Dated: 19-11-2020

Subject: TMUC Campus H-11/4 Visit for Bill Verification


Dear Sir,
A visit of TMUC H-11 Campus was conducted on 05 th and 11th November, 2020 for the
purpose of 3rd party evaluation as instructed by Mr. Faisal Mushtaq of various
components (Quantity and Quality) on campus site, the evaluation of the following
components was required:
1. Boundary Wall extension (Height increase)
2. Dismantling and fixing of floor tiles
3. Glass Partitions
4. Wood Partition
RE conducted the visit and met campus manager Mr. Ali Raza on site and inspected the
work in their presence. Following are the measurements of the aforementioned
components:

Boundary Wall
S. No. Description Unit Length Height Quantity

Boundary Wall
Extension (With double
inner plaster and outer
1 ft. 154.5 5 772.5 Sft.
single plaster with paint
on both side) - Right
side wall

Boundary Wall
Extension (With double
inner plaster and outer
2 ft. 29.83 5 149.15 Sft.
single plaster with paint
on both side) - Left
side wall

Total Quantity 921.65 Sft.


  Measured on Site      
Note: A portion of outer elevation hasn’t been painted (Left side outer elevation). Campus
supervisor has been informed to complete the task asap.
Addendum: The non-painted portion has been dealt with and has been painted by the
vendor/contractor. Pictures has been attached in the annex.
Glass Partition
S. No. Description Unit Length Height Quantity
1 Waiting Room ft. 22.5 9.25 208.125 Sft.
2 Admission Room ft. 32 10.75 344 Sft.
Total Quantity 552.125 Sft.
  Measured on Site      

Wooden Partition
S. No. Description Unit Length Height Quantity
1 Wooden Partition Lum Sum Quantity 1  
Total Quantity Measured on
1  
  Site      

Floor Tiles
Uni
S. No. Description t Length Width Quantity
Ground Floor
Entrance
Dismantling and
1 ft. 30 6 180 Sft.
removal of old tiles
and installation of
new (2'x2') Tiles
3rd Floor (Room)
D&R of old tiles and
2 ft. 4 12.5 50 Sft.
installation of new
(1'x1') Tiles
3rd Floor (Corridor)
Dismantling and
3 removal of old tiles ft. 49.75 8.83 439.3 Sft.
and installation of
new (2'x2') Tiles
4th Floor (Corridor)
Dismantling and
4 removal of old tiles ft. 10 4 40 Sft.
and installation of
new (2'x2') Tiles
4th Floor (Corridor)
Dismantling and
5 removal of old tiles ft. 36 9 324 Sft.
and installation of
new (2'x2') Tiles
Total Quantity
1033.3 Sft.
  Measured on Site      
Note: It has only been around 10 months since the completion of work but the tiles that were
repaired on the 4th floor and 3rd floor, the surrounding tiles that weren’t replaced are already
showing signs of displacement/debonding (hollow knocking sound when you walk on them).
They should have been inspected properly and redid and repaired along with the rest of the
tiling job in February as well. This practice should be avoided for future maintenance jobs.

Work has been checked on campus site via measurements and quality observations are
mentioned in the notes below the measurement tables. Rate analysis has also been
conducted and found satisfactory.

Kind Regards,

Muhammad Ammad Hassan,


Resident Engineer,
Roots Millennium Schools.
Annex: Pictorial Profile.
Boundary Wall Extension (unpainted patch) on 11th November

Boundary Wall Extension (patch painted) as of 19 th November