ESTIMATE

JOB: LEVEL/DRESSING OF EXISTING SKID PAD AND CONSTRUCTION OF 3 NEW PADS


FOUNDATION (10'x2'x3.25') GENSET D-398 AT TANK FARM BALKASSAR

SCOPE OF WORK
S/N DESCRIPTION QUANTITY RATE

1 REMOVING OF GI SHEET OF SHED AND INSTALLATION OF I JOB 10,000 PER 1


SHEET AFTER CONSTRUCTION OF FOUNDATION

2 LEVEL AND DRESSING OF EXISTING FOUNDATION 40 CFT 290 PER 1


19.5'x8.08' (AVG. 3" DEPTH)

3 DISMANTLING WITH JACKHAMMER (1.75' DEPTH) = 45 CFT 200 PER 1


3x3'x3'x4'

4 DISMANTLING AND EXCAVATION OF ROCK FLOOR 45 CFT 25 PER 1


(1.75' DEPTH) SIZE = 3'x3'x3'x4'

5 PROVING AND LAYING OF PCC (1:4:8) USING LP 15.00 CFT 290 PER 1
SAND AND MARGALA CRUSH (AVG. 6" DEPTH) SIZE
= 3x2.5'x2.5'x0.5'

6 SUPPY, CUTTING, BENDING AND FIXING OF STEEL 150 KG 300 PER 1


GR 60 BAR SIZE (3/4") INCLUDING USING 18 SWG
BINDING WIRE FOR PLACING REINFORCEMENT IN
POSITION INCLUDING CHAIRS AND SPACER
(SPACING 6" C/C BOTH SIDES)

7 PROVIDING AND LAYING OF RCC (1:2:4) USING LP 70 CFT 420 PER 1


SAND AND MARGALA CRUSH (COMPRESSIVE
STRENGTH 3000 PSI) SIZE = 3x2.5'x2.5'x4'

TOTAL

STATUS: JOB TO BE CARRIED OUT

BALKASSAR DATED NOVEMBER 30 , 2022


MUSHTAQ AHMED
A/E (CIVIL) AYAZ ALI
BALKASSAR SR ENGR (CIVIL)
ON OF 3 NEW PADS
LKASSAR

RATE AMOUNT

JOB 10,000.00

CFT 11,600.00

CFT 9,000.00

CFT 1,125.00

CFT 4,350.00

KG 45,000.00

CFT 29,400.00

OTAL 110,475.00
R ENGR (CIVIL)
Skid Foundation Design
S.N Measurements
o. Description Formula Length(m) Width(m) Quantity Remarks/References
Dimension Area (in m2) according to pump size and available
1 of Pad Length*Width 3.05 0.61 1.86 area on site. Pump Size chart Ref. 1

Depth =
Depth of
3
FootingWeight/Density Weight (Pump and Density of Min Depth of Footing will taken as 0.96m or 38".
of RCC weight) Concrete Area (Weight of Pump = 5645 kg/6 and Concrete 1:2:4
Concrete*Area 4,287 2400 1.86 0.96 weight = 1800 kg/m2)
Weight of pump Area Soil conditions and Weight and Size ratio is ok. See
P (Kpa)= Ref. 2 table.
2 Pressure Weight/Area 5645 1.86 Concrete 3036.6
Punching Depth of Cover
Shear Force/4*D*c Applied Force in N Footing (mm) (mm)
Check (N/mm )2
42,036.0 960.87 50 0.219 Punching Shear 1.562/mm2 < Allowable Stress
4
Strength of Concrete 4N/mm2
Allowable
Allowable Stress (N/mm )
2
Stress
= 0.8(fcu)0.5 25 4

