calibration of thermometers of steam

154
S. Item Remark
N.
chambers as per schedule being carried out? Yes/No
4 9 Whether Keeping & maintaining half hourly record Yes/No
of temperature of each & every chambers by
supervisor, as per steam cycle?
5 0 De-tensioning of benches after required release Yes/No
strength is done or not?
5 1 Whether Paint marking of batch no and date of Yes/No
casting on every demoulded sleeper is done?
5 2 Whether end painting of every demoulded sleeper Yes/No
before submerged for curing is done?
5 3 Whether casted sleeper in submerged water curing Yes/No
tanks are kept in layer wise just after demoulding?
5 4 Whether stacking of sleepers is batch wise & type Yes/No
wise (not more than 25 layers in each stack) in
stacking yard?
5 5 2nd coat end painting of sleepers after submerged Yes/No
water curing
5 6 Is Critical dimensional checking of sleepers done Yes/No
completely? (100 %)
5 7 Is 10% General dimensional checking of sleepers Yes/No
done?

155
S. Item Remark
N.
5 8 FTC checking of sleepers done or not? Yes/No

G Record Keeping & Documentation


5 9 Whether Lab tests of raw materials are being done? Yes/No
6 0 Whether Production registers maintained properly? Yes/No

6 1 Whether Inspection certificates of raw materials Yes/No


available?
6 2 Whether Steam curing records available? Yes/No
6 3 Whether Dimensional checking register of sleepers Yes/No
updated?
6 4 Whether Dimensional checking of moulds & benches. Yes/No
Its repair register is maintained properly?
6 5 Whether Calibration of Machines, pressure gauges Yes/No
& Proving rings is done?
6 6 SBT testing of sleepers, 15days water cured cubes Yes/No
and released cubes register is maintained upto date?
6 7 Whether Statistical analysis report register is Yes/No
available?

156
I. CHECK LIST FOR BRIDGE & TUNNEL:

S. Description Remarks Reference


N.
1 Whether the bridge is Minor Yes/No IRBM-1103
(Individual span < 12 m & Total Linear (3) (c)
Waterway < 18 m)? Span=………m
2 Whether the bridge is Major Yes/No IRBM-1103
(Individual span >12 m or Total Linear (3) (b)
Waterway > 18 m)?
Span=………m
3 Whether the bridge is Important Yes/No IRBM-1103
bridge (Total Linear waterway 300 m (3) (a)
OR Total Waterway 1000 m2 OR those
classified as "IMPORTANT BY CE/CBE")?
Span=………m
4 Whether the date of Inspection is Yes/No IRBM-203 (1)
indicated on the bridge?
If so, what is Last date of Inspection?
Date=…………
5 Whether the date of Painting is Yes/No IRBM-203 (1)
indicated on the bridge? If so, what
is Last date of Painting? Date →
6 Whether the date of Cleaning &
Greasing is indicated on the bridge? Yes/No IRBM-1107
If so, what is Last date of Cleaning & (4) (v)
Greasing? Date →

157
S. Description Remarks Reference
N.
7 Whether the date of lubrication of Yes/No IRBM-1107
bearing is indicated on the bridge? (4) (v)
If so, Last date of lubrication done?
Date=…………
8 Whether bridge / FOB is over railway track,
Yes/No SOD CH-
whether clearances are as per SOD?
1(10) (iii)
If so, what is the vertical clearance IRBM-1107
(5870 mm / 6350 mm)? (14) (a) (ii)

Vertical clearance=……………………
9 What is the clear horizontal distance
between respective centre of track and SOD CH-1 (8)
any other structure (limiting value
2135 mm)?
10 Whether Trolley refuge is provided? Yes/No IRBM- 1107
(8)
If so, Nos. required ______________ and
Nos. provided ____________.
11 Whether creep of bridge girder is Yes/No ------
notice?
12 Whether condition of the footpath is Yes/No IRBM-1107
good? (9)
13 Whether condition of drainage
Yes/No IRBM-210
arrangement is good? (2)
14 Whether the Camber has been
recorded at the time of Inspection? Yes/No IRBM-212

158
S. Description Remarks Reference
N.
If so, What is the method of recording IRBM-1107
Camber? (15) (b)
What is the Camber
a) As per Drawing? .....mm
b) As per time of Last inspection? .....mm
c) At the time of Present Inspection? .....mm
15 Whether the bridge is to be inspected Yes/No
at increased frequency? IRBM-107
If so, What is the frequency? (1)

16 Whether the entries are made in Yes/No IRBM-107


Bridge history Book? (2)

17 Whether the Steel members are free Yes/No IRBM-1107


(5)(c)
from distortion?
18 Whether the Steel members are free Yes/No IRBM-216
from Corrosion?
19 Percentage of Defective, Broken,
Loose, Corroded & Badly Driven rivets
a) Boom Flanges .....%
b) Web .....%
c) Main Joints .....%

d) Cross Girders .....%

159
S. Description Remarks Reference
N.
e) Stringers .....% IRBM-215
(3)
f) Bracing& Foot Path .....%
g) Base Plate .....%
2 0 Whether any member of steel girder IRBM-212
Yes/No
is overstressed? (As advised by CBE) (a)

2 1 Whether steel members are free from Yes/No IRBM-213


cracks? (1)

2 2 Whether Early steel girder floor Yes/No IRBM-107


system is inspected once in a year? (1) (c),

If so, what is the Last inspection 1102-(1) (e)


date? →
2 3 Whether Welded girder is inspected
once in a three years? Yes/No IRBM-1102-
(1) b
If so,what is the last inspection date? →
2 4 Whether proper scraping done
wherever required? Yes/No IRBM-217-
(1) b
2 5 Whether there is any local or uniform
Yes/No IRBM-216-
corrosion over large area? (3) (i)
2 6 Whether some pitting/corrosion is
Yes/No IRBM-216-
formed? (3) (ii),
If so, Location of Pitting/ corrosion? 1107 (5) (f)
(xvii)
2 7 Whether the average thickness of IRBM-218-
Yes/No
paint film is as per following (1) (ii) (b)

160
S. Description Remarks Reference
N.
requirement? IRBM-218-
(2) (ii)
a) Metalising (150 Micron)
b) Epoxy Painting (200 Micron)
28 Whether the Painting has been done Yes/No IRBM-217-
as per schedule (1 to 6 years)? (5)
If so, What is the last date of Painting? -----------
29 Whether all Holding Down (HD) Bolts Yes/No IRBM-1107-
are intact? (4)(ii)
What is the percentage of intact bolts
per bearing? ------%

30 Whether locking strips and guide strips Yes/No ------


are in good condition?
31 Whether bearing strip butts with Yes/No ------
locking strip?
32 Whether schedule of greasing (once in Yes/No
3 years) of bearings has been carried IRBM-222-
out? (2) (a)

Date of greasing…………….
33 Whether there are any cracks in Yes/No BS-102-
Knuckle slab, Saddle Plate and Roller? (3.2.3.1)
34 Whether bearing is centralized? Yes/No ------

35 Whether replacement of oil in oil bath Yes/No IRBM-222-


bearing is done? (once in 5 yrs) (2) (f)

