You are on page 1of 2

ESTIMATION FOR ALTAR STAGE

Option 1: Painted Altar Background


Description Quantity Unit Unit Price Total Price(Php)
Altar Floor, Altar Wall *Note (Order 1 load each for sand and gravel) (1
A.
Plaster, Main Floor load= 4 cu. m)
A.1. Sand 4 cu.m 11,000.00 11,000.00
A.2. Gravel 6 cu.m 11,000.00 11,000.00
A.3.Cement 67 pcs. 300.00 20,100.00
B. RSB (altar)
B.1. 10mmØ RSB 13 pcs. 190.00 2,470.00
B.2. 10mmØ RSB 48 pcs. 190.00 9,120.00
C. Paint Area (altar background)
C.1. Skimcoat 1 bag(20kg) 600.00 600.00
C.2. Flatwall Latex 1 pail(4L) 900.00 900.00
C.3. Gloss Latex 1 pail(4L) 900.00 900.00
D. Tile Area(Altar Floor) *Note (Use ceramic tiles)
D.1. Tile (30cmx30cm) 190 pcs. 50.00 9,500.00
D.2. Tile Grout 5 bag(2kg) 75.00 375.00

Materials Total 65,965.00


Altar Floor altar floor
L 2.7 m vol 1.62 cu.m
W 6 m sand 0.81 cu.m Total Quantity:
D 0.1 m gravel 1.62 cu.m altar+plaster
Volume 1.62 cu. m cement 15 bags sand 1.28 cu.m
gravel 1.62 cu.m
Plaster Finish(Altar Background) cement 24 bags
L 6 m Wall Area 18.6
H 3.1 m cement 9 bags *but if main floor slab is added(para sulit ang pagpa bunag)
Wall Area 18.6 sq. m sand 0.47 cu.m
gravel 8.37
Main Floor main floor
L 6.9 m vol 4.14 cu.m
W 6 m sand 2.07 cu.m
D 0.1 m gravel 4.14 cu.m
Reinforcing Steel Bar Volume 4.14 cu. m cement 38 bags
Altar Floor RSB D10-6m 13 pcs
Main Floor RSB D10-6m 48 pcs Total Quantity:
altar+plaster+main floor+tile altar
sand 3.89 cu.m
gravel 5.76 cu.m
cement 67 bags

OPTION 1: Painted Background


Paint Area *Using Paint Calculator *get
L 6 Skimcoat 7 liters 1
H 3.1 Flat Latex 3 liters 1
Wall Area 18.6 Gloss Latex 3 liters 1

Tile Area(Altar Floor) *By Manual Counting: Tile count


L 6 180 pcs 30x30cm
W 2.7 189 +5% breakage allowance
Floor Area 16.2 sq. m ~190 pcs

Mortar
Thickness 0.025 m cement 5 bags
Vol 0.405 cu.m sand 0.54 cu. m
grout 5 bags(2kg)