Professional Documents
Culture Documents
Sr.No Item Description Unit Quantity Unit Price Price (PRK) Remarks
Excavation of pits for
1 Excavation work Cft 28 0
foundation
2 Cement Local Bags 8 1,300 10,400 For Column Footing
3 Sand Local Cft 12 0 0
4 Coarse Aggregate Local 1" down Cft 24 0 0
1Pipe Length = 6 m,
5 MS Square Pipe of 1.5" Nos 17 4,500 76,500 Structure (New)
Gauge = 18
Size 3.66 m x 0.9 m
6 G.I Roof Sheets Nos 14 4,000 56,000 Roof Sheet (New)
(Gauge # 26)
7 Self Screws 4.2mm x 38mm Box 10 2,000 20,000
8 Welding Rods Normal welding rods (No#11) Box 10 1,450 14,500
For hand cutter 230 mm , Big
9 Steel Cutting Discs grinder 180 mm & baby grinder Dozen 2 8,000 16,000 Each
100 mm of 2mm Thickness
For Big grinder 180 mm & baby
10 Steel Grinding Discs Dozen 2 8,000 16,000
grinder 100 mm
11 Red Oxide 1 Gallon = 3.64 Liter Gallon 3 4,750 14,250 Paint
12 Steel grinding Discs Wire brush for baby grinder Dozen 1 4,000 4,000
Burger White Color
13 Enamel Paint Gallon 6 4,750 28,500 Paint
(1Gallon = 3.64 Liter)
14 Turpentine Oil 1 Gallon = 3.64 Liter Gallon 8 2,000 16,000 For Piant
15 Paint Brush 76 mm Cat Brush Nos 5 500 2,500 For Paint
Total Cost = 274,650
Calculations
Excavation Work
Size of one Pit = 0.45 m x 0.45m x 0.45 m
No of Total Pits = 8 Pcs
Volume of 1 Pit = 0.1002375 m3
Total volume of 08 pits = 0.8019 m3
28.323108 Cft
Concrete Material
Volume of 08 pits = 0.729 m3
Dry Volume = 1.12266 m3
Concrete Ratio = 1:1.5:3.0
Cement = 0.224532 7 Bags
Sand = 0.30618 10.81428
Total with Wastage (5%)= 11.35499148 Cft
Result Summary
L/760
Deflection/Span L/250 Member 4
LC#0 - LG
0.329 No Load Combinations with 'Serviceability' criteria could
be found so all load combinations were checked.
Buckling 1
0.084
LC#0 - LG 0.084 -
51.26 MPa
Custom Stress Limit 250 MPa
Member 4
LC#0 - LG 0.205 Checked member stresses for any stress values above 250
MPa.
Max Combined Normal Stress
51.26 MPa Checked if each individual member exceeds its Material
Material Yield 260 MPa Member 4
LC#0 - LG
0.197 Yield (260 MPa). 9 members checked in 1 Load
Combination(s).
51.26 MPa Checked if each individual member exceeds its Material
Material Strength 410 MPa Member 4
LC#0 - LG
0.125 Strength (410 MPa). 9 members checked in 1 Load
Combination(s).
Checked if the displacement perpendicular to the vertical
Global Governing
Displacement
h/300
h/13337.4
LC#0 - LG 0.022 axis for all nodes exceeds the global deflection limit
(h/300), where h is the vertical distance from a node to the
lowest support on the model.
Load Summary
Materials
General Structural Steel Metric, Steel, General Structural Steel 7850 0.27 260 410
Result Summary
L/230
Deflection/Span L/250 Member 4
LC#0 - LG
1.087 No Load Combinations with 'Serviceability' criteria could
be found so all load combinations were checked.
Buckling 1
0.284
LC#0 - LG 0.284 -
115.435 MPa
Custom Stress Limit 250 MPa
Member 4
LC#0 - LG 0.462 Checked member stresses for any stress values above 250
MPa.
Max Combined Normal Stress
115.435 MPa Checked if each individual member exceeds its Material
Material Yield 260 MPa Member 4
LC#0 - LG
0.444 Yield (260 MPa). 9 members checked in 1 Load
Combination(s).
115.435 MPa Checked if each individual member exceeds its Material
Material Strength 410 MPa Member 4
LC#0 - LG
0.282 Strength (410 MPa). 9 members checked in 1 Load
Combination(s).
Checked if the displacement perpendicular to the vertical
Global Governing
Displacement
h/300
h/8950.473
LC#0 - LG 0.034 axis for all nodes exceeds the global deflection limit
(h/300), where h is the vertical distance from a node to the
lowest support on the model.