161
S. Description Remarks Reference
N.
Date of oil replacement…………….
36 Whether connection of saddle plate Yes/No ------
with bottom boom is intact?
37 Whether condition of elastomeric Yes/No BS-102-
bearing is examined? (3.5.3)
If so, than
a) Is shear deformation more than Yes/No
50% of height of pads?
b) Is compression more than 5% of the Yes/No
height of Pads?
c) While in rotation any loss of contact Yes/No
between bearing and girder?
38 Whether any tilting/settlement is Yes/No IRBM-1107
reflected in cracks in substructure? (1) (a) (ii)

39 Whether there is any unusual scour Yes/No IRBM-


around the piers? 1107(1) (a) (i)
40 Whether water way is free from Yes/No IRBM-117(1)
obstruction? (f) IRBM-
1107(3)(ii)
41 Whether flooring, drop wall & curtain Yes/No IRBM-
wall are provided? 1107(1) (b)
What is the condition of componenet?
42 Whether (for foundation perennially IRBM-
Yes/No 1107(2) (d)
underwater) underwater inspection

162
S. Description Remarks Reference
N.
done? Yes/No
Date of inspection--_______________
43 Whether the Pitching of Guide bund/ Yes/No IRBM-809 (4)
groins is intact? (a)IRBM-
1107(3) (a)

44 Whether there is any erosion of bank Yes/No IRBM-1107


in the vicinity of abutment? (1)(a)

45 Whether there is any displaced / crack Yes/No IRBM-(221)


in bed block? (514)

46 Whether any bed block is shaken? Yes/No IRBM-1107


(4/a/iii)
47 Whether there is any crushing mark Yes/No
under bed plate?
48 Whether any inspection platform is Yes/No IRBM-
available? 1107(1) (a)
49 Whether there is any crack in masonry? Yes/No IRBM-1107-
(2) (a)
50 If yes, whether the crack is progressive? Yes/No
IRBM-1107-
51 Whether there is any weathering and Yes/No (2)
leaching of mortar?
52 Whether there is any vegetation Yes/No
growth in masonry?
53 Whether there is any crack in Yes/No
abutment face?

163
S. Description Remarks Reference
N.
54 Whether backfill materials are intact Yes/No
in case of horizontal crack on abutment
face?
55 Whether any bulging/tilting is noticed Yes/No IRBM-1107-
in ballast wall on abutment? (2)
56 Whether there is Highest Flood Level Yes/No IRBM-1107-
(HFL) with year & Danger Level (D L) (10) & 203
marking in abutments and gauge (2 & 3)
marking on shore piers on important
bridges?
57 Whether bridge tablet is showing Yes/No IRBM-
direction of flow, Bridge Number, span 1107(10) d,
arrangement, Rail level etc. has been f, h & 203 (2
provided? to 9)
58 Whether ballast retainer is leaning? Yes/No ------
59 Whether cracks in Arch Barrel with Yes/No IRBM-208-
special reference to its direction of (1) (i)
propagation & length of the crack IRBM-
observed? 1107(2) (e)
60 Whether any cracks in the intrados are Yes/No IRBM-208-
observed to be propagating in (1) (ii)
transverse direction i.e. direction IRBM-
perpendicular to traffic? 1107(2) (e)
61 Whether immediate rehabilitation Yes/No IRBM-209
measures for repair of cracks in the IRBM-
intrados planned & such cracks have 1107(2) (e)
been kept under close observation?
164
S. Description Remarks Reference
N.
62 Whether crushing of masonry of Arch, Yes/No IRBM-208-
loosening of Key stone etc. noticed? (1), (iv).IRBM-
1107(2) (e)
(viii)

63 Whether any leaning of Parapet wall Yes/No IRBM-208-


noticed and weep holes in Parapet wall (3)
are cleared? IRBM-1107
(2) (e) (xi)

64 Whether any tell-tale marks of repairs Yes/No IRBM-1107


earlier conducted? (2) (c)

65 Whether there are any loose boulders Yes/No IRBM-1007


at tunnel approaches & cutting and (2)
major discontinuities? IRBM-1012
66 Whether any weep holes are choked Yes/No IRBM-1008
in retaining walls and side drains? (1.4)
IRBM-1012
67 Whether any tree is precariously Yes/No IRBM-1007
standing on the top of approach cutting (2) & para
and slopes? 1012 (5)

68 Are catch water drains on the Yes/No IRBM-1007


approaches and on the top of tunnel (2)
cleaned?
69 Whether any portal has cracks in the Yes/No IRBM-1007
masonry or has shaken bulging (2)
masonry?

165
S. Description Remarks Reference
N.
70 Whether there are any loose boulders Yes/No IRBM-1007
in tunnel wall and roofing? (4, 2)

71 Whether there is any seepage inside Yes/No IRBM-1007


tunnel through rock joints in tunnel (4)
wall and roof noticed?
72 Whether side drain and drainage inside Yes/No IRBM-1007
the tunnel is clean? (5, 6, 7)
Whether ventilation shafts and adits, Yes/No
are free from vegetation?
Whether there is any water logged area Yes/No
near heavy seepage zone of tunnel?
73 Whether all fittings of steel sleepers Yes/No IRBM-1007
and rails particularly in heavy seepage (9)
zone are intact?
74 Whether any infringements in moving Yes/No IRBM-1007
dimension are noticed? (3)

75 Whether tablets on top of tunnel at Yes/No IRBM-1003


entrance indicating length, year of
construction and other information
are available?
76 Are water-ways clear at the bridge? Yes/No IRPWM-723 (2)
77 Whether SWR is continued over bridge Yes/No IRPWM Para
(span< 13.1 m), what is actual span? 272 (4)

78 Is any fish plate joint is on bridge or Yes/No


within 6 M. of abutment? (None
allowed)
166
S. Description Remarks Reference
N.
7 9 For 26 m long rolled rails, whether 1 m Yes/No C/slip No.
long fish plates with 6 bolts are 125 & Para
provided. 272(4/a) of
IRPWM
8 0 Whether permissible gaps at joints (as Yes/No IRPWM Para
per Zone and temperature range) are 510(3)
given?

8 1 Is there any creep at joints noticed? If IRPWM Para


yes, No.272 (6)
LH side .....mm

RH side .....mm

8 2 Whether at approach two well Yes/No Para No.


anchored standard rail lengths are 272 (6) of
provided? IRPWM
8 3 Whether LWR is continuing on the Yes/No Para No.
bridge (span ≤ 20 m, 20 m to 43 m, >43 272 (5) of
m), what is actual span? IRPWM
8 4 a) Whether rail free fastenings are Yes/No
provided from pier to pier with SEJ?
Yes/No
b) Whether SEJ is provided at the far
end of the bridge?
8 5 Whether all the provisions of LWR Yes/No
manual were followed in continuing
LWR on the bridge?

