Professional Documents
Culture Documents
Commissioning in principle is a process that documents, tests and validates design results, or in other words a
quality-oriented process to achieve, verify and document the performance of facilities, systems and assemblies
to meet the specified objectives and criteria.
Whatever the form of the project being implemented, it will carry out testing and commissioning of the
equipment and systems installed on the project. The data center project is no exception.
In data centers in most cases wherever there will be project requirements for commissioning and this is divided
into 5 stages (level /Cx) as follows:
Level 2 – Site Acceptences Test Site Acceptences Test (SAT) / Component L2 Script, Equipmet
(SAT) / Verifikasi Komponen dan Verification and Pre-Installation Checks Installation, Verification
Pemeriksaan Pra-Instalasi Is the process of ensuring that equipment And QC/QA Actifity,
brought to the site meets end user Yellow Tag
specifications prior to entering the facility
Once these checks have been completed, a
'Storage Check and Pre-Installation Check'
should be completed to ensure project
processes are adhered to and documented.
Level 4 – Component / System Level 4, this is additional testing of the L4 Script, Point-To-Point,
Fuction Performance Tested equipment to ensure that the equipment is Standart of Operatonal
functioning as designed and that the fault (SoO), Report Tested,
system (Fault/Alarm) is properly integrated Blue Tag
Level 5 – Integration System Final test that includes all systems working L5 Script, Standart of
Testing together as designed. Various tests will be Operation (SoO), Report
performed to establish a comprehensive test Tested. White Tag
routine and added to the Operations &
Maintenance (O&M) Manual