UNIT-V

Testing Process, Eleven Step Testing Process: Assess Project Management Development
Estimate and Status, Develop Test Plan, Requirements Phase Testing, Design Phase Testing,
Program Phase Testing, Execute Test and Record Results, Acceptance Test, Report Test Results,
Testing Software Installation, Test Software Changes, Evaluate Test Effectiveness, Testing
Specialized Systems and Applications, Testing Client/Server, Web Applications, Testing off the
Shelf Components, Testing Security, Testing a Data Warehouse.

THE ELEVEN STEP TESTING PROCESS:


The software testing process example, as illustrated in Figure 19, is an 11-step testing
process that follows the “V” concept of testing. The “V” represents both the software
development process and the 11-step software testing process. The first five steps use
verification as the primary means to evaluate correctness of interim development deliverables.
Validation is used to test the software in an executable mode. Results of both verification and
validation should be documented. Both verification and validation will be used to test the
installation of the software as well as changes to the software. The final step of the “V” process
represents both the development and test team evaluating the effectiveness of testing.

Step 1: Assess Development Plan and Status


Step 2: Develop the Test plan
Step 3: Test Software Requirements
Step 4: Test Software Design
Step 5: Test Software Construction
Step 6: Execute Tests
Step 7: Acceptance Test
Step 8: Report Test results
Step 9: Test Software Installation
Step 10: Test Software Changes
Step 11: Evaluate the test Effectiveness

1
2
Step 1: Assess Development Plan and Status: This first step is a prerequisite to
building the VV&T Plan used to evaluate the implemented software solution. During this step,
testers challenge the completeness and correctness of the development plan. Based on the
extensiveness and completeness of the Project Plan the testers can estimate the amount of
resources they will need to test the implemented software solution.

Step 2: Develop the Test Plan: Forming the plan for testing will follow same pattern as
any software planning process. The structure of all plans should be same, but content will vary
based on the degree of risk the testers perceive as associated with the software being developed.

Step 3: Test Software Requirements: Incomplete, inaccurate, or inconsistent


requirements lead to most software failures. The inability to get requirements right during the
requirements gathering phase can also increase the cost of implementation significantly. Testers,
through verification, must determine that the requirements are accurate, complete, and they do
not conflict with one another.

Step 4: Test Software Design: This step tests both external and internal design primarily
through verification techniques. The testers are concerned that the design will achieve the
objectives of the requirements, as well as the design being effective and efficient on the
designated hardware.

Step 5: Program (Build) Phase Testing: The method chosen to build the software from
the internal design document will determine the type and extensiveness of tests needed. As the
construction becomes more automated, less testing will be required during this phase. However,
if software is constructed using the waterfall process, it is subject to error and should be verified.
Experience has shown that it is significantly cheaper to identify defects during the construction
phase, than through dynamic testing during the test execution step.

Step 6: Execute and Record Results: This involves the testing of code in a dynamic
state. The approach, methods, and tools specified in test plan will be used to validate that the
executable code in fact meets stated S/W requirements, and structural specifications of design.

Step 7: Acceptance Test: Acceptance testing enables users to evaluate the applicability and
usability of the software in performing their day-to-day job functions. This tests what the user
believes the software should perform, as opposed to what the documented requirements state the
software should perform.

Step 8: Report Test Results: Test reporting is a continuous process. It may be both oral
and written. It is important that defects and concerns be reported to the appropriate parties as
early as possible, so that corrections can be made at the lowest possible cost.

3
Step 9: The Software Installation: Once the test team has confirmed that software is
ready for production use, ability to execute that software in a production environment should be
tested. This tests the interface to operating software, related software, and operating procedures.

Step 10: Test Software Changes: While this is shown as Step 10, in the context of
performing maintenance after the software is implemented, the concept is also applicable to
changes throughout the implementation process. Whenever requirements change, the test plan
must change, and the impact of that change on software systems must be tested and evaluated.

Step 11: Evaluate Test Effectiveness: Testing improvement can best be achieved by
evaluating the effectiveness of testing at the end of each software test assignment. While this
assessment is primarily performed by the testers, it should involve the developers, users of the
software, and quality assurance professionals if the function exists in the IT organization.

TESTING CLIENT/SERVER SYSTEMS:


The success of a client/server program depends heavily on both the readiness of an
organization to use the technology effectively and its ability to provide clients the information
and capabilities that meet their needs. If an organization is not ready to move to client/server
technology, it is far better to work on changing the organization to a ready status than on
installing client/server technology. Preparing the organization for client/server technology is an
important component of a successful program, regardless of whether it is an organization-wide
client/server technology or just a small program. If the organization is ready, the client/server
approach should be evaluated prior to testing the client systems.

