MATERIAL QUIANTITES

1. EARTHWORKS
a. EXCAVATION 15.262 m³
b. GRAVEL BEDDING (0.1m thk)
Gravel 1.666 m³
c. EMBANKMENT 10.2817 m³

2. CONCRETE
a. FOOTING (Class A)
Cement 14 bags (40kg)
Sand 0.75 m³
Gravel 1.5 m³
b. Wall Footing (Class A)
Cement 20 bags (40kg)
Sand 1.066 m³
Gravel 2.132 m³
c. Column (Class A)
Cement 18 bags (40kg)
Sand 0.948 m³
Gravel 1.896 m³
d. Roof Beam (Class A)
Cement 20 bags (40kg)
Sand 1.08 m³
Gravel 2.16 m³

3. STEELWORKS
a. FOOTING (Class A)
12 mm dia Bars 25 pcs
Tie Wire 4.5 kg
b. Wall Footing (Class A)
10 mm dia bars 20 pcs
Tie Wire 2.5 kg
c. Column (Class A)
12 mm dia Bars 19 pcs
10 mm dia bars 34 pcs
Tie Wire 46 kg
d. Roof Beam (Class A)
12 mm dia Bars 26 pcs
10 mm dia bars 27 pcs
Tie Wire 19 kg
4. MAS ONRY
a. CHB 5" 605 pcs
b. CHB 4" 257 pcs
c. Cement 87 bags
d. Sand 7.133 m³

5. TILE WORKS
a. 30cm x 30cm Ceramic Tiles 334 pcs
b. Cement 3 bags
c. Gravel 0.48 m³
d. Grout 15 kg