167
S. Description Remarks Reference
N.
8 6 C/C spacing between sleepers (450 Yes/No C/slip No.
mm), what is actual value? 102 & para
273 (B/iii) of
IRPWM
8 7 Clear spacing between sleepers. ......mm
8 8 Whether guard rail are provided on Yes/No IRPWM Para
girder bridges? no.275
8 9 Clearance between guard rail and -----mm
running rail?
(250+50/ 250-50 mm)
9 0 Straight length of guard rail beyond the -----mm
span L1 (1875 mm)? IRPWM Para
no.275/2
9 1 Length of flared portion of guard rail L2 -----mm
(4875 mm)?
9 2 How much below is the top table of -----mm
guard rail from top of running rail (< 25
mm)?
9 3 Whether the ends of guard rails are Yes/No
vertically bent and buried and block of
timber is provided
9 4 Whether pathway has been provided Yes/No IRPWM C/
at the centre of the track with slip No. 102
chequered plates?
9 5 Whether all AT welds on bridge as well Yes/No C/slip No.
as on approaches of 100 M of both ends 131 of
IRPWM
168
S. Description Remarks Reference
N.
are provided with joggled fish plates
and clamps or with fish bolts at two far
end bolts?
9 6 Whether trolley refuses are provided? Yes/No CS No. 119 of
(at every 100 m or on every pier) IRPWM
9 7 Whether track Parameters like gauge, Yes/No IRBM-1107-
cross level, cant, versines are within limits? (7) (g) (i)
9 8 Whether condition of track fittings and
their tightness, particularly rubber
pads in case of steel channel sleeper Yes/No ------
are good?
9 9 Whether guard rail are bent down in IRBM-1107-
Yes/No
the ballast at approach? (e) iii
100 Whether tightness and correct osition IRBM-1107-
of lips of hook bolts checked by actually Yes/No (c)
touching with hand?
101 Whether steps are provided for
Yes/No ------
inspection of bridge?
102 Whether anti sabotage/theft fittings
Yes/No ------
are provided on the bridge?
103 Whether zero toe load track fastening
(rail free fastening) of LWR on bridge ------
Yes/No
and box anchoring of 2 to 4 sleepers in
the Centre of girders are provided as
per LWR manual?
104 Whether arrow mark of hook bolts is
aiming towards c/l of track? Yes/No
Percentage of hook bolts not holding
flange of girder--_______ .
169
J. ITEMS PERTAINIG TO PASSAENGERS AMMINITIES
A. ADARSH STATION.

Ref: Commercial circular no 50 of 2013 circulated vide Rly Bd.’s Letter


no. 2009/TG-IV/10/PA/Adarsh Stns dated. 13-08-2013.

1. FACILITIES AT ADARSH STATIONS (‘A1, A, B & C’ CATEGORY)

S. Item to be Inspected REMARK


N.
1 Whether improvements in facade of station building Yes/No
are done?
2 Whether retiring room available? (Except ‘C’ Yes/No
category, for ‘B’ category GM can sanction based on
need & demand)
3 Whether waiting room (with bathing facility) Yes/No
available for upper class with TV? ( Except ‘B’ & ‘C’
category)
4 Whether waiting room (with bathing facility)
Yes/No
available for other classes with TV? ( Except ‘C’
category)
5 Whether separate ladies waiting room (with bathing Yes/No
facility) available? (Except ‘B & C’ category)
6 Whether cloak room available? (Except ‘C’ category, Yes/No
for ‘B’ category GM can sanction based on need &
demand)
7 Whether computer based public address system is Yes/No
available?

170
S. Item to be Inspected REMARK
N.
8 Whether circulating area is available with Yes/No
necessary lighting?
(refer Table at Pg. no.186,187 for required
illumination level)
9 Whether landscaping and circulating area is Yes/No
available? (If space is available)(Except ‘C’ category)
1 0 Whether earmarked parking is available? Yes/No
1 1 Whether prepaid taxi/radio taxi booth available? Yes/No
(Except ‘B & C’ category)
1 2 Whether electronic train indicator board/ plasma Yes/No
TV train indicator system is available?
1 3 Whether lifts/escalator (if feasible) is available? Yes/No
(Except ‘B’ & for ‘C’ category, GM can sanction based
on need & demand)
1 4 Whether standard signage are available? Yes/No

1 5 Whether ‘Pay & Use’ toilets are available in Yes/No


circulating area/ concourse area? (If not feasible,
departmental toilets are to be provided)
1 6 Whether ‘High level’ platforms are available? Yes/No

1 7 Whether air conditioned VIP lounge is available? Yes/No


(Only for ‘A1’ category)
1 8 Whether coach indicator board is available? (Only Yes/No
for ‘A1’ & ‘A’ category)

171
S. Item to be Inspected REMARK
N.
1 9 Whether FOB is available? (For ‘C’ category – Wider FOB) Yes/No

2 0 Whether ‘water coolers’ are available? Yes/No


2 1 Whether ‘PRS’ is available? ( Except ‘C’ category) Yes/No

2 2 Whether ‘UTS’ is available? Yes/No

2 3 Whether energy efficient, adequate lighting is Yes/No


available on platform. FOB, circulating and
concourse etc.? (Refer table at Pg. no.186,187 for
required illumination level)
2 4 Whether ‘Battery car’ is available? (Only for ‘A1’ Yes/No
category)
2 5 Whether ramp at entry to station for PH and Sr. Yes/No
citizens is available?
2 6 Whether separate parking for disabled person is Yes/No
available?
2 7 Whether ‘Non slippery’ walkway from parking lot to Yes/No
station building is available?
2 8 Whether toilet for PH is available? Yes/No

2 9 Whether ‘May I help you’ booth is available? Yes/No

3 0 Whether trolley path/end pathway for inter platform Yes/No


movement of wheel chair for PH is available?
3 1 Whether ‘Wheel chair’ is available? Yes/No

3 2 Whether mobile charging points are available? (If Yes/No


electric power is available).

172
2. FACILITIES AT ADARSH STATIONS (‘D & E’ CATEGORY)

S. Item to be Inspected REMARK


N.
1 Whether suitable face lift given to station building? Yes/No

2 Whether waiting room for other than upper classes


(without bathing facility) is available? (For ‘D’ Yes/No
category only and for ‘E’ category seating cluster/
enclosure on main platform)
3 Whether computer based public address system is Yes/No
available? (For ‘D’ category only)
4 Whether circulating area is available with necessary
lighting? (For ‘D’ category only)
Yes/No
(refer Table at Pg. no.186,187 for required
illumination level)
5 Whether landscaping and circulating area is Yes/No
available? (If space is available)
6 Whether earmarked parking is available? (For ‘D’ Yes/No
category only)
7 Whether standard signage are available? Yes/No

8 Whether ‘Pay & Use’ toilets are available in Yes/No


circulating area/ concourse area? (If not feasible,
deptt. toilets are to be provided)
9 Whether high level for category ‘D’ and medium level Yes/No
for category ‘E’ platforms are available?
1 0 Whether FOB is available? Yes/No

173
S. Item to be Inspected REMARK
N.
1 1 Whether ‘water coolers’ are available? Yes/No

1 2 Whether ‘UTS cum PRS’ is available? Yes/No


(for category ‘E’ GM can sanction based on need &
demand)
1 3 Whether energy efficient, adequate lighting is Yes/No
available on platform. FOB, circulating and
concourse etc.? (Refer table at Pg. no.186,187 for
required illumination level)
1 4 Whether ramp at entry to station for PH and Yes/No
Sr.citizens is available?
1 5 Whether separate parking for disabled person is Yes/No
available?(For ‘D’ category only)
1 6 Whether ‘Non slippery’ walkway from parking lot to Yes/No
station building is available? (For ‘D’ category only)
1 7 Whether trolley path/end pathway for inter platform Yes/No
movement of wheel chair for PH is available?
1 8 Whether ‘Wheel chair’ is available? Yes/No
1 9 Whether mobile charging points are available? Yes/No
(If electric power is available).