Overview: Figure 15-1 shows simplified client/server architecture. There are many possible
variations of the client/server architecture, but for illustration purposes, this is representative. In
this example, application software resides on the client workstations. The application server
handles processing requests. The back-end processing (typically a mainframe or super-
minicomputer) handles processing such as batch transactions that are accumulated and processed
together at one time on a regular basis. The important distinction to note is that application
software resides on the client workstation.

Figure 15-1 shows the key distinction between workstations connected to the mainframe and
workstations that contain the software used for client processing. This distinction represents a
major change in processing control. For this reason, client/server testing must first evaluate the
organization’s readiness to make this control change, and then evaluate the key components of
the client/server system prior to conducting tests.

This topic will provide the material on assessing readiness and key components. The actual
testing of client/server systems will be achieved using the seven-step testing process.

4
Concerns: The concerns about client/server systems reside in the area of control. The testers
need to determine that adequate controls are in place to ensure accurate, complete, timely, and
secure processing of client/server software systems. The testers must address the following five
concerns:

1. Organizational Readiness: The culture is adequately prepared to process data using


client/server technology. Readiness must be evaluated in the areas of management, client
installation, and server support.
2. Client Installation: The concern is that the appropriate hardware and software will be in
place to enable processing that will meet client needs.
3. Security: There is a need for protection of both the hardware, including residence software,
and the data that is processed using that hardware and software. Security must address threats
from employees, outsiders, and acts of nature.
4. Client Data: Controls must be in place to ensure that everything is not lost, incorrectly
processed, or processed differently on a client workstation than in other areas of the
organization.
5. Client/Server standards: Standards must exist to ensure that all client workstations operate
under the same set of rules.

5
Workbench: Figure 15-2 provides a workbench for testing client/server systems. This
workbench can be used in steps as the client/server system is developed or concurrently after the
client/server system has been developed. The workbench shows four steps, as well as the quality
control procedures necessary to ensure that those four steps are performed correctly. The output
will be any identified weaknesses uncovered during testing.

Input: The input to this test process will be the client/server system. This will include the
server technology and capabilities, the communication network, and the client work stations that
will be incorporated into the test. Because both the client and the server components will include
software capabilities, the materials should provide a description of the client software, and any
test results on that client software should be input to this test process.

Do Procedures: Testing client/server software involves the following three tasks:


1. Assess readiness
2. Assess key components
3. Assess client needs

TESTING A DATA WAREHOUSE:


A data warehouse is a central repository of data made available to users. The centralized storage
of data provides significant processing advantages but at the same time raises concerns of the
data’s security, accessibility, and integrity. This topic focuses on where testing would be most
effective in determining the risks associated with those concerns.

Overview: This testing process lists the more common concerns associated with the data ware
house concept. It also explains the more common activities performed as part of a data
warehouse. Testing begins by determining the appropriateness of those concerns to the data
warehouse process under test. If appropriate, the severity of the concerns must be determined.

6
This is accomplished by relating those high-severity concerns to the data warehouse activity
controls. If in place and working, the controls should minimize the concerns.
Concerns: The following are the concerns most commonly associated with a data warehouse:
 Inadequate assignment of responsibilities: There is inappropriate segregation of duties or
failure to recognize placement of responsibility.
 Inaccurate or incomplete data in a data warehouse: The integrity of data entered in the
data warehouse is lost because of inadvertent or intentional acts.
 Losing an update to a single data item: One or more updates to a single data item can be
lost because of inadequate concurrent update procedures.
 Inadequate audit trail to reconstruct transactions: The use of data by multiple
applications may split the audit trail among those applications and the data warehouse
software audit trail.
 Unauthorized access to data in a data warehouse: The concentration of data may make
sensitive data available to anyone who gains access to the data warehouse.
 Inadequate service level: Multiple users vying for the same resources may degrade the
service to all because of excessive demand or inadequate resources.
 Placing data in the wrong calendar period: Identifying transactions with the proper
calendar period is more difficult in some online data warehouse environments than in others.
 Failure of data warehouse software to function as specified: Vendors provide most data
warehouse software, making the data warehouse administrator dependent on the vendor to
ensure the proper functioning of the software.
 Improper use of data: Systems that control resources are always subject to misuse and
abuse.
 Lack of skilled independent data warehouse reviewers: Most reviewers are not skilled in
data warehouse technology and, thus, have not evaluated data warehouse installations.
 Inadequate documentation: Documentation of data warehouse technology is needed to
ensure consistency of understanding and use by multiple users.
 Loss of continuity of processing: Many organizations rely heavily on data warehouse
technology for the performance of their day-to-day processing.
 Lack of criteria to evaluate: Without established performance criteria, an organization
cannot be assured that it is achieving its data warehouse goals.
 Lack of management support: Without adequate resources and “clout,” the advantages of
data warehouse technology may not be achieved.