Load Summary
Materials
General Structural Steel Metric, Steel, General Structural Steel 7850 0.27 260 410
Truss Analysis:
1. MS Pipe 18 gauge
2. Thickness = 1.2 mm
3. Outer Dimensions = 1.5” * 1.5” = 40 mm * 40 mm
4. Mild Steel Density = 7850 kg/m3
5. Mass per Unit Length = 0.94 Kg/m
The Truss members were also Checked using SKYCIV software so the stress report of the
SKYCIV is given as follows:
Beam Deflection of Internal Beam
Beam Specification for Internal Beam
1. MS Pipe 18 gauge
2. Thickness = 1.2 mm
3. Outer Dimensions = 1.5” * 1.5” = 40 mm * 40 mm
4. Mild Steel Density = 7850 kg/m3
5. Mass per Unit Length = 0.94 Kg/m
Load of the Beam =0.94 * 9.81 N/m
Load of the Beam = 9.212 N/m
Since Beams are 3.408m apart,
So, line load of Roof on Internal Beams if 1.5’’ * 1.5” pipe is used = 38.5 * 3.048 N/m =
117.348 N/m
So total Load on Internal Beam will be = w = 117.348 + 9.212 N/m
w =126.56 N/m
I = (4.911 * 10^-8) m4 Formula: (I=BH^3/12)
5𝑤𝐿4
Deflection =
384𝐸𝐼
Deflection = 4.83 mm
Design Safety factor = 1.3
Deflection with safety factor = 6.279 mm
Design Allowed Deflection for Dead Load = L/360 = (3.408 * 10^3)/ 360 = 9.5 mm
(International building Code ICB-2000)
6.279 mm < 9.5 mm (Within limits)
Column Buckling Calculations:
Total Number of Columns = 10
Total Load of the Roof along with the trusses and beams = 10,179.015 N
Load on Each Column = 10,179.015 N / 10 = 1,017.9 N
From classic elastic column buckling theory the Euler buckling load is the compressive axial
force necessary to cause lateral instability of a vertical column. The formula for the Euler
buckling load is:
𝜋 2 𝐸𝐼
𝑓𝑐 = − 2
𝐿
Where:
E is Young's modulus,
I is the moment of inertia of the column cross-section,
L is column length.
Figure 10.3. The effect of pressure on the effective force and buckling.
𝜃 = 0.05
Area of Sheet = 3.66 × 0.9 = 3.294
𝐴𝑟𝑒𝑎𝑒𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 = 3.294 × cos (0.05)
𝑨𝒓𝒆𝒂𝒆𝒇𝒇𝒆𝒄𝒕𝒊𝒗𝒆 = 𝟑. 𝟐𝟗𝟑
O&M Building
n
Law
6.1 m
ouse
erh
Vehicle
4.6 m
m
Pow
Entrance
6.1
dge
18.3 m
20
Bri
12.
ess
2m
Acc
m
1.5
6.1
Pedestrian Access
24.4 m
Proposed Parking Shed At Backside of The O&M Building
(Existing & Extension Plan )
O&M Building
awn
6.1 m
eL
ous
d
She
erh
Vehicle
4.6 m
m
Pow
ing
Entrance
6.1
ark
dge
m
18.3 m
gP
20
Bri
12.
stin
ess
Exi
2m
Acc
m
Extension
1.5
6.1
(New)
Pedestrian Access
18.3 m 6.1 m
Proposed Parking Shed At Backside of The O&M Building
(Vehicles Arrangements Plan )
O&M Building
awn
eL
6.1 m
ous
erh
5m
V#14 V#11 V#08
Pow
2.7
Vehicle Entrance
dge
Bri
3.0 m 3.0 m
ess
9Bi rea
V#13 V#10 V#07
kes
Acc
acit ng A
Cap Parki
m
V#05 V#04 V#03 V#02 V#01
y=
V#12 V#09 V#06
6.1
e
Bik
Pedestrian Access
24.4 m
0.407m
G.I Roof Sheets
3.66 m x 0.9 m
(G#26)
40 mm x 40 mm MS
Pipe (G#18) 40 mm Square Edge Beam MS
Pipe (G#18)
2.95 m
2.7 m
100 mm Square MS
Pipe (G#16) G.L
Compacted Earth
0.45 m
0.45 m
6.0 m
Proposed Parking Shed At Backside of The O&M Building
(Foundation Plan )
0.45 m
100 mm Square MS
0.45 m
Pipe (G#16)
Foundation 100 mm Square MS
Concrete 1:2:4 Pipe (G#16)
0.45 m
Compacted
Earth
Foundation 0.45 m
Concrete 1:2:4
Foundation Plan
Foundation Section
Proposed Parking Shed At Backside of The O&M Building
(General Roof Plan )
6.1 m
40 mm MS Square
Pipe (G#18) Internal Beam Deflection
m
=4.83 mm
20
12.
m
6.1
24.40 m
40 mm MS Square Truss
100 mm (G#18) (For Roof)
MS Square 40 mm MS Square
Pipe (G#18) Pipe Internal Beam
(For Column) (G#18)(For Roof)
Proposed Parking Shed At Backside of The O&M Building
(Truss Plan )
24.4m
9.1m
3.0m
40 mm x 40 mm MS 40 mm x 40 mm MS
Pipe (G#18) Pipe (G#18)
100 mm Square MS
Pipe (G#16)