Name of Project : INSTALLATION OF 1 UNIT BASKETBALL BOARD AND RING (COMPLETE SET) Date Date
: April 6, 2014
Location : NEW ANTIQUE, M'LANG, COTABATO Source of Fund : SK FUND 2014
Appropriations : P 19,797.30
Project Description : Fabrication of Basketball Board and Ring
Implementation Procedure : " By Administration " Technical Personnel Required : Mason, Welder & Laborer
Calendar days to complete : 8 W.D Equipment to be used : Masonry tools, Painting Tools & Welding Machine
Estimated Cost by Item of Work :
% of Total Unit Quantity Unit Cost Total Amount
SCOPE OF WORK TO BE DONE
Noted: APPROVED :
SARAH L. ALAMADA ALEX C. CHAVEZ SR.
LGOO V/ PMC Chairman Barangay Chairman
Republic of the Philippines
Region XII
OFFICE OF THE MUNICIPAL ENGINEER
M'lang, Cotabato
April 6, 2014
I. STEEL WORKS:
Quantity= 1 lot
A. Material
1 length 5mm x 2'' x 2'' x 6m Angle Bar @ P 1,200.00 P 1,200.00
2 length 3.5mm x 1-1/2'' x 1-1/2'' x 6m Angle Bar @ P 800.00 P 1,600.00
4 pcs. 20mm Ø x 250mm Anchor Bolt w/ Nut & Bolt @ P 150.00 P 600.00
1 length 50mm Ø x 6m G.I Pipe S-40 @ P 1,800.00 P 1,800.00
1 pcs. 2mm x 1200mm x 2400mm Plain G.I. Sheet @ P 2,250.00 P 2,250.00
1 length 100mm Ø x 6m G.I. Pipe S-40 @ P 3,800.00 P 3,800.00
2 lin.ft. 10mm thick x 150mm flat Bar (Base Plate) @ P 250.00 P 500.00
1 pc. Hacksaw Blade Sandflex @ P 100.00 P 100.00
6 kgs. Welding Rod N-55 Nihon @ P 115.00 P 690.00
2 ln.ft. 6mm x 4'' Flatbar (Bracket) @ P 85.00 P 170.00
2 ln.ft. 6mm x 1'' Flatbar (Ring Support) @ P 50.00 P 100.00
2 ln.ft. 6mm x 6'' Flatbar (Ring Plate) @ P 135.00 P 270.00
1 length 16mm dia. x 6m Plain bar (ring) @ P 425.00 P 425.00
4 pcs. 10mm dia. x 3'' Carriage bolt w/ nut & washer @ P 35.00 P 140.00
Sub-Total Cost for A= P 13,645.00
B. Labor:
1 Welder for 7 days @ P 350.00 P 2,450.00
1 Labor for 7 days @ P 200.00 P 1,400.00
Sub-Total Cost for B= P 3,850.00
S U M M A R Y
MATERIALS P 14,922.00
LABOR P 4,400.00
CONTINGENCY P 475.30
PROJECT COST P 19,797.30