Professional Documents
Culture Documents
4, 5, 6 & 7 Levels of
Commissioning
Summarized
August 7, 2022 | Bob Morris
When we look at commissioning a data center, in most cases,
there will be a project requirement to structure the process into
five stages, commonly referred to as ‘Levels.’ So what are the 5
levels of commissioning?:
Level 0 – NO TAG
Level 1 – RED TAG
Level 2 – YELLOW TAG
Level 3 – GREEN TAG
Level 4 – BLUE TAG
Level 5 – WHITE TAG
Level 6 – NO TAG
Level 7 – NO TAG
If want to see a typical checklist for commissioning a data center checkout our article DATA CENTER |
Commissioning Checklist
Level 0 – Design and Planning
This is the start of the levels and would equate to the pre-design /
design stage responsibilities within the standard commissioning
process.
After these checks have been completed a ‘Storage Check and Pre-
Installation Check’ should be completed to ensure the project
process is adhered to and documented.
These checks are usually recorded via checksheets and form part of
the overall process.
We have written more on delivery checks in our article 3 Types of Commissioning Checklists, in the section
for the construction checks, we cover the delivery requirements for various systems and equipment.
The equipment will be provided with a YELLOW TAG to verify level
completion and signed by the contractor/vendor, designer, and
commissioning agent.
To read our 8 STEP GUIDE for delivering Level 2, see our article | LEVEL 2 – DATA CENTER
COMMISSIONING | Component Delivery
Once the system has been verified to have been installed correctly,
the pre-commissioning / pre-functional and startup testing should
occur.
All should be fully documented and form part of the overall
structured process.
Huge, huge amount of work and why it is paramount that this level
is planned out very early within the project. Anything hanging over
from the previous levels could seriously impact, so best to have
them all completed and signed off before moving to this step.
During this level, the focus will be on proving that all systems can
work together and meet the expected design and project
requirements.
The testing will usually cover the Mechanical Systems, known as the
‘Heat Load Test,’ and the Electrical Systems, known as ‘Electrical
Integrated Testing.’
The client should accept the documentation and that the project
has been fully delivered and handed over.