K2 JHR01 – 03 : CLS

DAILY SITE REPORT


Date : 08th January 2024
• DAILY MANPOWER

Working time 0800 – 0000 Weather Fine Raining Time -


Manpower Records Machinery Records
Project Manager 1 BIM Modeler 1 Machinery operator 3 Mobile crane 1
Site Manager 1 Planner 1 General Worker 25 Excavator 1
Project Engineer 1 QA/QC 2 Carpenter 20 Lorry -
Fire retardant Backhoe -
Safety Officer 1 8 Bar Bender 19
painter Sky lift -
Site Supervisor 1 Brick work 24 M&E 3 Scissor lift 1
Safety Supervisor 1 Bondek Installer 7
Subcon Supervisor 5
Total 124
ACTIVITY
• Shear stud installation at 1st floor zone 3 Remarks:
• BRC laying for 1st floor slab at zone 3
• Bricklaying works at 1st floor zone 2
• Erecting scaffolding for brick laying works at 1st floor
• Fire retardant painting works at ground floor zone 3
• Fire retardant painting works at ground floor zone 4
• Concreted 1.35m RC Wall for blast wall 2-1
DAILY SITE PROGRESS REPORT
Bondek Installation (First Floor)

Table Legend:
Bondek
Area (m2):
2264/3002 (75%)
DAILY SITE PROGRESS REPORT
Bondek Installation (Upper Roof)

Table Legend:
Bondek
Area (m2):
847/1410 (80%)
DAILY SITE PROGRESS REPORT
Bondek Installation (Lower Roof)

Table Legend:
Bondek
Area (m2):
0/1592 (0%)
DAILY SITE PROGRESS REPORT
Ground Floor Slab Progress Layout
Table Legend:
Concreted
Zone 1
BRC laying
Concreted area (m2):
3002/3002 (100%)
Zone 2
SCHEDULE PLAN
16/12/23 22/12/23

Zone 3

Zone 4
DAILY SITE PROGRESS REPORT
First Floor Slab Progress Layout

Table Legend:
Concreted
BRC laying
Zone 1
Concreted area (m2):
827/3002 (28%)
Zone 2 SCHEDULE PLAN
21/12/23 08/01/24

Zone 3

Zone 4
DAILY SITE PROGRESS REPORT
Upper Roof Slab Progress Layout

Table Legend:
Concreted
BRC laying
Concreted area (m2):
956/1410 (68%)

Zone 1 SCHEDULE PLAN


15/12/23 15/01/24

Zone 2
DAILY SITE PROGRESS REPORT
Lower Roof Slab Progress Layout

Table Legend:
Concreted
BRC laying
Concreted area (m2):
Zone 3
0/1592 (0%)

SCHEDULE PLAN
25/12/23 10/01/24

Zone 4
DAILY SITE PROGRESS REPORT
Steel Structure Layout (Upper Roof Floor)

Table Legend:
Steel Column
I-Beam
Beam: 85/97 (88%)
Note:
12 members highlighted
(red) is to be installed after
overhead crane installed
DAILY SITE PROGRESS REPORT
Steel Structure Progress

PLAN VS PLAN VS
PLAN QTY ACTUAL QTY PLAN QTY ACTUAL QTY
DATE CUMULATIVE ACTUAL / DATE CUMULATIVE ACTUAL /
/NOS /NOS /NOS /NOS
NOS NOS
27/10/23 17 14 -3 -3 7/11/23 18 0 -53 -53
28/10/23 17 15 -20 -5 8/11/23 18 0 -71 -71
29/10/23 17 13 -22 -9 9/11/23 18 0 -89 -89
30/10/23 17 10 -26 -16 10/11/23 18 0 -107 -107
31/10/23 17 12 -33 -21 11/11/23 18 9 -125 -116
1/11/23 17 15 -38 -23 12/11/23 18 11 -134 -123
2/11/23 17 18 -40 -22 13/11/23 19 28 -142 -114
3/11/23 17 15 -39 -24 14/11/23 19 12 -133 -121
4/11/23 17 15 -41 -26 15/11/23 19 28 -140 -112
5/11/23 17 3 -43 -40 16/11/23 19 8 -131 -123
6/11/23 17 22 -57 -35 17/11/23 19 22 -142 -120
DAILY SITE PROGRESS REPORT
Steel Structure Progress