Workbench: Figure 21-1 illustrates the workbench for testing the adequacy of the data
warehouse activity. The workbench is a three-task process that measures the magnitude of the
concerns, identifies the data warehouse activity processes, and then determines the tests
necessary to determine whether the high-magnitude concerns have been adequately addressed.
Those performing the test must be familiar with the data warehouse activity processes. The end
result of the test is an assessment of the adequacy of those processes to minimize the high-
magnitude concerns.

7
Input: Organizations implementing the data warehouse activity need to establish processes to
manage, operate, and control that activity. The input to this test process is knowledge of those
data warehouse activity processes. If the test team does not have that knowledge, it should be
supplemented with one or more individuals who possess a detailed knowledge of the data
warehouse activity processes.

Enterprise-wide requirements are data requirements that are applicable to all software systems
and their users. Whenever anyone accesses or updates a data warehouse, that process is subject
to the enterprise-wide requirements. They are called enterprise wide requirements because they
are defined once for all software systems and users. Each organization must define its own
enterprise-wide controls. However, testers should be aware that many IT organizations do not
define enterprise-wide requirements. Therefore, testers need to be aware that there may be
inconsistencies between software systems and/or users. For example, if there are no security
requirements applicable enterprise-wide, each software system may have different security
procedures.
Enterprise-wide requirements applicable to data warehouse include and not limited to following:
 Data Accessibility: Who has access to the data warehouse, and any constraints or limitations
placed on that access.
 Update Controls: Who can change data within the data warehouse as well as the sequence
in which data may be changed in the data warehouse.
 Date Controls: The date that the data is applicable for different types of processes. For
example, with accounting data it is the date that the data is officially recorded on the books of
the organization.
 Usage Controls: How data can be used by the users of the data warehouse, including any
restrictions on users forwarding data to other potential users.
 Documentation Controls: How the data within the data warehouse is to be described to
users.

8
Do Procedures: To test a data warehouse, testers should perform the following three tasks:
1. Measure the magnitude of data warehouse concerns.
2. Identify data warehouse activities to test
3. Test the adequacy of data warehouse activity processes

Output: The output from the data warehouse test process is an assessment of the adequacy of
the data warehouse activity processes. The assessment report should indicate the concerns
addressed by the test team, the processes in place in the data warehouse activity, and the
adequacy of those processes.

TESTING WEB-BASED SYSTEMS:


Web-based systems are those systems that use the Internet, intranets, and extranets.
Internet is a worldwide collection of interconnected networks. An intranet is a private network
inside a company using web based applications, but for use only within an organization. An
extranet is a private network that allows external access to customers and suppliers using web-
based applications.

Overview: Web-based architecture is an extension of client/server architecture. The difference


between client/server architecture and web-based architecture is:

In Client/Server architecture, application software resides on the client workstations. The


application server handles processing requests. The back-end processing (typically a mainframe
or super-minicomputer) handles processing such as batch transactions that are accumulated and
processed together at one time on a regular basis. The important distinction to note is that
application software resides on the client workstation.

For web-based systems, the browsers reside on client workstations. These client workstations are
networked to a web server, either through a remote connection or through a network such as a
local area network (LAN) or wide area network (WAN).

As the web server receives and processes requests from the client workstation, requests may be
sent to the application server to perform actions such as data queries, electronic commerce
transactions, and so forth.

The back-end processing works in the background to perform batch processing and handle high-
volume transactions. The back-end processing can also interface with transactions to other
systems in the organization. For example, when an online banking transaction is processed over
the Internet, the transaction is eventually updated to the customer’s account and shown on a
statement in a back-end process.

9
Concerns: Testers should have the following concerns when conducting web-based testing:

 Browser Compatibility: Testers should validate consistent application performance on a


variety of browser types and configurations.
 Functional Correctness: Testers should validate that the application functions correctly.
This includes validating links, calculations, displays of information, and navigation.
 Integration: Testers should validate the integration between browsers and servers,
applications and data, and hardware and software.
 Usability: Testers should validate the overall usability of a web page or a web application,
including appearance, clarity, and navigation.
 Security: Testers should validate the adequacy and correctness of security controls,
including access control and authorizations.
 Performance: Testers should validate the performance of the web application under load.
 Verification of Code: Testers should validate that the code used in building the web
application (HTML, Java, and so on) has been used in a correct manner. For example, no
nonstandard coding practices should be used that would cause an application to function
incorrectly in some environments.

