Date: 20/05/2023
AGENDA
HS&E STATISTICS
INCIDENT SUMMARY
KEY ISSUES
OPEN/CLOSE OBSERVATION & NCR
REPORTED NEAR MISS
PROJECT RELATED UPDATES
WELFARE FACILITY
HSE BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE
HSE MILESTONES & ACHIEVEMENTS
1 Week Look Ahead
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
HS&E Statistics
SL.NO FIGURES WEEK CONTRACTORS (PTD) TOTAL (YTD)
5. NO. OF INCIDENT/ACCIDENT 0 1 1
Lagging Indicators
1.2
0.8
0.6
0.4
0.2
0
15-Feb
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
KEY ISSUES
SN CONTRACTOR KEY ISSUES ACTION TAKEN
(Long Pending)
2 BENAN •
•
Proper Internet connection not provided
Some of medical items are not provided as per MOH requirements In Progress of rectification
• No Equipment/machinery/devices checklist maintained (Long Pending)
• Delay in report submission Daily , weekly & Monthly
• Lack of HSE documentation & site supervision
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
OPEN/CLOSED OBSERVATION & NCR
SN CONTRACTOR OPEN OBSERVATION CLOSED OBSERVATION
1 RPCO 1 8
2 BENAN 0 4
1 RPCO 0 2
2 BENAN 2 1
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
RPCO OPEN/CLOSED OBSERVATION
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
RPCO OPEN/CLOSED OBSERVATION
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
RPCO OPEN/CLOSED OBSERVATION & NCR
1 RPCO • RPCO not complied as agreed date 26-Feb-23 stipulated in the comment CLOSED
sheet. (PW-2022001B-C0101-JAS-PCM-NCR-000001)
• RPCO to provide visible Sta. number in the roads (PW-2022001B-C0101-JAS-
PCM-NCR-000002 )
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
BENAN OPEN/CLOSED OBSERVATION
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
BENAN OPEN/CLOSED OBSERVATION & NCR
BENAN NCR (OPEN/CLOSED)
SN CONTRACTOR NCR issued on ACTION TAKEN
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
REPORTED NEAR MISS
RPCO NEAR MISS (OPEN/CLOSED)
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
INCIDENT SUMMARY
PACKAGE CONTRACTOR INCIDENT INCIDENT BRIEF DECRIPTION ROOT CAUSE ACTION STATUS
CLASSIFICATION DATE
A RPCO Property damage 15-02-23 Electric pole hit by unknown vehicle Poor Illumination
at incident
Hard
barriers
Closed
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
RPCO;
1. Fence-1B: (3+300 to 4+400) Installing 4 Tension Wires.
2. Fence–1B: (3+700 to 5+000) Installing Extension Arms.
3. Fence-1B: (2+500 to 4+150) Installing Barbed Wires.
4. Fence–1C: (0+550 to 0+800) Clearing / Grading.
5. Fence–1C: (0+000 to 0+600) Survey Alignment.
6. Station (15+200 to 15+500) spreading, grading, levelling and compacting 6th
BACKFILL 30CM layer of Subgrade Material.
7. Station (0+100 to 1+200) Cutting / Clearing / Grading.
8. Station (15+750 to 15+950) spreading, grading, levelling and compacting 5th
BACKFILL 30CM layer of Subgrade Material.
9. Station (12+300 to 11+000) spreading, grading, levelling and compacting
SUBBASE 20CM layer.
10. Station (15+500 to 15+750) spreading, grading, levelling and compacting 5th
BACKFILL 30CM layer of Subgrade Material (READY FOR FDT).
11. Importing SUBBASE Material from Site Crusher using 2 Dump Trucks: (qty = 21
trips = 504 CUM).
12. R2: (1+000 to 1+800) Excavation/ Slope Scaling of Benches.
13. R2: (0+700 to 0+800) Rock filling 4th Layer.
14. R2: (0+900 to 1+000) Rock filling 1st Layer.
15. R2: (0+900 to 1+000) Rock filling EMBANKMENT SLOPE 4th Layer.
16. R2: (0+800 to 0+900) Cutting / Backfilling / Clearing (READY).
17. R2: (0+600 to 0+675) spreading, grading, levelling and compacting 7th ROCKFILL
layer.
