DAILY PROGRESS REPORT
Presented in table 1.1 are corresponding the progress of ongoing activities on Block 04,
Lot no. 29-30. Currently the activity “Tile Work” has been completed.

Manpower Report: Block 04, Lot no. 29-30 Date: September 6, 2022
  Current Activities Manpower % Completion
1 Exterior Roof Ceiling Board Installation 2 45%
2 Tile Work 2 100%
3 Exterior Skim Coat Application 2 25%
TABLE 1.1

Presented in table 1.2 are corresponding the progress of ongoing activities on Block 06,
Lot no. 35-36. Currently the activity “Panel Board Adjustment” has been completed.

Manpower Report: Block 06, Lot no. 35-36 Date: September 5, 2022

Current Activities Manpower % Completion


1 Skim Coat Application (2nd Floor) 1 85%
2 Panel Board Adjustment 1 100%
3 Kitchen Sink 2 15%
TABLE 1.2

Presented in table 1.3 are corresponding the progress of ongoing activities on Block 06,
Lot no. 29-30. Currently, the activity “Kitchen Sink” is ongoing with a progress of 25% to
completion.

Manpower Report: Block 06, Lot no. 29-30 Date: September 5, 2022

Current Activities Manpower % Completion


1 Kitchen Sink 2 25%
TABLE 1.3