Ref. 1 Ref. 2
Steel Schedule for Skid Foundation
Dimentions
S.No Description Symbol Measurements (m) Remarks
1 Length of Footing X 3.96 13 feet
2 Breadth of Footing Y 1.52 5 Feet
3 Height of Footing h 0.91 3 Feet
4 Dia of Main Bar dm 0.0254 #8 Bar
5 Dia of Distribution Bar dd 0.0127 #4 Bar
6 Spacing of Main Bar Sm 0.152 6 Inches
7 Spacing of Distribution Bar Sd 0.229 9 Inches
8 Concrete Cover c 0.05 2 Inches
Calculations
S.No Description Formula Quantity Remarks
1 Number of Main Bars Nm=(Y/Sm) 10 Number of Bars
2 Number of Dist Bars Nd=(X/Sd) 17 Number of Bars
Main Bar Cutting Length Cm1=[X-2c]+2[h-2c]-2[2dm] 5.39 m
Total Main Bar Cutting Length Top Cm=Nm*Cm1 53.88 m
3 Total Main Bar Cutting Length Bottom Cm=Nm*Cm1 53.88 m
Dist Bar Cutting Length Cd1=[Y-2c]+2[h-2c]-2[2dm] 3.002 m
Total Dist Bar Cutting Length Top Cd=Nd*Cd1 52.02 m
4 Total Dist Bar Cutting Length Bottom Cd=Nd*Cd1 52.02 m
Main Bar Steel (Kg) Top Wm=D2*Cm/162 214.56 Kg
5 Main Bar Steel (Kg) Bottom Wm=D2*Cm/162 214.56 Kg
Dist Bar Steel (Kg) Top Wd=D2*Cd/162 51.79 Kg
6 Dist Bar Steel (Kg) Bottom Wd=D2*Cd/162 51.79 Kg
Total Steel (Kg) 532.70 Kg
Steel Quantity Check
Total Steel >= Min Quantity of Steel So,
1 Quantity of Steel (Min) L*W*h*1%*Density of Steel 416.83 Steel is OK
Steel Schedule for Skid Foundation
Dia: of Bar Weight of 1m
Length of Total Length Total Weight
S.No Bar Type (mm) and Shape of Bar No: of Bars length Bar
Bar(m) of Bar(m) of Bar (Kg)
Spacing (Kg/m)

Main
Reinforcem
25.4 10 Top
1 ent (X- 4.65 37.23 2.24 83.40
(#6bar) 10 Bottom
Bars) Top
and Bottom

Distribution
Reinforcem
12.7 17 Top
2 ent (Y- 2.24 58.24 0.996 58.01
(#4bar) 17 Bottom
Bars) Top
and Bottom

TOTAL 141.41
ESTIMATE
Job: LEVEL/DRESSING OF EXISTING SKID PAD AND CONSTRUCTION OF 3 NEW PADS FOUNDATION
(2.5'x2.5'x4') GENSET D-398 AT TANK FARM BALKASSAR
SCOPE OF WORK
S/N DESCRIPTION QUANTITY RATE AMOUNT

LEVEL AND DRESSING OF EXISTING


FOUNDATION 19.5'X8.08' (AVG. 3"
1 DEPTH) 40 CFT 290 PER 1 CFT 11600
DISMANTLING WITH JACKHAMMER (1.5'
2 DEPTH) = 11'x2.5'x3' 41.25 CFT 200 PER 1 CFT 8250

DISMANTLING AND EXCAVATION OF


ROCK FLOOR (1.5' DEPTH) SIZE =
11'x2.5'x3' 41.25 CFT 25 PER 1 CFT 1031.25

PROVING AND LAYING OF PCC (1:4:8)


USING LP SAND AND MARGALA CRUSH
3 (AVG. 6" DEPTH) SIZE = 1X10'X2'X0.5' 10.00 CFT 290 PER 1 CFT 2900

SUPPY, CUTTING, BENDING AND FIXING


OF STEEL GR 60 BAR SIZE (3/4")
INCLUDING USING 18 SWG BINDING WIRE
FOR PLACING REINFORCEMENT IN
POSITION INCLUDING CHAIRS AND
4 SPACER (SPACING 6" C/C BOTH SIDES) 150 KG 300 PER 1 KG 45000

PROVIDING AND LAYING OF RCC (1:2:4)


USING LP SAND AND MARGALA CRUSH
(COMPRESSIVE STRENGTH 3000 PSI) SIZE
5 = 1X10'X2'X3' 60 CFT 420 PER 1 CFT 25200
TOTAL 93981.25
Steel Schedule for Foundation
Dimentions
S.No Description Symbol Measurements (m) Remarks
1 Length of Footing X 3.96 13 feet
2 Breadth of Footing Y 1.52 5 Feet
3 Height of Footing h 0.91 3 Feet
4 Dia of Main Bar dm 0.01905 #6 Bar
5 Dia of Distribution Bar dd 0.0127 #4 Bar
6 Spacing of Main Bar Sm 0.152 6 Inches
7 Spacing of Distribution Bar Sd 0.152 6 Inches
8 Concrete Cover c 0.102 2 Inches
Calculations
S.No Description Formula Quantity Remarks
1 Number of Main Bars Bottom Nm=(Y/Sm) 10 Number of Bars
2 Number of Main Bars Top Nm=(Y/Sm) 10 Number of Bars
3 Number of Dist Bars Bottom Nd=(X/Sd) 26 Number of Bars
4 Number of Dist Bars Top Nd=(X/Sd) 26 Number of Bars
Main Bar Cutting Length Cm1=[X-2c]+2[h-2c]-2[2dm] 5.10 m
Total Main Bar Cutting Length Bottom Cm=Nm*Cm1 51.03 m
5 Total Main Bar Cutting Length Top Cm=Nm*Cm1 51.03 m
Dist Bar Cutting Length Cd1=[Y-2c]+2[h-2c]-2[2dm] 2.692 m
Total Dist Bar Cutting Length Bottom Cd=Nd*Cd1 69.97 m
6 Total Dist Bar Cutting Length Top Cd=Nd*Cd1 69.97 m
Main Bar Steel (Kg) Bottom Wm=D2*Cm/162 114.32 Kg
7 Main Bar Steel (Kg) Top Wm=D2*Cm/162 50.81 Kg
Dist Bar Steel (Kg) Bottom Wd=D2*Cd/162 156.75 Kg
8 Dist Bar Steel (Kg) Top Wd=D2*Cd/162 69.67 Kg
Total Steel (Kg) 391.55 Kg
Steel Quantity Check
Total Steel >= Min Quantity of Steel So,
1 Quantity of Steel (Min) L*W*h*0.9%*Density of Steel 375.15 Steel is OK
Steel Schedule for 13'x5' RAFT Foundation
Dia: of Bar Total
S. No: of Cut Length Weight of
Bar Type (mm) and Shape of Bar Length of Weight of Steel
No Bars 1 of Bar Bar / ft
Spacing Bars