Workbench:

Figure 22-1 illustrates the workbench for web-based testing. The input to the workbench is the
hardware and software that will be incorporated in the web-based system to be tested. The first
three tasks of the workbench are primarily involved in web-based test planning. The fourth task
is traditional software testing. The output from the workbench is to report what works and what
does not work, as well as any concerns over the use of web technology.

10
Input: The input to this test process is the description of web-based technology used in systems
being tested. Following list shows how web-based systems differ from other technologies. The
description of the web-based systems under testing should address these differences:
 Uncontrolled User Interfaces (browsers): Because of the variety of web browsers
available, a web page must be functional on those browsers that you expect to be used in
accessing your web applications. Furthermore, as new releases of browsers emerge, your web
applications will need to keep up with compatibility issues.
 Complex Distributed Systems: In addition to being complex and distributed, web-based
applications are also remotely accessed, which adds even more concerns to the testing effort.
While some applications may be less complex than others, it is safe to say that the trend in
web applications is to become more complex rather than less.
 Security Issues: Protection is needed from unauthorized access that can corrupt applications
and/or data. Another security risk is that of access to confidential information.
 Multiple Layers in Architecture: These layers of architecture include application servers,
web servers, back-end processing, data warehouses, and secure servers for electronic
commerce.
 New Terminology and Skill Sets: Just as in making the transition to client/server, new skills
are needed to develop, test, and use web-based technology effectively.
 Object-Oriented: Object-oriented languages such as Java are the mainstay of web
development.

Do Procedures:

Task 1: Select Web-Based Risks to Include in the Test Plan


 Security.
 Performance
 Correctness
 Compatibility (configuration
 Reliability.
 Data integrity
 Usability.
 Recoverability.
Task 2: Select Web-Based Tests
 Unit or Component
 Integration
 System
 User Acceptance
 Performance
 Load
 Regression
Task 3: Select Web-Based Test Tools
 HTML tools
 Site validation tools
 Load/stress testing tools
 Test case generators
Task 4: Test Web-Based Systems

11
TESTING SOFTWARE SYSTEM SECURITY
Testing software system security is a complex and costly activity. Performing comprehensive
security testing is generally not practical. What is practical is to establish a security baseline to
determine the current level of security and to measure improvements.

Effectiveness of security testing can be improved by focusing on the points where security has
the highest probability of being compromised. A testing tool that has proved effective in
identifying these points is the penetration-point matrix. The security-testing process described in
this topic focuses primarily on developing the penetration-point matrix, as opposed to the
detailed testing of those identified points.

Overview: This test process provides two resources: a security baseline and an identification
of the points in an information system that have a high risk of being penetrated. Neither resource
is statistically perfect, but both have proven to be highly reliable when used by individuals
knowledgeable in the area that may be penetrated. The penetration-point tool involves building a
matrix. In one dimension are the activities that may need security controls; in the other
dimension are potential points of penetration. Developers of the matrix assess the probability of
penetration at various points in the software system at the points of intersection. By identifying
the points with the highest probability of penetration, organizations gain insight as to where
information systems risk penetration the most.

Concerns: There are two major security concerns: Security risks must be identified, and
adequate controls must be installed to minimize these risks.

Workbench: This workbench assumes a team knowledgeable about the information system to
be secured. This team must be knowledgeable about the following:

 Communication networks in use


 Who has access to those networks
 Data or processes that require protection
 Value of information or processes that require protection
 Processing flow of the software system
 Security systems and concepts
 Security-penetration methods

The workbench provides three tasks for building and using a penetration-point matrix (see Figure
20-1). The security-testing techniques used in this workbench are the security baseline and the
penetration-point matrix. The prime purpose of the matrix is to focus discussion on high-risk
points of potential penetration and to assist in determining which points require the most
attention. These techniques can be used by project teams, special teams convened to identify
security risks, or by quality assurance/quality-control personnel to assess the adequacy of
security systems.

12
Input: The input to this test process is a team that is knowledgeable about the information
system to be protected and about how to achieve security for a software system. The reliability of
the results will depend heavily on the knowledge of the individuals involved with the
information system and the specific types of individuals who are likely to penetrate the system at
risk points. The security-testing techniques presented in this topic are simple enough that the
team should not require prior training in the use of the security test tools.