174
B. FACILITIES AT STATION NOMINATED AS MODEL STATION
1. For categories ‘A1, A & B’

Ref: Comprehensive instructions issued by Rly. Board vide letter no.


2012/LM (PA)/3/5 dated 11-09-2012.

S. Item to be Inspected REMARK


N.
1 Whether Retiring Rooms are provided? Yes/No

2 Whether Waiting Rooms with bathing facilities are Yes/No


provided?
a . Upper class (Except ‘B’ category) Yes/No
b. 2nd Class Yes/No
c. Separate For ladies (Combined upper & 2nd Class) Yes/No
(Except ‘B’ category)
3 Whether Cloak Room is provided? Yes/No
4 Whether enquiry & computer based announcement Yes/No
is provided?
5 Whether National Trains Enquiry System (NTES) is Yes/No
provided? (Except ‘B’ category)
6 Whether Interactive Voice Response System (IVRS) Yes/No
is provided?
7 Whether Public Address System is provided? Yes/No

8 Whether Book Stalls / other stalls of essential goods Yes/No


are provided?
9 Whether Refreshment Room is provided? Yes/No

175
S. Item to be Inspected REMARK
N.
1 0 Whether Parking / Circulatory Area is provided? Yes/No
(High mast with light is to be provided if feasible)
1 1 Whether washable apron with jet cleaning machines Yes/No
are provided?
1 2 Whether electronic train indicator boards are Yes/No
provided?
1 3 Whether touch screen enquiry system is provided? Yes/No
1 4 Whether watering vending machines are provided? Yes/No
(Optional for category ‘A & B’)
1 5 Whether FOB is provided? Yes/No
1 6 Whether escalator is provided? (Except category ‘B’) Yes/No
1 7 Whether travellator is provided? Yes/No
(Except category ‘B’)
(Subject to space available and feasibility)
1 8 Whether standardized signage are provided? Yes/No
1 9 Whether modular catering stalls are provided? Yes/No
2 0 Whether automatic vending machines are provided? Yes/No
(Optional for category ‘A & B’)
2 1 Whether pay & use toilets are provided on platforms Yes/No
and circulating area?
2 2 Whether cyber cafes are provided?
Yes/No
(Except category ‘A & B’, subject to space available
and feasibility)
176
S. Item to be Inspected REMARK
N.
2 3 Whether ATMs, preferably with ticketing facilities Yes/No
have been provided?
2 4 Whether at least one AC VIP/Executive lounge is Yes/No
provided? (Except category ‘A & B’)
2 5 Whether Food Plaza is provided? (Except category ‘A Yes/No
& B’)
2 6 Whether train coach indication system is provided?
Yes/No
(Except category ‘A & B’)
2 7 Whether Close Circuit Television (CCTV) for Yes/No
announcement and security purpose is provided?
(Except category ‘A & B’)
2 8 Whether coin operated ticket vending machines are Yes/No
provided?
2 9 Whether pre-paid taxi service facility is provided? Yes/No
(Only at category ‘A1’ with GM’s approval)
3 0 Whether high level platforms available? Yes/No

177
C. MINIMUM ESSENTIAL AMENITIES AT STATIONS OF
DIFFERENT CATEGORIES.

Ref: Comprehensive instructions issued by Rly. Board vide letter no.


2012/LM (PA)/3/5 dated 11-09-2012.

1. MINIMUM ESSENTIAL AMENITIES AT ‘A-I & A’ CATEGORY STATION

S. Facilities As per Norms Facilities


N. A1 A provided
1 Booking facility 15 10 Yes/No
(No. of counters)
(To operate round the
clock except if there
is no night working)
2 UTS As per norms Yes/No
3 Drinking water (on Yes/No
20 taps
each platform)
4 Waiting Hall 250 Sqm. 125 Sqm. Yes/No
(marginally lower up
to 5 Sqm allowed)

5 Seating arrangement 150 125 Yes/No


(No. of seats per
platform)

6 Platform shelter : 500 Sqm. 400 Sqm. Yes/No


on each platform
Urinals

178
S. Facilities As per Norms Facilities
N. A1 A provided
7 Urinals 12 nos 10 nos Yes/No
i. includes provision in waiting rooms/hall
ii. 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for ladies
and gents
iii. Includes ‘Pay & Use’ toilets also.
8 Latrines 12 nos 10 nos Yes/No
i. includes provision in waiting rooms/hall
ii. 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for ladies
and gents
iii. Includes ‘Pay & Use’ toilets also.
9 Foot Over Bridge Minimum one FOB Yes/No
(with cover, new FOB- per station
minimum width 6m)
1 0 Water Cooler Two on each platform Yes/No
1 1 Signage As per standard (Refer Yes/No
Railway Board’s circular No.
97/TG II/39/11/signage dated
11.03.99)

1 2 Platform All platforms should be of Yes/No


high level

179
S. Facilities As per Norms Facilities
N. A1 A provided
1 3 Ligting Refer Rly Bd.’s letter no. Yes/No
2004/Elec (G)/109/1 dated
18-05-2007 – Extract at Pg.
no.186,187
1 4 Fans One row of fans/Bay of COP Yes/No
for 6 to 9 m wide shed.
Two rows of fans/Bay of COP Yes/No
for shed wider than 9 m.

1 5 Time Table Display As per extent instructions Yes/No


1 6 Clock As decided by Zonal Rlys. Yes/No
1 7 Public address As per extent instructions Yes/No
system/ Computer
based announcements
1 8 Parking cum
circulatory area , As per extent instructions Yes/No
with lights
1 9 Electronic train As per extent instructions
Yes/No
indicator board At station entrance/
concourse, on foot over
bridge (At landing location)
and on platform at suitable
locations.

2 0 Public phone booth As per extent instructions Yes/No

180
2. MINIMUM ESSENTIAL AMENITIES AT ‘B, C & D’ CATEGORY
STATION
S. Facilities As per Norms Facilities
N. B C D provided
1 Booking facility - 6 4 4 Yes/No
(No. of Counters)
(To operate round the
clock except if there
is no night working)
2 UTS As per norms Yes/No

3 Drinking water (taps 20 nos 06 nos 08 nos Yes/No


on each platform)
4 Waiting Hall 75 Sqm NIL 30 Sqm. Yes/No
(marginally lower up
to 5 Sqm allowed)
5 Seating arrangement 100 10 50 Yes/No
(seats per platform)
6 Platform shelter (on 200 Sqm 200 Sqm 50 Sqm Yes/No
each platform)
7 Urinals 6 nos 4 nos 4 nos Yes/No
i. includes provision in waiting rooms / hall
ii. 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for
ladies and gents
iii. Includes ‘Pay & Use’ toilets also.

