Date: 24-May-22

WAFA Field - Flash Daily Report Countdown to Completion: 15 Days


Export Gas A Unit Shutdown Overall Progress: 12%

01). Progress Overview


Export A Major Overhaul (C-Level Inspection) Vessels Inspection
Progress: 10.07% 14.00%
WF: 60% 40%

02). Highlights & Concerns (Deviations, Interruptions, Hindrances) 03). Key Milestone
1). MT001A: GG has been removed to Workshop. Plan Actual
Description
2). HC001A: Inspection of 1st stage discharge cooler is ongoing. Start Finish Start Finish
3). HC002A: Inspection of 2nd stage discharge cooler commenced. Export Gas A Unit Shutdown Activities: 19-May-22 8-Jun-22 19-May-22
4). Turbine C Level Inspection 19-May-22 8-Jun-22 19-May-22
5). Vessels Inspection 23-May-22 7-Jun-22 23-May-22

04). Activities Performed 05). Activities Planned Next Day (Look-ahead)


No. Activity Description Start Date Status % Comp No. Activity Description
1 MT001A: Disconnect & transport GG to Workshop 19-May-22 Completed 100% 1 MT001A: Disassembly of GG and inspection of parts.
2 MT001A: Disasembly of GG 23-May-22 Ongoing 6% 2 HC001A: Reinstall plugs and removed blinds.
3 MT001A: Inspection of parts 21-May-22 Ongoing 9% 3 HC002A: Preliminary inspection and cleaning.
4 MT001A: Stationary and precommissioning 21-May-22 Ongoing 9% 4
5 HC001A: Internal cleaning & inspection 23-May-22 Ongoing 70% 5
6 HC002: Internal cleaning & inspection 24-May-22 Ongoing 25% 6
7 7
8 8
9 9
10 10

06). Turbine C-Level Inspection 07). Vessels Inspection


Curve

Planned Daily Actual Daily Planned Accrued Actual Accrued Planned Daily Actual Daily
100 4.5 Planned Accrued Actual Accrued

90 4 100 14
90
"S"

80 3.5 12
80
70
3 10
70
Actual

60
2.5 60
50 8
2 50
40 6
40
1.5
30
30 4
20 1
VS

20
10 0.5 2
10
Plan

0 0 0 0
19-May
20-May
21-May
22-May
23-May
24-May
25-May
26-May
27-May
28-May
29-May
30-May
31-May
1-Jun
2-Jun
3-Jun
4-Jun
5-Jun
6-Jun
7-Jun
8-Jun