SUMMARY OF PROJECT STATUS REPORT

Project Name: - GTC 644 E / 2014, Extension of Distribution Network Phase 06 Package E Date: -07-05-2018

Project Particulars

Contract Value: - 174, 200,000.00 Qatar Riyal

Approved Invoiced (INV 20) Amount 51,648,868.42 Qatar Riyal (29.64 %)

Under review invoice amount (INV 21) 2,178,104.04

Approved Variation for new Items 1,104,535.00

Project Time Status

Project Start Date: - 11th August 2015

Project Completion Date (EOT 02): - 02nd December 2018 ( 82.05 % Completed)

Milestone 01: - 21st June 2018

Milestone 02: - 02nd December 2018

Summary of Pipe Length

1. Original Scope of Work = 115 km


2. Handed over / Available Scope of Work (DI.Pipe) = 99.002 Km (Total cost 79 Million, 45.3%)

a. Executable Scope of Works = 88.411 Km (Total cost 69.7 Million, 40.01%)


b. On Hold Scope of Works = 10.591 Km (Total cost 9.4 Million)

3. Length of Pipe Laying Completed = 72.086 Km (81.53 % Completed Job in Hand)


4. Length of 09 bars Test Completed = 62.078 Km
5. Length of Handed over to KM-Operation Dept. = 49.467 Km
6. Length of Work in Progress = 11.615 Km
7. Length of RO Under Process = 4.710 Km
8. Deletion of Area from Scope of work = 34.571 Km