8 Ltrines(Nos) 6 2 4 Yes/No

181
S. Facilities As per Norms Facilities
N. B C D provided
i. includes provision in waiting rooms / hall
ii. 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for
ladies and gents
iii. Includes ‘Pay & Use’ toilets also.
9 Foot Over Bridge Minimum one FOB Yes/No
per station
1. New FOB-minimum width 6m.
2. For ‘D’ category FOB to be provided during
doubling/Gauge conversion for crossing
stations.
1 0 Water Cooler - on 02 02 01 Yes/No
each platform.
Ref: Rly Bd.’s letter
no. 69/Elect (g)/730/8
dt.30-03-1971.
1 1 Signage (Refer As per standerd Yes/No
Railway Board’s (Expect ‘C & D’ category)
circular No. 97/TG II/
39/11/signage dated
11.03.99)
1 2 Platform (Level) Medium High Medium Yes/No
1 3 Lighting Ref: Rly Bd.’s letter no. 2004/ Yes/No
Elect(G)/109/1 dated 18-05-
2007 , extract at page no.
186,187

182
S. Facilities As per Norms Facilities
N. B C D provided
14 Fans One row of fans/Bay of COP Yes/No
for 6 to 9 m wide shed.
Two rows of fans/Bay of COP Yes/No
for shed wider than 9 m.

15 Time Table Display As per extent instructions Yes/No

16 Clock As decided by Zonal Rlys. Yes/No


17 Public address As per extent instructions Yes/No
system/ Computer (Except ‘C & D’ category)
based
announcements

3. MINIMUM ESSENTIAL AMENITIES AT ‘E & F’ CATEGORY


STATION
S. Facilities As per Norms Facilities
N. provided
1 Booking facility – (No. 02 01 Yes/No
of counters)
To operate round the clock except if there is no night
working.
2 UTS As per norms NIL Yes/No
3 Drinking water- nos of 02 Appropriate
taps on each platform facility
Yes/No
If piped water is not available separate
arrangement of potable water as approved by GM,
to be made.
4 Waiting Hall 15 Sqm 10 Sqm Yes/No
183
S. Facilities As per Norms Facilities
N. B C D provided
5 Seating
arrangement (No of
seats per platform) 10 NIL Yes/No
6 Platform shelter 50 Sqm (Min.) Shady trees Yes/No
7 Urinals 1 no. NIL Yes/No
i. includes provision in waiting rooms / hall
ii 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for ladies
and gents
iii Includes ‘Pay & Use’ toilets also.

8 Latrines 1 Number NIL Yes/No


i. includes provision in waiting rooms / hall
ii 1/3rd to be reserved for ladies. In case of 2 toilets
existing, one each should be earmarked for ladies
and gents
iii Includes ‘Pay & Use’ toilets also.
9 Platform Rail level Yes/No

10 Lighting Ref: Rly Bd.’s letter no. 2004/ Yes/No


Elec (G)/109/1 dated 18-05-
2007, extract at Pg. no.186,187
11 Fans One row of fans/ NIL Yes/No
Bay of COP for 6
to 9 m wide
shed.
Two rows of NIL Yes/No
fans/Bay of COP
for shed wider
than 9 m.
184
S. Facilities As per Norms Facilities
N. B C D provided
12 Time Table Display As per extent instructions Yes/No

13 Clock As Decided by Zonal Rlys. Yes/No

Extract of Rly Bd.’s letter no. 2004/Elec (G)/109/1 dated


18-05-2007: Lighting arrangement at different areas:-
S. Location Lux
N level
1 Concourse 100
2 Circulating area 30
3 Waiting Hall 100
4 Retiring Room 100
5 Platform
a. Open 30
b. Covered 100
6 Enquiry cum Reservation office
a. General 100
b. Counter 150
7 Covered Passage way
a. Corridors 50
b. FOB 50
c. Stairs 50
185
S. Facilities As per Norms Facilities
N. B C D provided
8 Parcel/luggage office
a. General 100
b. Counter 150
9 Time table- using task lighting 200
10 Outdoor car parking 30
11 Restaurant area
a. Kitchen 150
b. Stores 100
c. Dining Hall 150
12 Other service buildings at station 200
13 Cloak Room
a. General 100
b. Counter- using task lighting 150
14 Public Utility Services - Toilet/ Bathroom 75

186
K. ITEMS PERTAINIG TO COLONY AND OTHER BUILDINGS
Ref: Rly Bd.’s letter no. 2014/LMB-II/1/1 dated 25-07-
2014 and 2014/LMB-II/1/1 (A) dated 25-07-2014.
(A) COLONY INSPECTION BY ‘COLONY INSPECTION GROUP
(CIG)’
1. General:
S. Particular Remarks
N.
1 Whether ‘CIG’ formulated as per latest Yes/No
instructions?
2 Whether ‘CIG’ inspection & meetings are held Yes/No
regularly once in THREE months?
3 Artisans training: Initial and refresher arranged Yes/No
regularly?
4 Whether modern tools & equipment are available Yes/No
with artisans?
5 Whether standard ‘Tool kit’ is available with Yes/No
artisans?
6 Whether ‘Valve’ operation is automised? Yes/No

7 Whether old quarters, planned for replacement has Yes/No


been inspected thoroughly and it has been ensured
that repair is not economical?

2. Items to be inspected by ‘COLONY INSPECTION GROUP (CIG)’:


S. Particular Remarks
N.
1 Whether Cleanliness of colony is upto mark? Yes/No

187
S. Particular Remarks
N.
2 Whether quarters are maintained in sound Yes/No
condition having structural integrity?
3 Whether leaky roofs are attended properly? Yes/No

4 Whether outside door & windows are maintained Yes/No


properly?
5 Whether water supply is maintained properly? Yes/No
6 Whether sanitation and drainage arrangements Yes/No
are maintained properly?
7 Whether repair to floors is done properly? Yes/No
8 Whether repairs to pathways is done properly? Yes/No
9 Whether repairs to fencing and other items is done Yes/No
properly?
1 0 Whether improvement of substandard quarters Yes/No
done?
1 1 Whether disposal of waste from colony is arranged Yes/No
properly?
1 2 Whether encroachment is prevented properly? Yes/No
1 3 Whether cattle nuisance is prevented properly? Yes/No
1 4 Whether subletting of quarters is checked & Yes/No
prevented properly?
1 5 Whether security arrangements for colony are Yes/No
proper?

188
(B) MAINTENANCE SCHEDULE FOR STAFF QTRS. AND COLONY:
1. Schedule for finishing items: For type II to V Qtrs.

