1 PREPARATION
1.1 Mobilisasi & Demobilisasi (Equipment, manpower, indirect material, etc) Lot 1
1.2 Utility (Office, mess, transportasi, komunikasi, makan, dll) month 2
1.3 Safety & HSE (Sepatu, helm, kacamata, full body hernes, dll) Lot 1
1.4 WPS-PQR & Welder certificate By MIGAS Lot
1.5 Work Permit
a. Local Gaverment Permit month 2
b. Restribution month 2
c. Community Development and other levies month 2
Sub TOTAL PREPARATION WORK
2.4.3 - Installation Mechanical & Piping Offtake Station - Material Piping 2nd Batch
2.4.3.1 - Plug Valve 2 Inch #300 Pc 8.00
2.4.3.2 - Design API 6D, Fire Safe Design, API-607 or Eq, Size 2" ANSI #600 Pc 26.00
RF Flanged
2.4.3.3 - Plug Type, Lubricated Plug + Antifriction Coating/Treatment, Pc 2.00
Handwheel
2.4.3.4 - Material Body/Bonnet A352 Gr. LCC, Plug A352 Gr.LCC with 3 mil Pc 11.00
ENP, Stem :
2.4.3.5 - +Cr/ENP & A182-F6a ENP, Seat Matel Based, Stem Packing Pc 7.00
Graphite
2.4.3.6 - Ball Valve ¾ Inch #800, Lever Pc 16.00
2.4.3.7 - Check Valve 1 ½" #150 Pc 1.00
2.4.3.8 - Check Valve 2" #150 Pc 2.00
2.4.3.9 - Gate Valve 1 ½ #800 Pc 1.00
2.4.3.10 - Gate Valve ½ #800 Pc 1.00
2.4.3.11 - Gate Valve 2" #150 Pc 2.00
2.4.3.12 - Gate Valve ¾ #800 Pc 3.00
2.4.3.13 - Globe Valve ¾ Inch 800 (Body A105,PE,#800) Pc 1.00
2.4.3.14 - Plug Valve 2 Inch #150 Pc 3.00
2.4.3.15 - Plug Valve 2 Inch #600 Pc 6.00
2.8 COMMISIONING
2.8.1 - Offtake Station
3 PROJECT MANAJEMENT
3.1 Project Manajement Team man-month 9
3.2 Project Supporting Team man-month 30.00
3.3 Enginering
A. Shop Drawing and Calculation Lot 1.00
B. Reporting & Dokumentasi Lot 1.00
C. As-Built Drawing Lot 1.00
TOTAL