You are on page 1of 1

Project 

Civil, Mechanical, Electrical

Vendor name : PT. Cakra Hexa Swadaya
PO No : 
PO Subject : 
Site : SST 36m - Greenfield
BOQ CME BOQ Plan BOQ Actual QTY Amount Dibayarkan Sesuai PO  Amount Additional

NO PEKERJAAN UoM Unit Price (IDR) Qty Unit Amount (IDR) Sisa PO Qty Amount (IDR)  Qty  Amount (IDR)  Qty  Amount (IDR)

1 Tower Foundation
Soil work
a. Excavation of soil for foundation           43.20 m3
b. Sand layer under the foundation t=5cm            1.25 m3

Concrete work
d. Concrete work floor (lean concrete 5cm)            1.25 m3
e. Concrete K‐225 
 ‐ Weight of steel (WoS) with SNI 07.2052 1990/JIS G‐3112 Standard     1,260.40 kg
 ‐ Concrete K‐225 with SK SNI 03.2002 Standard           13.80 m3

Borepile
f. Bored Pile Ø 60cm (supply and installation) logitudinal bar 30 pcs              ‐ m

2 Outdoor Foundation
Soil work
a. Excavation of soil for Outdoor Foundation            0.50 m3
b. Aanstamping under the Outdoor Foundation t=15cm            0.15 m3
c. Sand layer under the Outdoor Foundation t=5cm            0.05 m3

Concrete work
d. Concrete work floor (lean concrete 5cm)              ‐ m3
e. Concrete K‐225 
 ‐ Weight of steel (WoS) with SNI 07.2052 1990/JIS G‐3112 Standard           19.58 kg
 ‐ Concrete K‐225 with SK SNI 03.2002 Standard             0.20 m3

f. Stone masonry            0.60 m3

3 Fence and Yard


a. Site Construction 7m x 7m
 ‐  Excavation            2.60 m3
 ‐  Sand Layer Thickness 5 cm            0.19 m3
 ‐  Fence (Included stone masonry,sloof,post)          26.80 m1
 ‐  Landscaping (gravel) thickness 15 cm           41.56 m2
 ‐  Swing  door 1.2 m width            1.00 Ls

b. Stone masonry            2.17 m3

Total Rp                                      ‐ Rp                                       ‐ Rp                                      ‐ Rp                                    ‐

Prepared by: Approve By : 

PT. CAKRA HEXA SWADAYA