S. Particular Remarks
N.
1 Whether exterior colour washing & Interior white Yes/No
washing including ceiling done once in a year?
2 Whether white washing of Kitchen & pantry done Yes/No
once in a year?
3 Whether painting with plaster paint, synthetic Yes/No
enamel, Oil bound distemper, acrylic paint and
acrylic distemper done once in TWO years?
4 Whether polishing/painting of interior wood work Yes/No
and painting of steel work done once in THREE years?
5 Whether premix, semi dense carpeting of roads Yes/No
done once in FIVE years?
6 Whether collection of water samples and analysis
done for:
a . Physical & bacteriological test – Every month. Yes/No
b. For chemical test – Six monthly. Yes/No

2. Schedule for sanitation items: For residential buildings


and colonies:
S. Particular Remarks
N.
1 Whether cleaning and disinfection of water Yes/No
storage/distribution tanks & water mains done
once in SIX months?
189
S. Particular Remarks
N.
2 Whether cleaning of manholes/gully chambers/ Yes/No
inspection chambers and flushing of building
sewers done once in a YEAR before monsoon?
3 Whether cleaning of storm water drains done once Yes/No
in a YEAR before monsoon?
4 Whether cleaning of wet drains meant to serve as Yes/No
quarter drains done at least once in a FORTNIGHT?
5 Whether clearing of rank vegetation done at least Yes/No
once in a MONTH during monsoon?
6 Whether clearing of rank vegetation done as per Yes/No
requirement in period other than monsoon?
(C) CHECKLIST FOR TAKING OVER BUILDING / QUARTER AFTER
CONSTRUCTION:
S. Description of item Remarks
N.
GENERAL ITEMS
1 Whether proper drains and drain pipes has been Yes/No
provided for the disposal of water.
2 Whether the surrounding area cleared off, of unused
materials and construction debris/waste etc. ? Yes/No

3 Whether plinth protection has been provided for


the building? Yes/No
INSIDE BUILDING ITEMS
WALLS
1 Are there any cracks in walls? Yes/No
2 Are there any signs of dampness/leakage on walls?
3 Whether finishing of wall surface is smooth and proper?

190
S. Particular Remarks
N.
FLOORS
1 Are there any cracks in floors, skirting and dado? Yes/No
2 Are the floors laid to proper slopes? Yes/No

3 Is there a stagnation of water in WC, bath and verandahs? Yes/No


4 Whether finishing of floor surface is smooth and proper? Yes/No
ROOFS
1 Are there any leakages in roofs? Yes/No
2 Whether ‘Golas’ are properly made? Yes/No
3 Is the slope of roof proper? Yes/No
4 Are the traps and rain water pipes proper to drain Yes/No
water without ponding?

DOORS, WINDOWS AND VENTILATORS


1 Are all the fittings viz. locking arrangement, tower Yes/No
bolts, pull bolts, door stoppers, hooks, stays and
hinges etc. are provided & functioning properly?
2 Whether quality of wood is as per specification? Yes/No
3 Whether surface of frame and shutter is smooth? Yes/No
FINISHING
1 Is the plastering of walls and ceiling satisfactory, Yes/No
smooth and free from cracks and other defects?
2 Is the painting of walls / doors and windows proper? Yes/No

191
S. Particular Remarks
N.
WATER SUPPLY AND SANITATION
1 Is there any leakage in the sewer lines, drainage Yes/No
pipes etc.?
2 Are flushing cisterns, wash basins etc. correctly Yes/No
fitted and working properly?
3 Are the covers of manholes, gully traps and floor Yes/No
traps etc. provided?
4 Is the slope of sanitary pipes proper? Yes/No
5 Is the condition of water overhead tank proper Yes/No
including float valve & cleaning of tank?
6 Any other deficiency noticed in the building Yes/No

L. ITEMS PERTAINING TO LAND MATTER.


S. Item to be inspected Remarks Reference
N.
1. Whether village-wise Yes/No
land records i.e.
Jamabandi, Shajra, and
mutation documents
available? Para 806 (a) to (c) of
IRWM for Land record
2 Whether land plans are Yes/No and for micro filming
authenticated? Para 806 (d)
3 Whether authenticated Yes/No
land plans are available
and micro filming done.
192
S. Item to be inspected Remarks Reference
N.
4 Whether land boundary Yes/No Para 808 (v) of IRWM
post is being provided
at 50 m on either side?
5 Whether within the Yes/No Para 809 (b) of IRWM
boundary, the
demarcation of offsets
is done at change point?
6 Whether land boundary Yes/No Para 813 (a to e) of
post is visible? IRWM
7 Whether land boundary Yes/No
post/boundary wall is
missing/damaged?
8 Whether periodical Yes/No
verification of land
boundary is being done?
9 Whether land boundary Yes/No
verification registers
are available?
1 0 Whether there is any Yes/No Para 814 (C) of IRWM.
encroachment of
jhuggies /permanent
structures?
1 1 Is the encroachment Yes/No Para 814 (e & f) of IRWM
register maintained? & Ann 8.2
1 2 Whether any
encroachment has been

193
S. Item to be inspected Remarks Reference
N.
dealt under Public Yes/No
Premises (Eviction of
Unauthorized
occupants) Act (PPE
Act)?
1 3 Whether any action is Yes/No
being taken for removal
of encroachment?
1 4 Whether there is any Yes/No
case registered in the
Court regarding
encroachments?
1 5 Whether there is any Yes/No Para 818 of IRWM
unauthorized Religious
structure in the
premises?
1 6 Whether Religious Yes/No
structure register is
maintained?
1 7 Whether track crossing Yes/No -
register is maintained?
1 8 Whether there is any Yes/No -
unauthorized track
crossing?
1 9 Whether realization of Yes/No Para 1033 of ENGG
way leaves charges CODE.
done?

194
S. Item to be inspected Remarks Reference
N.
2 0 Whether validity period Yes/No
of any track crossing
expired? Para 1033 of
2 1 Whether agreements Yes/No Engg. Code
are available for track
crossing?
2 2 Is there any private Yes/No Para 1830 and 1139 of
siding? Engg. Code. OR refer
liberalized siding
policy vide boards
various letters.
2 3 Are there any Yes/No Para 821 (c) of IRWM.
commercial plots?
2 4 Are there any Shops/ Yes/No
Tehbazari?
2 5 Whether license fee has Yes/No Para 821 (f) of IRWM.
been updated for the
current year?
2 6 Whether license fee has Yes/No Refer Rly Bd updated
been updated on the policy.
basis of market value of
land after 5 years?
2 7 Whether land is licensed Yes/No No. 2009/LML/16/3
to Railway Staff for Grow dated 16/07/2010
More Food (GMF)
purposes?

195
S. Item to be inspected Remarks Reference
N.
2 8 Whether any land is Yes/No Refer Rly Bd updated
licensed to Container policy.
Corporation of India /
International Container
Depot (CONCOR)?
2 9 Whether execution of Yes/No
land license agreement
has been done for all
cases?
3 0 Whether validity of any Yes/No
agreement has expired?
3 1 Whether any tree is Yes/No Para 715 of IRWM
infringing signal / OHE /
track?
3 2 Whether matured trees Yes/No Para 721 of IRWM.
are being processed for
sale?
3 3 Whether tree register is Yes/No Para 720 of IRWM
maintained?
3 4 Whether any action has Yes/No Para 721 (2) of IRWM.
been initiated for de
notification of protected
forest?
3 5 Whether master data Yes/No N0.2014/LML-II/2/3
entry in land module has dated 28/07/2014
been done or not?

