Work Progress

Site Progress up-to-date


1. Building Architectural Works
27%
a. Building Internal Architectural Works 26%
i. Brickwall-in-Position
98%
ii. Internal Wall Partition Plastering Works
96%
1. Plastering Work
94%
2. Ceiling Works
18%
a. Framing Work
40%
b. Installation of ceiling board
1%
b. M&E Works 36%
i. Piping & Conduiting Works
75%
1. Cold+Hot Water & Plumbing Works
81%
2. Fire Fighting Services
71%
3. Electrical Services
79%
4. ELV Services
79%
5. HVAC Services
63%
ii. Cabling & Wiring Works
55%
1. Fire Fighting Services
51%
2. Electrical Services
63%
3. ELV Services
63%
4. HVAC Services
43%
iii. Fixture
0%
c. Wall Finishes
0%
d. Floor Finishes
0%
e. Door
56%
f. ID Work
0%
2. Miscellaneous Internal Works
60%
a. Steel Works (Hand Railing & Balusters)
90%
3. Building External Architectural Works
50%
4. Infrastructure Works Within Boundary
18%
a. Fencing Wall & MS Works
95%
5. Schedule
a. Actual schedule upon completion on site is 34%

6. Main Activities
a. Screeding,
b. Rendering,
i. Rear Elevation 1st Floor- 7th Floor GL/ 2.5-4 A
c. Plastering
i. Room 3019,3020
ii. Basement retaining wall
iii. 1st floor external wall 1017,1016
iv. Roof Garden retaining wall
d. Infra
i. Fencing
ii. Main drain
iii. Piling Sesco Substation, genset room
7. Remaining Works
a. EDOT-toilet U frame, Pool U frame
b. Ming Sing- Tile work on room toilet
c. MS- Elevator installation
d. AC room screed -> waterproof -> painting work -> a compressor
installation
8. Manpower ,machineries & material
a. Eka 2 Supervisor + 23 Plasterer + 4 Scaffolders
b. Wong 3 supervisor + 12 Plasterer
c. ELV 3 wireman
d. Premier 1 engineer + 1 supervisor +2 workers
e. Chia 2 plumber
f. Lift 3 installer
g. Air Cond 2 installer
h. Fire fighting - 1 worker
i. Paling General Worker- 1 foreman + 1 plasterer + 1 housekeeper + 6
general worker (9)
j. 1 crane operator + 1 excavator operator
9. Current Issue and subsequence plan
a. Previous On-hold Progress due to amendments on ID Layout Room
i. Phase one (11 rooms)
1. 3rd floor.(3017,3018,3021)
2. 4rd floor.(4014,4015,4016,4017)
3. 5th floor. (5014,5015,5016,5017)
ii. Phase two (38 rooms)
1. 1st Floor (1001, 1016, 1017, 1026)
2. 2nd Floor (2001, 2004, 2015, 2016, 2024, 2025)
3. 3rd Floor (3001, 3004, 3011, 3014, 3015, 3023, 3024)
4. 4nd Floor (4001, 4004, 4007, 4010, 4013, 4014, 4016,
4017, 4018, 4019)
5. 5nd Floor (5001, 5004, 5007, 5010, 5013, 5014, 5015,
5016, 5017, 5018, 5019)
iii. On-going (73)