Main
1 Reinforcement 19.05 (#6bar) 10 16.75 167.44 0.68 114.03
(X-Bars) Bottom

Main
2 Reinforcement 12.7 (#4bar) 10 16.75 167.44 0.30 50.23
(X-Bars) Top

Distribution
3 Reinforcement 19.05 (#6bar) 26 8.83 229.58 0.68 156.34
(Y-Bars) Bottom

Distribution
4 Reinforcement 12.7 (#4bar) 26 8.83 229.58 0.30 68.87
(Y-Bars) Top

TOTAL WEIGHT OF STEEL 389.48


Drawing Schematics
Steel Schedule for Column
Dimentions
S.No Description Symbol Measurements (m) Remarks
1 Length of Footing X 3.05 10 feet
2 Breadth of Footing Y 0.76 2.5 Feet
3 Height of Footing h 2.74 9 Feet
4 Dia of Main Bar 1 dm1 0.01905 #6 Bar
5 Dia of Main Bar 2 dm2 0.0127 #4 Bar
6 Dia of Distribution Bar (Ring) dd 0.009525 #3 Bar
7 Spacing of Main Bar Sm 0.152 6 Inches
8 Spacing of Distribution Bar Sd 0.152 6 Inches
9 Concrete Cover c 0.05 2 Inches
Calculations
S.No Description Formula Quantity Remarks
1 Number of Main Bars X Top (Long Dir) Nm=2*(X/Sm) 40 Number of Bars
2 Number of Main Bars Y Top (Short Dir) Nm=2*(Y/Sm)-2 6 Number of Bars
3 Main Bars #6 Bars 12
4 Main Bars #4 Bars 34
5 Main Bar Cut Length L length+Raft+Dowel 4.88 m
6 Main Bars #6 Bars Total Length 58.54 m
7 Main Bars #4 Bars Total Length 165.85 m
8 Main Bar #6 Bar Steel Weight (Kg) Wm=D2*Cm/162 131.13 Kg
9 Main Bar #4 Bar Steel Weight (Kg) Wm=D2*Cm/162 165.13 Kg
10 Total Rings 12 Number
11 Ring Outer Length 7.47 m
12 Ring Inner 1 Length 5.18 m
13 Ring Inner 2 Length 3.96 m
14 Ring Inner 3 Length 3.96 m
15 Dist Bar Ring Steel (Kg) Wd=D2*Cd/162 138.24 Kg
Total Steel (Kg) 434.50 Kg
Steel Quantity Check
Total Steel >= Min Quantity of Steel So,
1 Quantity of Steel (Min) L*W*h*0.8%*Density of Steel 384.77 Steel is OK
Steel Schedule for 13'x5' RAFT Foundation
Dia: of Bar (mm) No: of Cut Length 1 of Total Length of Weight of Bar /
S.No Bar Type Weight of Steel
and Spacing Bars Bar Bars ft

Main Reinforcement Bar


1 19.05 (#6bar) 12 16.00 192.00 0.68 130.75
X Long and Y Short Dir

Main Reinforcement Bar


2 12.7 (#4bar) 34 16.00 544.00 0.30 163.20
X Long and Y Short Dir

Distribution
Reinforcement Bar
3 9.525 (#3bar) 12 809.67 0.17 137.64
(Rings) (3 Different
Sizes)

TOTAL WEIGHT OF STEEL 431.60