196
M. STEEL STRUCTURES IN WORKSHOPS, RUNNING SHEDS AND
PLATFORMCOVERS IN WHICH ROOF TRUSSES ARE FIXED
TO BUILT UP STANCHIONS
Ref: Para229 IRWM

S. Item to be inspected Remarks


N.
1. Whether truss/column is in sound condition? Yes/No
2. If not, whether any remedial action is being taken? Yes/No
3. Whether the timber is decaying? Yes/No

3(a) If so, whether any remedial action is being taken? Yes/No


4. Whether bed blocks or pedestals are in sound Yes/No
condition?
4(a) If not, whether any remedial action is being taken? Yes/No
5. Whether all fixtures are intact in bed blocks or Yes/No
pedestals?
5(a) If not, whether any remedial action is being taken? Yes/No

6. Whether the condition of paint is in good condition? Yes/No


6(a) If not, whether any remedial action is being taken? Yes/No
7. Whether date of painting is mentioned on the Yes/No
structure?
8. Whether corrosion of steel is taking place? Yes/No
8(a) If so, whether any remedial action is being taken? Yes/No
9. In the case of steel work built into masonry, such as Yes/No
tie rods of arched buildings, whether any corrosion
197
S. Item to be inspected Remarks
N.
is apparent near the masonry?
9(a) If so, whether any remedial action is being taken? Yes/No
10 Whether the condition of rivets, bolts and tie rods Yes/No
particularly of water storage tanks are in sound
condition?
10(a) If not, whether any remedial action is being taken? Yes/No

11. Whether any crack have developed in cast iron tank


plates? Yes/No

11(a) If so, whether any remedial action is being taken? Yes/No

12. Whether any deformation of the structure has Yes/No


occurred?
12(a) If so, whether any remedial action is being taken? Yes/No
13. Whether anchor-bolts are tightly fastened to Yes/No
foundations & bearings?
13(a) If not, whether any remedial action is being taken? Yes/No

N. CI/WI/PRESSED UP STEEL WATER TANK & STAGING & FLOOD


LIGHTTOWERS

Ref: Para229 IRWM


S. Item to be inspected Remarks
N.
1. Whether any crack has developed in CI/WI/Pressed Yes/No
up steel/tank plates?
198
S. Item to be inspected Remarks
N.
1(a) If so, whether any remedial action is being taken? Yes/No
2. Whether corrosion in steel is taking place? Yes/No
2(a) If so, whether any remedial action is being taken? Yes/No

3 In the case of steel-work built into masonry, such Yes/No


as tie rods of arched buildings and roof trusses,
whether any corrosion is apparent near the
masonry?
3(a) If so, whether any remedial action is being taken? Yes/No
4 Whether the condition of rivets, bolts and tie rods Yes/No
particularly of water storage tanks are in sound
condition?
4(a) If not, whether any remedial action is being taken? Yes/No
5 Whether bed blocks or pedestals are in sound Yes/No
conditions?
5(a) If not, whether any remedial action is being taken? Yes/No
6 Whether all fixtures are intact in bed blocks or Yes/No
pedestals?
6(a) If not, whether any remedial action is being taken? Yes/No

7 Whether the condition of paint is good? Yes/No

7(a) If not, whether any remedial action is being taken? Yes/No

8 Whether date of painting is mentioned on the Yes/No


structure?

199
S. Item to be inspected Remarks
N.
9 Whether anchor-bolts are tightly fastened to Yes/No
foundations & bearings?
9(a) If not, whether any remedial action is being taken? Yes/No
10 Whether any deformation of the structure has Yes/No
occurred?
10(a) If so, whether any remedial action is being taken? Yes/No

11 Whether decay in timber is taking place in case of Yes/No


wooden staging?
11(a) If so, whether any remedial action is being taken? Yes/No
12 Whether any sign of leakage has been detected in Yes/No
water tank?
12(a) If so, whether any remedial action is being taken? Yes/No

O. WATER SUPPLY INSTALLATION

1. List of Check Points on Quality of Water supply – General:


S. Item to be inspected Remarks Ref.
N.
1 Are inspections of the various water supply Yes/No
IRWM
installations being done as per IRWM i.e. Once
Para
in THREE months by ADEN and joint inspection
554/c/i
once in a year by SSE/W with MECH/ELE dept.?
2 Are records of inspections of the various water Yes/No IRWM
supply installations being maintained properly Para
in registers? 554/e
200
S. Item to be inspected Remarks Ref.
N.
3 Whether storage tank (Underground & elevated) Yes/No IRWM
is clean and date of cleaning is mentioned? Para 537
4 Whether tube well is protected against Yes/No
contamination from surface water?
5 Whether water samples tested from filtration Yes/No IRWM
plant every MONTH? Para 554/a

6 Whether water samples tested for chemical Yes/No IRWM


examination SIX MONTHLY (or once before & after Para 554/a
monsoon)?
7 Whether samples collected as per specified Yes/No IRWM
manner? Para 532
8 Whether collected samples sent to medical Yes/No IRWM
department or lab duly leveled, sealed without Para
delay? 532/e
9 Whether leakage detection test conducted? Yes/No IRWM
Para 546

2. Inspection of Chlorination Plant


S. Item to be inspected Remarks
N.
1 Whether chlorination plant is in good working Yes/No
condition?
2 Whether records like log book, and plant failure Yes/No
register of the chlorination plant properly
maintained and up to date?

201
S. Item to be inspected Remarks
N.
3 If the plant is maintained and operated through Yes/No
contract, are all records of operation and
maintenance properly maintained?
4 Are plant failures promptly attended? Yes/No
5 If the plant is maintained and operated Yes/No
departmentally, are spares of all critical
components in stock?
6 Whether chlorine demand of the raw/untreated Yes/No
water is being regularly tested?
7 Whether equipment/disinfectant chemicals in Yes/No
chlorination plant are stored properly in safe
condition?
8 Whether proper record of date of receipt, date of Yes/No
testing and date of consumption of the hypochlorite
solution maintained?
9 Are all components of chlorination plant Yes/No
functioning properly including proportionate dozing
system (if provided)?
10 Whether contact period of 30 to 60 minutes is Yes/No
maintioned?
11 Whether residual chlorine of 0.2 ppm is available Yes/No
in normal condition?