ACTUAL PLAN VS MITIGATIO ACTUAL PLAN VS


PLAN QTY CUMULATI PLAN QTY CUMULATI
DATE QTY ACTUAL / DATE N QTY ACTUAL /
/NOS VE /NOS VE
/NOS NOS PLAN/QTY /NOS NOS
18/11/23 19 10 -139 -129 28/11/23 21 31 39 -113 -74
19/11/23 20 30 -149 -119 29/11/23 21 31 29 -95 -52
20/11/23 20 34 -139 -105 30/11/23 21 31 37 -87 -46
21/11/23 20 13 -125 -112 1/12/23 21 29 41 -71 -34
22/11/23 20 19 -132 -113 2/12/23 22 29 32 -52 -31
23/11/23 20 13 -133 -120 3/12/23 22 29 36 -42 -6
24/11/23 20 21 -140 -119 4/12/23 22 29 38 -28 (10)
25/11/23 21 38 -140 -102 5/12/23 22 29 20 -12 (8)
26/11/23 21 31 -123 -92 6/12/23 22 29 18 -14 (4)
27/11/23 21 21 -113 -92 7/12/23 22 29 6 -18 -12
TOTAL: 808 796 -12
DAILY SITE PROGRESS REPORT
Blast Wall Layout

Structure Progress Structure Progress


BW 1-1 Footing 100% Footing 100% BW 2-1
Wall 7% Wall 7%

Structure Progress Structure Progress


BW 1-2 Footing 100% Footing 100% BW 2-2
Wall 7% Wall 7%

Structure Progress Structure Progress


BW 1-3 Footing 100% Footing 100% BW 2-3
Wall 7% Wall 7%

Structure Progress Structure Progress


BW 1-4 Footing 0% Footing 100% BW 2-4
Wall 0% Wall 7%
DAILY SITE PROGRESS REPORT
Blast wall Progress

PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
17/10/23 0 0 0 30/10/23 14 0 -104
18/10/23 0 0 0 31/11/23 90 0 -194
19/10/23 0 0 0 1/11/23 0 0 -194
20/10/23 90 0 -90 2/11/23 20 90 -124
21/10/23 0 0 -90 3/11/23 30 0 -154
22/10/23 0 0 -90 4/11/23 0 90 -65
23/10/23 0 0 -90 5/11/23 30 0 -95
24/10/23 0 90 0 6/11/23 0 0 -95
25/10/23 30 0 -30 7/11/23 0 30 -64
26/10/23 0 0 -30 8/11/23 14 0 -78
27/10/23 0 0 -30 9/11/23 3 30 -51
28/10/23 0 0 -30 10/11/23 14 0 -65
29/10/23 90 30 -90 11/11/23 20 0 -85
DAILY SITE PROGRESS REPORT
Blast wall Progress

PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
12/11/23 11 0 -96 25/11/23 23 0 -420
13/11/23 20 0 -116 26/11/23 20 0 -440
14/11/23 0 0 -116 27/11/23 0 0 -440
15/11/23 110 0 -226 28/11/23 40 0 -480
16/11/23 0 0 -226 29/11/23 30 90 -420
17/11/23 0 0 -226 30/11/23 0 0 -420
18/11/23 3 0 -229 1/12/23 93 0 -513
19/11/23 0 0 -229 2/12/23 0 0 -513
20/11/23 33 0 -262 3/12/23 3 0 -516
21/11/23 11 0 -273 4/12/23 26 0 -542
22/11/23 3 0 -276 5/12/23 3 0 -545
23/11/23 11 0 -287 6/12/23 39 0 -584
24/11/23 110 0 -397 7/12/23 40 0 -624
DAILY SITE PROGRESS REPORT
Blast wall Progress

PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
8/12/23 11 0 -635 21/12/23 26 0 -808
9/12/23 20 0 -655 22/12/23 0 0 -808
10/12/23 0 0 -655 23/12/23 0 0 -808
11/12/23 124 0 -779 24/12/23 51 0 -859
12/12/23 0 0 -779 25/12/23 0 0 -859
13/12/23 3 0 -782 26/12/23 0 0 -859
14/12/23 23 0 -805 27/12/23 23 120 -762
15/12/23 3 0 -808 28/12/23 0 0 -762
16/12/23 30 0 -838 29/12/23 90 0 -852
17/12/23 11 0 -849 30/12/23 12 90 -751
18/12/23 3 0 -852 31/12/23 3 0 -754
19/12/23 0 90 -762 1/1/24 0 0 -754
20/12/23 20 0 -782 2/1/24 20 30 -744
DAILY SITE PROGRESS REPORT
Blast wall Progress

PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
3/1/24 44 0 -788 16/1/24 9
4/1/24 0 0 -788 17/1/24 0
5/1/24 0 30 -758 18/1/24 3
6/1/24 29 0 -816 19/1/24 20
7/1/24 0 0 -816 20/1/24 0
8/1/24 17 0 -833 21/1/24 11
9/1/24 20 22/1/24 0
10/1/24 0 23/1/24 0
11/1/24 20 24/1/24 20
12/1/24 0 25/1/24 3
13/1/24 3 26/1/24 0
14/1/24 0 27/1/24 0
15/1/24 3 28/1/24 0
DAILY SITE PROGRESS REPORT
Blast wall Progress

PLAN QTY ACTUAL QTY PLAN VS ACTUAL PLAN QTY ACTUAL QTY PLAN VS ACTUAL
DATE DATE
/VOL /VOL / VOL /VOL /VOL / VOL
29/1/24 0 6/2/24 20
30/1/24 0 7/2/24 0
31/1/24 3 8/2/24 0
1/2/24 0 9/2/24 0
2/2/24 0 10/2/24 0
3/2/24 9 11/2/24 0
4/2/24 0 12/2/24 3
5/2/24 0
TOTAL: -1,784m3 810m3 -974m3
DAILY SITE PROGRESS REPORT
Brick Wall Progress

BRICK WALL PROGRESS SUMMARY (8/1/24)


GROUND FLOOR
ZONE TOTAL AREA (M2) AREA WORK DONE (M2) PROGRESS
1 286 228 80%
2 202 202 100%
3 197 176 89%
4 345 206 60%
AVERAGE PROGRESS: 82%
FIRST FLOOR
ZONE TOTAL AREA (M2) AREA WORK DONE (M2) PROGRESS
1 1116 176 16%
2 1477 80 5%
3 937 0 0%
4 492 0 0%
AVERAGE PROGRESS: 5.31%
DAILY SITE PROGRESS REPORT
Cable Trench Progress Layout

Progress:
Cable trench
BW 1-1 BW 2-1 installation:
(147m/326m)
45.09%

BW 1-2 BW 2-2

BW 1-3 BW 2-3

BW 1-4 BW 2-4
DAILY SITE PROGRESS REPORT
Copper Tape Installation (Ground Floor Layout)

TABLE LEGEND:
Copper tape installed
DAILY SITE PROGRESS REPORT
Copper Tape Installation (First Floor Layout)

TABLE LEGEND:
Copper tape installed
DAILY SITE PROGRESS REPORT
Daily Planning (09/01/2024)

Civil, Structure & Architecture:


No. Trade Location/Zone Remark
1. Fire Retardant painting works Zone 3 Ground Floor
2. Bondek Installation Zone 4 1st Floor
3. Brick laying Zone 4 Ground floor
4. Brick laying Zone 1 & Zone 2 First floor
5. Formwork and rebars installation for stiffeners Zone 1 & Zone 2 Ground Floor
6. Formwork and rebars installation for stiffeners Zone 1 & Zone 2 1st Floor
7. Concreting stiffeners Zone 1 & Zone 2 1st Floor
BW1-4
8. Formwork & Rebars installation for walls
BW1-2
10. Excavation TX3 Footing TX3
11. BRC laying at 1st floor slab zone 4 Zone 4 1st floor
DAILY SITE PROGRESS REPORT
Daily Planning (09/01/2024)

Mechanical & Electrical


No. Trade Location/Zone Remark
1. Cable laying works Consumer/SSU
3
1
2

4
Bird View 1
Bird View 2
Bird View 3
Bird View 4
• PROGRESS PHOTO

• Bricklaying works at 1st floor zone 1


• PROGRESS PHOTO

• Bricklaying works at 1st floor zone 1


• PROGRESS PHOTO

• Bricklaying works at 1st floor zone 1


• PROGRESS PHOTO

• Copper tape installation at 1st floor zone 3


• PROGRESS PHOTO

• End cap installation work at first floor zone 3


• PROGRESS PHOTO

• Shear stud installation at 1st floor zone 3


• PROGRESS PHOTO

• Installation signages at 33kv SSU


• PROGRESS PHOTO

• Concreting works at 1st floor zone 3


• PROGRESS PHOTO

• Bondek installation at 1st floor zone 4


• PROGRESS PHOTO

• Fire retardant painting works at ground floor zone 3


• PROGRESS PHOTO

• Plastering works at ground floor zone 2


• PROGRESS PHOTO

• Excavation works for tx3


• PROGRESS PHOTO

• Formwork installation for RC column at blast wall 2-1


• PROGRESS PHOTO

• Concreting works for stiffeners at ground floor zone 4


• PROGRESS PHOTO

• Laying control cable at consumer switchgear