DAILY PROGRESS REPORT


Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently, the activities “Septic Tank Installation and Stair Railing Welding” has
been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: August 31, 2022
  Current Activities Manpower % Completion
1 Septic Tank Installation 2 100%
2 Gutter Installation 2 50%
3 Stair Railing Welding 2 100%
4 Ceiling Putty Application 1 10%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently, all of the activities are still ongoing with “Firewall Finishing and Interior
Skim Coating (2nd layer)” having the most progress with a 95% to completion.

Manpower Report: Block 06, Lot no. 35-36 Date: August 31, 2022

Current Activities Manpower % Completion


1 Interior Skim Coating (2nd layer) 1 95%
2 Firewall Finishing 2 95%
3 Ceiling Installation 2 45%
4 Tile Works 2 30%
5 Electrical Works 1 70%
TABLE 1.2
Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, all the activities are ongoing with “Clearing ” having the most progress
with a 95% to completion.

Manpower Report: Block 06, Lot no. 29-30 Date: August 31, 2022

Current Activities Manpower % Completion


1 Clearing 2 95%
2 Ceiling Frame Installation 2 25%
TABLE 1.3