ESTIMATE

JOB: LEVEL/DRESSING OF EXISTING SKID PAD AND CONSTRUCTION OF 3 NEW PADS


FOUNDATION (2.5'x2.5'x4') GENSET D-398 AT TANK FARM BALKASSAR

SCOPE OF WORK
S/N DESCRIPTION QUANTITY RATE

1 REMOVING OF GI SHEET OF SHED AND INSTALLATION OF I JOB 10,000 PER 1


SHEET AFTER CONSTRUCTION OF FOUNDATION

2 LEVEL AND DRESSING OF EXISTING FOUNDATION 40 CFT 290 PER 1


19.5'x8.08' (AVG. 3" DEPTH)

3 DISMANTLING WITH JACKHAMMER (2' DEPTH) = 55 CFT 200 PER 1


3x3'x3'x4'

4 DISMANTLING AND EXCAVATION OF ROCK FLOOR 55 CFT 25 PER 1


(2' DEPTH) SIZE = 3'x3'x3'x4'

5 PROVING AND LAYING OF PCC (1:4:8) USING LP 9.50 CFT 290 PER 1
SAND AND MARGALA CRUSH (AVG. 6" DEPTH) SIZE
= 3x2.5'x2.5'x0.5'

6 SUPPY, CUTTING, BENDING AND FIXING OF STEEL 150 KG 300 PER 1


GR 60 BAR SIZE (3/4") INCLUDING USING 18 SWG
BINDING WIRE FOR PLACING REINFORCEMENT IN
POSITION INCLUDING CHAIRS AND SPACER
(SPACING 6" C/C BOTH SIDES)

7 PROVIDING AND LAYING OF RCC (1:2:4) USING LP 80 CFT 420 PER 1


SAND AND MARGALA CRUSH (COMPRESSIVE
STRENGTH 3000 PSI) SIZE = 3x2.5'x2.5'x4'

TOTAL

STATUS: JOB TO BE CARRIED OUT

BALKASSAR DATED NOVEMBER 30 , 2022


MUSHTAQ AHMED
A/E (CIVIL) AYAZ ALI
BALKASSAR SR ENGR (CIVIL)
ON OF 3 NEW PADS
LKASSAR

RATE AMOUNT

JOB 10,000.00

CFT 11,600.00

CFT 11,000.00

CFT 1,375.00

CFT 2,755.00

KG 45,000.00

CFT 33,600.00

OTAL 115,330.00
R ENGR (CIVIL)
ESTIMATE
Job: LEVEL/DRESSING OF EXISTING SKID PAD AND CONSTRUCTION OF 3 NEW PADS FOUNDATION
(2.5'x2.5'x4') GENSET D-398 AT TANK FARM BALKASSAR
SCOPE OF WORK
S/N DESCRIPTION QUANTITY RATE AMOUNT

LEVEL AND DRESSING OF EXISTING


FOUNDATION 19.5'X8.08' (AVG. 3"
1 DEPTH) 40 CFT 290 PER 1 CFT 11600
DISMANTLING WITH JACKHAMMER (2'
2 DEPTH) = 3X3'X3'X4' 55 CFT 200 PER 1 CFT 11000

DISMANTLING AND EXCAVATION OF


ROCK FLOOR (2' DEPTH) SIZE = 3X3'X3'X4' 55 CFT 25 PER 1 CFT 1375

PROVING AND LAYING OF PCC (1:4:8)


USING LP SAND AND MARGALA CRUSH
3 (AVG. 6" DEPTH) SIZE = 3X2.5'X2.5'X0.5' 9.50 CFT 290 PER 1 CFT 2755

SUPPY, CUTTING, BENDING AND FIXING


OF STEEL GR 60 BAR SIZE (3/4")
INCLUDING USING 18 SWG BINDING WIRE
FOR PLACING REINFORCEMENT IN
POSITION INCLUDING CHAIRS AND
4 SPACER (SPACING 6" C/C BOTH SIDES) 150 KG 300 PER 1 KG 45000

PROVIDING AND LAYING OF RCC (1:2:4)


USING LP SAND AND MARGALA CRUSH
(COMPRESSIVE STRENGTH 3000 PSI) SIZE
5 = 3X2.5'X2.5'X4' 75 CFT 420 PER 1 CFT 31500
TOTAL 103230
Steel Schedule for Skid Foundation
Weight of 1m
Dia: of Bar Length of Total Length Total Weight
S.No Bar Type Shape of Bar No: of Bars length Bar
(mm) Bar(m) of Bar(m) of Bar (Kg)
(Kg/m)

Main
Reinforcem
19.05
1 ent (X- 5 3.24 32.36 2.24 72.48
(#6bar)
Bars) Top
and Bottom

Distribution
Reinforcem
19.05
2 ent (Y- 5 3.24 32.88 2.24 73.66
(#6bar)
Bars) Top
and Bottom

TOTAL 146.13