18. (SITE OFFICE NEAR ST. 1+700) Laying SUBBASE 20 CM LAYER (READY FOR FDT).
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
PROJECT RELATED UPDATES
SN DESCRIPTION PHOTOS
1. BENAN:
▪ Bore hole cleaning BH M 122 at Monolith total depth 28.0m to 39.0m
(Televiewer test)
▪
▪ Continue drilling BH M 113 at Monolith total depth 55m to 68.5m
▪ ( we faced total water loss at a depth of 15m & 24m)
▪ Continue drilling BH M 128 at Monolith total depth 47.0m to 49.0m
▪
▪ Continue drilling at Secondary Wadi route 0 BH 15 total depth 9.0m to 12.5m
▪
▪ Continue drilling BH M-108 at Monolith total depth 0.0m to 22.0m
▪
▪ Continue drilling at Secondary Wadi route 0 BH 16 total depth 0.0m to 5.0m
▪
▪ The lifting operation was stopped at 4:30 pm
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
WELFARE FACILITY
CONTRACTOR TOTAL EMPLOYEE’S HSE TOILET RESTING SHELTER PRAYER AREA
NAME AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED AVAILABLE/REQUIRED
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO PHOTO
RPCO
RPCO – Removal of accumulative sand with jersey barriers of T-Junction Detour on daily basis.
• LED light, Blinking soler lights and soler sunflowers been installed at T-Junction 375 Road
detour to prevent accident/awareness during darkness hours.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th-2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO PHOTO
date/water filling date been mentioned. To maintain welfare facilities in good manner.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th-2023
ENVIRONMENTAL BEST PRACTISE
ENVIRONMENTAL BEST PRACTISE ENVIRONMENTAL BEST PRACTISE
PHOTO PHOTO
RPCO- RPCO -Spraying water at access road been maintained as part of safety &
1. Trash bins provided at suitable points around site and in case of slightly full it's environmental protection on daily basis.
been emptied by skip bin and disposed by certified sub-contractor.
2. Provided separate food waste skip bin to dispose on daily bases to avoids
attraction of pests.
PROJECT-W ADVANCE WORK PACKAGE-A HSE Data - From May 14th to May 20th, 2023
HSE BEST PRACTISE
HSE BEST PRACTISE HSE BEST PRACTISE
PHOTO PHOTO
BENAN-Material been shifted using appropriate Tools & lifting gears during manual
BENAN – Using appropriate PPE for the intended task. handling.
PHOTO PHOTO
SN DESCRIPTION
RPCO –
• R2 – Cut is done almost 55%
Station 9
• R2 - Fill almost 70%.
• R3 – From Station 9 to station 10 subbase 20cm layer done
1. • R3 – From Station 11 to 12+300 subbase 20cm layer done.
• Fence 1B – All posts are concreted, and mesh installation is almost 30% done.
• Fence2 – All posts are concreted done and 55% mesh is installed already
• RPCO is Sending additional Equipment's to increase productivity.
SN DESCRIPTION
BENAN : Up to
• Finish 12 BH on phase1.
1. •
•
5 BH in progress (phase 1).
Submit the interpretive report for permanent road (21 bh).
• Submit the draft report of Phase 1 (10 BH).
• Submit the MASW interpretive report .
• Submit the InSAR study report.
• Finish 10 BH on the secondary route 2 BH in progress.
RPCO • Precast progress for over all project for next week is 4.4%
BENAN •
•
Continue drilling 0 BH-16 at Wadi
Continue drilling 0 BH-15 at Wadi depth
• Continue drilling BH M 113 at Monolith
• Continue Tricon drilling BH M 130 at Monolith (Pressure metre Test)
• continue drilling Angle drilling rig at Monolith BH M-108
• Continue drilling BH-128 at Monolith
• Rig mobilize to BH-M109 cleaning bore hole then after perform Televiewer test