Project Execution Process

Level 1
Engineering & Delivery Level 2 Level 3 Pre- Level 4
Kick Off Raw Material Production Internal Factory
Document Preparation & Installation Turn on Test & Integrated Level 5
Meeting Preparation Process Testing Acceptance
Approval Delivery Inspection Inspection System Test Handover
Test
Detail Execution Process
 Kick Off Meeting
Project Plan is reviewed and team gets clarify on technical, commercial, scope of
work and responsibilities

Date : Aug 02, 2023

 Engineering & Document Approval Process


Stage for submission approval process for all drawing, specification and
procedures to define BoQ and production process reference. All these document
need minimum B Status (Approved with minor comments)

Date : Aug 04, 2023 – Aug 11, 2023

 Raw Material Preparation


Raw material order process based on approved Drawing & Datasheet /
Specification

Date :
- JHR01-JHR02 : Aug 8 – Nov 24, 2023
- JHR03 : Aug 8 – Jan 08, 2024
Detail Execution Process
 Production Process
Production process in electrical & mechanical, vacuum, core coil and tank
assembly. This stage will start after all material for electrical & mechanical
complete received at warehouse.

Date :
- JHR 01-02 : Oct 02 - Nov 10, 2023
- JHR 03 : Nov 27 – Dec 18, 2023
 Internal Testing
After all production process finish, this internal test should be conduct to
measure all required technical specification & the function is running well

 Level 1 Factory Acceptance Test (Witnessed)


Process that evaluates the equipment during and after the assembly process by
verifying that it is built and operating in accordance with design specifications
and shall be witnessed by client/user for acceptance.

Date :
- Tx 2.5 MVA & 3.5 MVA : Nov 6-10, 2023 (1 unit)
- Tx 40 MVA : Nov 27-30, 2023 (1 unit)
Detail Execution Process
 Delivery Preparation & Delivery
Stage for final QC check, packing process, and coordinate with all parties
(shipping line & trucking/forwarder) for all documents needed in clearance
process. For this project we will arrange partial delivery for all equipment.

Date :
JHR01-02 (1st Shipment) : Dec 15, 2023 (ETA on Site)
JHR01-02 (2nd Shipment) : Jan 05, 2023 (ETA on Site)
JHR03 : Mar 05, 2023 (ETA on Site)

 Level 2 Installation Inspection


Re-assembly process for all dismantle part of MV transformer, oil purification,
visual check and function test. For the power skid system (Tx + RMU),we will
install complete skid into foundation and prepare the equipment for visual check
& function test.

Date :
JHR01-02 : Jan 18, 2024
JHR03 : Apr 15, 2024
Detail Execution Process
 Level 3 Pre-Turn on Test & Inspection
Pre-commissioning and commissioning occur after construction and installation,
and before the facility or asset is put into operation. (Pre-)commissioning involves
various activities to ensure all systems and components of the facility are properly
installed, tested, and ready for operation.

Date :
JHR01-02 : Apr 16, 2024
JHR03 : Oct 21, 2024

 Level 4 Integrated System Test


Completion of all test required for transformers, MV Sub Pods and RMU to be
integrated and get approved certificate from consultants and K2 (End User).

Date :
JHR01-02 : May 20, 2024
JHR03 : Nov 18, 2024
Detail Execution Process
 Level 5 Handover
Final tests that include all systems working together as designed. Numerous tests
will occur to create a comprehensive test routine and is added into the Operations
& Maintenance Manuals (O&M).

Date :
JHR01-02 : May 24, 2024
JHR03 : Nov 22, 2024