Do Procedures:
This test process involves performing the following three tasks:
1. Establish a security baseline.
2. Build a penetration-point matrix.
3. Analyze the results of security testing.

Check Procedures: The check procedures for this test process should focus on the
completeness and competency of the team using the security baseline process and the
penetration-point matrix, as well as the completeness of the list of potential perpetrators and
potential points of penetration. The analysis should also be challenged

Output: The output from this test process is a security baseline, the penetration-point matrix
identifying the high-risk points of penetration, and a security assessment.

13
DEVELOPING THE TEST PLAN:
The scope of the effort to determine whether software is ready to be placed into production
should be defined in a test plan. To expend the resources for testing without a plan will almost
certainly lead to waste and the inability to evaluate the status of corrections prior to installation.
The test planning effort should follow the normal test planning process, although the content will
vary because it will involve not only in-house developed software but also vendor-developed
software and software embedded into computer chips.

Overview: The test plan describes how testing will be accomplished. Its creation is essential to
effective testing and should take about one-third of the total testing effort. If you develop the
plan carefully, test execution, analysis, and reporting will flow smoothly. Consider the test plan
as an evolving document. As the developmental effort changes in scope, the test plan must
change accordingly. It is important to keep the test plan current and to follow it, for it is the
execution of the test plan that management must rely on to ensure that testing is effective; and it
is from this plan that testers will ascertain status of the test effort and base opinions on its results.

Objective: The objective of a test plan is to describe all testing that is to be accomplished,
together with the resources and schedule necessary for completion. The test plan should provide
background information on the software being tested, test objectives and risks, and specific tests
to be performed. Properly constructed, the test plan is a contract between the testers and the
project team/users. Thus, status reports and final reports will be based on that contract.

Concerns: Concerns testers face in ensuring that test plan will be complete include following:

 Not enough training. The majority of IT personnel have not been formally trained in testing,
and only about half of full-time independent testing personnel have been trained in testing
techniques. This causes a great deal of misunderstanding and misapplication of testing
techniques.

 Us-versus-them mentality. This common problem arises when developers and testers are on
opposite sides of the testing issue. Often, the political infighting takes up energy, sidetracks
the project, and negatively impacts relationships.

 Lack of testing tools. IT management may consider testing tools to be a luxury. Manual
testing can be an overwhelming task. Although more than just tools are needed, trying to test
effectively without tools is like trying to dig a trench with a spoon.

 Lack of management understanding/support of testing. If support for testing does not


come from the top, staff will not take the job seriously and testers’ morale will suffer.
Management support goes beyond financial provisions; management must also make the
tough calls to deliver software on time with defects or take a little longer and do the job right.

 Lack of customer and user involvement. Users and customers may be shut out of the
testing process, or perhaps they don’t want to be involved. Users and customers play one of
the most critical roles in testing: making sure the software works from a business perspective.

14
 Not enough time for testing. This is common complaint. The challenge is to prioritize the
plan to test the right things in the given time.

 Over-reliance on independent testers. Sometimes called the “throw it over the wall”
syndrome. Developers know that independent testers will check their work, so they focus on
coding and let the testers do the testing. Unfortunately, this results in higher defect levels and
longer testing times.

 Rapid change. In some technologies, especially rapid application development (RAD), the
software is created and/or modified faster than the testers can test it. This highlights the need
for automation, but also for version and release management

 Testers are in a lose-lose situation. On the one hand, if the testers report too many defects,
they are blamed for delaying the project. Conversely, if the testers do not find the critical
defects, they are blamed for poor quality.

 Having to say no. The single toughest dilemma for testers is to have to say, “No, the
software is not ready for production.” Nobody on the project likes to hear that, and
frequently, testers succumb to the pressures of schedule and cost.

Input: Accurate and complete inputs are critical for developing an effective test plan. The
following two inputs are used in developing the test plan:

 Project plan. This plan should address the totality of activities required to implement the
project and control that implementation. The plan should also include testing.

 Project plan assessment and status report. This report (developed from Step 1 of the
seven-step process) evaluates the completeness and reasonableness of the project plan. It also
indicates the status of the plan as well as the method for reporting status throughout the
development effort.

Do Procedures:

The following six tasks should be completed during the execution of this step:
1. Profile the software project.
2. Understand the software project’s risks.
3. Select a testing technique.
4. Plan unit testing and analysis.
5. Build the test plan.
6. Inspect the test plan.