This project status report provides an update on the GTC 644 E / 2014 Extension of Distribution Network Phase 06 Package E project. The project is 82.05% completed and on track to meet the revised completion date of December 2nd, 2018. To date, 51.6 million Qatar Riyals have been approved out of the total 174.2 million contract value. Key milestones include completion of pipe laying for 72.1 km of the original 115 km scope by July 2018.
This project status report provides an update on the GTC 644 E / 2014 Extension of Distribution Network Phase 06 Package E project. The project is 82.05% completed and on track to meet the revised completion date of December 2nd, 2018. To date, 51.6 million Qatar Riyals have been approved out of the total 174.2 million contract value. Key milestones include completion of pipe laying for 72.1 km of the original 115 km scope by July 2018.
This project status report provides an update on the GTC 644 E / 2014 Extension of Distribution Network Phase 06 Package E project. The project is 82.05% completed and on track to meet the revised completion date of December 2nd, 2018. To date, 51.6 million Qatar Riyals have been approved out of the total 174.2 million contract value. Key milestones include completion of pipe laying for 72.1 km of the original 115 km scope by July 2018.
Project Completion Date (EOT 02): - 02nd December 2018 ( 82.05 % Completed)
Milestone 01: - 21st June 2018
Milestone 02: - 02nd December 2018
Summary of Pipe Length
1. Original Scope of Work = 115 km
2. Handed over / Available Scope of Work (DI.Pipe) = 99.002 Km (Total cost 79 Million, 45.3%)
a. Executable Scope of Works = 88.411 Km (Total cost 69.7 Million, 40.01%)
b. On Hold Scope of Works = 10.591 Km (Total cost 9.4 Million)
3. Length of Pipe Laying Completed = 72.086 Km (81.53 % Completed Job in Hand)
4. Length of 09 bars Test Completed = 62.078 Km 5. Length of Handed over to KM-Operation Dept. = 49.467 Km 6. Length of Work in Progress = 11.615 Km 7. Length of RO Under Process = 4.710 Km 8. Deletion of Area from Scope of work = 34.571 Km