6. Main Activities
a. Screeding,
b. Rendering,
i. Rear Elevation 1st Floor- 7th Floor GL/ 2.5-4 A
c. Plastering
i. Room 3019,3020
ii. Basement retaining wall
iii. 1st floor external wall 1017,1016
iv. Roof Garden retaining wall
d. Infra
i. Fencing
ii. Main drain
iii. Piling Sesco Substation, genset room
7. Remaining Works
a. EDOT-toilet U frame, Pool U frame
b. Ming Sing- Tile work on room toilet
c. MS- Elevator installation
d. AC room screed -> waterproof -> painting work -> a compressor
installation
8. Manpower ,machineries & material
a. Eka 2 Supervisor + 23 Plasterer + 4 Scaffolders
b. Wong 3 supervisor + 12 Plasterer
c. ELV 3 wireman
d. Premier 1 engineer + 1 supervisor +2 workers
e. Chia 2 plumber
f. Lift 3 installer
g. Air Cond 2 installer
h. Fire fighting - 1 worker
i. Paling General Worker- 1 foreman + 1 plasterer + 1 housekeeper + 6
general worker (9)
j. 1 crane operator + 1 excavator operator
9. Current Issue and subsequence plan
a. Previous On-hold Progress due to amendments on ID Layout Room
i. Phase one (11 rooms)
1. 3rd floor.(3017,3018,3021)
2. 4rd floor.(4014,4015,4016,4017)
3. 5th floor. (5014,5015,5016,5017)
ii. Phase two (38 rooms)
1. 1st Floor (1001, 1016, 1017, 1026)
2. 2nd Floor (2001, 2004, 2015, 2016, 2024, 2025)
3. 3rd Floor (3001, 3004, 3011, 3014, 3015, 3023, 3024)
4. 4nd Floor (4001, 4004, 4007, 4010, 4013, 4014, 4016,
4017, 4018, 4019)
5. 5nd Floor (5001, 5004, 5007, 5010, 5013, 5014, 5015,
5016, 5017, 5018, 5019)
iii. On-going (73)