202
P. RAIN WATER HARVESTING SYSTEM (RWH)

S. Item to be inspected Remarks


N.
1 Whether new buildings which are being provided Yes/No
with suitable RWH structures as per local bye laws?
2 Whether recharged water is silt free and properly
maintained? Yes/No
3 Whether well/trench used for RWH is being cleaned Yes/No
periodically?
4 Whether the recharge shafts for RWH are being Yes/No
constructed 10-15 m away from the building for the
safety of building?
5 Whether there is an approved plan for RWH Yes/No
installation?
6 Has the RWH system been checked before Yes/No
monsoon?
7 Has the RWH system been checked after monsoon? Yes/No

  

203
CHAPTER NO – 5
Inspection at New construction Site

A. CHECK LIST FOR WORK SITES


Infringement to Running Line by Construction Machinery Vehicles

S. Items to be checked Remarks Reference


N.
1 Vehicle to ply minimum generally 6m Yes/No
clear from center line of track, if
required, upto 3.5 m only with the
permission of Engineer – in – charge.
Has this been done? Para 826
of IRPWM,
2 If required to work within less than 3.5 Yes/No For
m clearance from the center line of dimensional
track, whether the presence of details
authorized Railway Inspector is refer ann-
ensured? ii of PCE/
ECR
3 Whether proper barricading or 150 Yes/No
circular
mm thick line (of lime) marking at a
no. 16 /
distance of 3.5m from the centre of
2010/
track has been provided or not?
Track
4 Is nominated vehicl is plying between Yes/No
sunrise & sunset?

204
S. Items to be checked Remarks Reference
N.
5 Whether trained drivers are being
utilized and the presence of at least Yes/No
one flag man and one supervisor
certified for such work?
6 If night working is done, whether it has Para 826
been permitted by AEN/XEN in writing Yes/No of IRPWM,
any by deputing one inspector? For
dimensional
7 Whether walkie talkie sets or mobile details
phones have been provided at the refer ann-
site of work? ii of PCE/
ECR
8 Whether S & T and electrical staff
circular
have been informed before starting
no. 16/
of work along the track?
2010/
9 Whether vehicle / tractor drivers Track
trained by the Railway Officers/
Supervisors to work along the track
as per safety guide lines?
10 For night working whether sufficient
light has been provided?

205
B. Work in /near Electrified Territory :

S. Items to be checked Remarks Reference


N.
1 Whether work is being done in
presence of authorized Over Head Yes/No
equipments (OHE) staff with proper
power block & permit to work?

2 If track bonds, feeder connection etc.


have been disturbed, whether they Yes/No
have been re-connected properly
after completion of work?
Para 283
3 Whether mast foundation is exposed Yes/No (2)of
and track level raised/slewed beyond IRPWM
permissible limits?

4 Whether a minimum distance of 2


met. has been maintained between Yes/No
live OHE wire and body parts of the
worker or tools or metallic supports,
etc.?

206
C. Precautions within station Premises

S. Items to be checked Remarks Reference


N.
1 Whether contractor has ensured
proper barricading and protection at Yes/No
the site of work?
2 Whether sufficient free space for Para 34(3)
movement of passenger traffic & 34(4) of
provided, to avoid any untoward Yes/No GCC
incidents for all works done within
station premises, especially on
passenger platform?
3 Whether proper signage has been Yes/No
provided?

D. Check list for Track Ballast:

S. Items to be checked Remarks Reference


N.
1 Whether the track ballast is hard, well Specification
graded machine crushed and angular Yes/No of ballast as
in shape. per IRS GE-
1, June
2 Physical properties of the ballast
2004
a . Is the abrasion value of the track Yes/No corrected
ballast done is less than 30% upto CS no 3
dtd 05-1-
09GCC

207
b. Is the impact value of the ballast is Yes/No
less than 20% Specification
of ballast
c. Is Water absorption in less than 1% Yes/No as per IRS
GE-1, June
(In exceptional cases on technical and
2004
economic ground, can be relaxed up to
corrected
35% and 25% respectively by CTE in
upto CS no
open line and CAO/C for construction
3 dtd 05-1-
projects.)
09GCC
3 Size and gradation:
Is the ballast satisfy the following size Yes/No
and gradation:
a . Retained on 65 mm Sq. mesh sieve Yes/No
5% Maximum
b. Retained on 40 mm Sq. mesh sieves Yes/No
40% - 60%
c. Retained on 20 mm Sq. mesh sieve Yes/No
Not less than 98% for machine
crushed. Not less than 95% for hand
broken.
Oversize Ballast:
a . In case retention on 65 mm square
mesh sieve exceeds 10%, the stack
shall be rejected.
b. In case retention on 40 mm square
mesh sieve exceeds 70%, the stack
shall be rejected.

208
Under size Ballast:
The ballast shall be treated as under
size and shall be rejected if:-
a. Retention on 40 mm sq. mesh sieve Yes/No
is less than 40%
b. Retention on 20 mm sq. mesh sieve
is less than 98%
(For machine crushed) or 95% (for hand Yes/No Specification
broken.) Has this been done? of ballast
4 Stack measurement as per IRS
GE-1, June
Stacking if done on a neat, plain and firm 2004
ground with good drainage. The height corrected
of stack is not less than 1 m except in upto CS no
hilly area where it may be 0.5 mm. 3 dtd 05-1-
Cubical content of each stack should 09GCC
normally be not less than 30 cum in plain
area and 15 cum in hill area.
The screen for sieving the ballast shall
be of square mesh. If Mesh in not less
100 X 70 X 10 cm (LXBXH). The following
tolerances in the size of the hole for 65,
40 and 20mm nominal size shall be
permitted.

209
a. 65 mm sq. mesh plus/minus 1.5 mm Specification
of ballast
b. 40mm sq. mesh plus/minus1.5 mm as per IRS
c. 20mm sq. mesh plus/minus 1.0 mm GE-1, June
2004
corrected
upto CS no
3 dtd 05-1-
09GCC

E. Form Work in Concreting Work :

S.N. Items to be checked Remarks


1 Whether proper temporary support e.g. Yes/No
shoring, timbering and strutting has been
checked before concreting works?
2 Whether stability and safety of all structures, Yes/No
excavation and works has been ensured?
3 Whether form work is water tight? Yes/No
4 Whether dimensions are checked and found Yes/No
correct?

F. Box Pushing Work. :


S.N. Items to be checked Remarks
1 Whether box pushing work is to be done in parts Yes/No
of 10 to 20 cm to minimize disturbance to track?
2 Are trains permitted to pass during actual box Yes/No
pushing operation?

210
3 Whether track parameter has been checked Yes/No
and recorded before the passing of first train?
4 After close of box pushing work whether the Yes/No
speed of first train passed at speed of stop
dead and 10 kmph and subsequent trains were
upto 30 kmph?
5 Whether track parameter has been checked Yes/No
after each round of box pushing by the
supervisor In-charge before leaving site?
6 Whether posting of proper look out Man with
Yes/No
banner flags and other protection equipments
has been ensured when box pushing is not in
progress?

  

211
Notes

212
Notes

213
Notes

214
Notes

215
Notes

216
Notes

217
Notes

218
This book is compilation of updated instructions on different
subjects, kindly also refer to latest correction slips, if any.

Although due care has been taken while preparing this


compilation. In case of any doubt/discrepancies, users are
advised to kindly refer to original document/correction-slips, as
indicated therein. The same may be brought to the notice of
IRICEN, Pune at e-mail id: mail@iricen.gov.in
Published by :
Indian Railways Institute of Civil Engineering, Pune
11-A, South Main Road, Koregaon Park, Pune - 411001.
Design by :
HUMA Adds, Pune.

Printed by :
Kalyani Corporation, Sadashiv Peth, Pune - 30.
Price < 60/-

You might also like