Professional Documents
Culture Documents
Villaverde, Allan A.
Manpower Report: Block 04, Lot no. 29-30 Date: August 31, 2022
Current Activities Manpower % Completion
1 Septic Tank Installation 2 100%
2 Gutter Installation 2 50%
3 Stair Railing Welding 2 100%
4 Ceiling Putty Application 1 10%
TABLE 1.1
Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, all of the activities are still ongoing with “Firewall Finishing and Interior
Skim Coating (2nd layer)” having the most progress with a 95% to completion.
Manpower Report: Block 06, Lot no. 35-36 Date: August 31, 2022
Manpower Report: Block 06, Lot no. 29-30 Date: August 31, 2022